ZB 22 13 2023 04 05 Traffic Impact Study Rev 1

Preserved file SHA-2564edff3c0d91100b3ecb43d093934664b85fdf3094a4ed5d2ef1d450c058f5ed2

Indexed text

Page 31

0.1 0.1 Control Delay (s/veh) 8.9 0.0 9.5 0.2 12.5 26.5 Level of Service (LOS) A A A A B D Approach Delay (s/veh) 0.0 0.4 12.5 26.5 Approach LOS A A B D Copyright © 2023 University of Florida. All Rights Reserved. HCS™ TWSC Version 2023 Generated: 3/28/2023 4:15:36 PM FB PM - Eagle Rock Ave & Rosney Terr-Dway.xtw

Page 32

HCS Two-Way Stop-Control Report General Information Site Information Analyst CGH Intersection Eagle Rock & E. Site Dway Agency/Co. Dynamic Traffic Jurisdiction Essex County Date Performed 3/28/2023 East/West Street Eagle Rock Avenue Analysis Year FB North/South Street East Site Driveway Time Analyzed PM PSH Peak Hour Factor 0.97 Intersection Orientation East-West Analysis Time Period (hrs) 0.25 Project Description 1021-99-025T Lanes Major Street: East-West Vehicle Volumes and Adjustments Approach Eastbound Westbound Northbound Southbound Movement U L T R U L T R U L T R U L T R Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12 Number of Lanes 0 0 2 0 0 0 2 0 0 1 0 0 0 0 Configuration T TR LT T LR Volume (veh/h) 760 7 28 635 33 26 Percent Heavy Vehicles (%)

Page 32

760 7 28 635 33 26 Percent Heavy Vehicles (%) 0 2 2 Proportion Time Blocked Percent Grade (%) 0 Right Turn Channelized Median Type | Storage Undivided Critical and Follow-up Headways Base Critical Headway (sec) 4.1 7.5 6.9 Critical Headway (sec) 4.10 6.84 6.94 Base Follow-Up Headway (sec) 2.2 3.5 3.3 Follow-Up Headway (sec) 2.20 3.52 3.32 Delay, Queue Length, and Level of Service Flow Rate, v (veh/h) 29 61 Capacity, c (veh/h) 838 258 v/c Ratio 0.03 0.24 95% Queue Length, Q₉₅ (veh) 0.1 0.9 Control Delay (s/veh) 9.4 0.4 23.2 Level of Service (LOS) A A C Approach Delay (s/veh) 0.7 23.2 Approach LOS A C Copyright © 2023 University of

Page 32

23.2 Approach LOS A C Copyright © 2023 University of Florida. All Rights Reserved. HCS™ TWSC Version 2023 Generated: 3/28/2023 4:14:25 PM FB PM - Eagle Rock Ave & East Site Driveway.xtw

Page 33

HCS Two-Way Stop-Control Report General Information Site Information Analyst CGH Intersection Eagle Rock & W. Site Dway Agency/Co. Dynamic Traffic Jurisdiction Essex County Date Performed 3/28/2023 East/West Street Eagle Rock Avenue Analysis Year FB North/South Street West Site Driveway Time Analyzed PM PSH Peak Hour Factor 0.97 Intersection Orientation East-West Analysis Time Period (hrs) 0.25 Project Description 1021-99-025T Lanes Major Street: East-West Vehicle Volumes and Adjustments Approach Eastbound Westbound Northbound Southbound Movement U L T R U L T R U L T R U L T R Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12 Number of Lanes 0 0 2 0 0 0 2 0 0 0 1 0 0 0 Configuration T TR LT T R Volume (veh/h) 760 29 7 661 7 Percent Heavy Vehicles (%)

Page 33

760 29 7 661 7 Percent Heavy Vehicles (%) 0 2 Proportion Time Blocked Percent Grade (%) 0 Right Turn Channelized No Median Type | Storage Undivided Critical and Follow-up Headways Base Critical Headway (sec) 4.1 6.9 Critical Headway (sec) 4.10 6.94 Base Follow-Up Headway (sec) 2.2 3.3 Follow-Up Headway (sec) 2.20 3.32 Delay, Queue Length, and Level of Service Flow Rate, v (veh/h) 7 7 Capacity, c (veh/h) 822 594 v/c Ratio 0.01 0.01 95% Queue Length, Q₉₅ (veh) 0.0 0.0 Control Delay (s/veh) 9.4 0.1 11.1 Level of Service (LOS) A A B Approach Delay (s/veh) 0.2 11.1 Approach

Page 33

A B Approach Delay (s/veh) 0.2 11.1 Approach LOS A B Copyright © 2023 University of Florida. All Rights Reserved. HCS™ TWSC Version 2023 Generated: 3/28/2023 4:16:16 PM FB PM - Eagle Rock Ave & West Site Driveway.xtw

Page 34

HCS Two-Way Stop-Control Report General Information Site Information Analyst CGH Intersection Eagle Rock & Rosney/Dway Agency/Co. Dynamic Traffic Jurisdiction Essex County Date Performed 3/28/2023 East/West Street Eagle Rock Avenue Analysis Year FB North/South Street Rosney Terrace/Driveway Time Analyzed SAT PSH Peak Hour Factor 0.95 Intersection Orientation East-West Analysis Time Period (hrs) 0.25 Project Description 1021-99-025T Lanes Major Street: East-West Vehicle Volumes and Adjustments Approach Eastbound Westbound Northbound Southbound Movement U L T R U L T R U L T R U L T R Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12 Number of Lanes 0 0 2 0 0 0 2 0 0 1 0 0 1 0 Configuration LT TR LT TR LTR LTR Volume (veh/h) 1 715 8 15 684 0 6 0 11 3

Page 34

LTR Volume (veh/h) 1 715 8 15 684 0 6 0 11 3 0 1 Percent Heavy Vehicles (%) 0 0 0 0 0 0 0 0 Proportion Time Blocked Percent Grade (%) -2 2 Right Turn Channelized Median Type | Storage Undivided Critical and Follow-up Headways Base Critical Headway (sec) 4.1 4.1 7.5 6.5 6.9 7.5 6.5 6.9 Critical Headway (sec) 4.10 4.10 7.10 6.10 6.70 7.90 6.90 7.10 Base Follow-Up Headway (sec) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3 Follow-Up Headway (sec) 2.20 2.20 3.50 4.00 3.30 3.50 4.00 3.30 Delay, Queue Length, and Level of Service Flow Rate, v (veh/h) 1 16 18 4 Capacity, c (veh/h) 891 860 326 168 v/c Ratio 0.00 0.02 0.05 0.03 95% Queue Length, Q₉₅ (veh) 0.0 0.1 0.2 0.1 Control Delay (s/veh) 9.0 0.0 9.3 0.2

Page 34

0.2 0.1 Control Delay (s/veh) 9.0 0.0 9.3 0.2 16.7 27.0 Level of Service (LOS) A A A A C D Approach Delay (s/veh) 0.0 0.4 16.7 27.0 Approach LOS A A C D Copyright © 2023 University of Florida. All Rights Reserved. HCS™ TWSC Version 2023 Generated: 3/28/2023 4:18:08 PM FB SAT - Eagle Rock Ave & Rosney Terr-Dway.xtw

File revisions (1)