Page 331

(b) Diligent Pursuit of Governmental Approvals. Redeveloper agrees to prosecute all of Redeveloper’s applications for Governmental Approvals diligently and in good faith, and in accordance with the Project Schedule. Subject to the requirements of Applicable Law, Redeveloper shall determine when and in what order to file each specific application. At Redeveloper’s reasonable request, the Township will, in its reasonable judgment, sign consents or other documents required in connection with Redeveloper’s applications for Governmental Approvals and will supply information which is in the Township’s possession. The Township will, in its reasonable judgment, otherwise cooperate with and support Redeveloper in connection with the applications for Governmental Approvals as Redeveloper and Redeveloper’s counsel may reasonably request. (c) Appeals. If (i) one or more of Redeveloper’s Applications for Governmental Approvals is denied, or approved with conditions that Redeveloper in its commercially reasonable judgment deems unacceptable, or (ii) anyone contests or challenges the grant of such Governmental Approval to Redeveloper, then unless the Township consents in advance to a different course of action Redeveloper may appeal or defend against such action, and during the pendency of the appeal proceeding otherwise continue as Redeveloper deems appropriate to seek the remaining Governmental Approvals. If Redeveloper determines not to appeal or defend against such action as set forth above, it may terminate this Agreement upon thirty (3) days notice to the Township and the Parties shall have no further rights or obligation to each other hereunder. (d) Application for Site Plan Approval. Each Governmental Application submitted by or on behalf of the Redeveloper in connection with the Redevelopment Project shall conform in all material respects to the Redevelopment Plan and all Applicable Laws; provided, however, that nothing herein shall be construed as limiting the Redeveloper’s ability to apply for reasonable bulk or area variances or waivers as may necessary or appropriate under the circumstances and in accordance with the applicable provisions of the Redevelopment Plan. 4.8 Commencement and Completion Schedule. The Redeveloper agrees to Commence Construction and diligently Complete Construction of the Project, and failure to do so shall be a Default by Redeveloper.

Page 331

. 4.8 Commencement and Completion Schedule. The Redeveloper agrees to Commence Construction and diligently Complete Construction of the Project, and failure to do so shall be a Default by Redeveloper. Subject to the provisions of this Agreement with respect to Force Majeure and the applicable provisions of Section 5.2, if any, any material change in the scope of the Project (including changes in the Project budget if relevant to the calculation of the PILOT), changes or updates to the Project Schedule, or extension of the projected Completion Date, shall require the Township’s prior written approval, which the Township will not unreasonably withhold. Redeveloper agrees to simultaneously provide to the Township copies of all project pro formas, Project Schedules and budgets that Redeveloper submits to actual or potential lenders or investors in connection with the financing of the Project, to the extent that they are materially different from those previously supplied to the Township by Redeveloper. The Redeveloper understands that absent extraordinary and unforeseeable circumstances the Township will require Redeveloper’s adherence to the schedule for Commencement of Construction and Completion of Construction, interim deadlines or milestones and time periods for the various activities and actions to be taken by the Redeveloper hereunder, subject only to the occurrence of a Force Majeure Event. 20 4839-2360-2911, v. 3

Page 332

4.9 Plans and Specifications. Redeveloper hereby agrees that following an Event of Default the Township and anyone acting on the Township’s behalf shall have an irrevocable license to use Redeveloper’s Plans and Specifications, Governmental Applications, and Governmental Approvals to complete the Project, without cost to or liability of the Township (other than for actual services rendered to the Township subsequent to the Event of Default) and agrees to use best efforts to ensure that all agreements between Redeveloper and its contractors and consultants shall so provide. Redeveloper shall be compensated for such Plans and Specifications as provided in Section 10.8. In addition, all performance or completion bonds provided by Redeveloper’s contractors shall name the Township as an intended beneficiary thereof, as its interests may appear, unless Redeveloper’s construction lender objects in writing and for good cause to the inclusion of the Township. 4.10 Progress Reports and Project Oversight by the Township. During the implementation of the Project, the Redeveloper shall make periodic Progress Reports, no less frequently than on February 1 and August 1 and at such other times as may be reasonably requested by the Township, in such detail as may reasonably be requested by the Township, as to the actual progress of Redeveloper and which shall include, among other things, a description of activities completed, milestones achieved, status of the Project with respect to the Project Schedule, activities to be undertaken prior to the next regularly scheduled Progress Report, and any unanticipated problems or delays and the explanation therefor. If Redeveloper fails to meet a milestone or completion date set out in the Project Schedule and is notified of same in writing by the Township, or if Redeveloper conclusively determines between Progress Reports that it will fail to meet a milestone or completion date on the Project Schedule, Redeveloper shall promptly provide written notice to Township stating: (a) the reason for the failure to complete the applicable task, (b) Redeveloper’s proposed method for correcting such failure, (c) Redeveloper’s schedule for completing such task, and (d) the method or methods by which Redeveloper proposes to achieve subsequent tasks by the Completion Date. This Section shall not in any way be construed as entitling Redeveloper to

Page 332

ng such task, and (d) the method or methods by which Redeveloper proposes to achieve subsequent tasks by the Completion Date. This Section shall not in any way be construed as entitling Redeveloper to an extension of the Completion Date or modification of the Project Schedule or Project budget, absent the Township’s prior written consent. Redeveloper acknowledges and agrees that time is of the essence in providing the Progress Reports to the Township in accordance with this Section. 4.11 Certificate of Occupancy and Certificate of Completion. Redeveloper shall apply to the appropriate governmental officer or body for a Certificate of Occupancy, as required under Applicable Laws. Following the issuance of all required Certificates of Occupancy and the satisfaction of the terms and conditions of this Redevelopment Agreement with respect to the applicable Phase of the Project by Redeveloper, and upon receipt of a Notice of Completion from Redeveloper, the Township agrees to issue and not unreasonably withhold a Certificate of Completion, in proper form for recording, which shall acknowledge that the Redeveloper has performed all of its duties and obligations under this Redevelopment Agreement and has completed construction of the applicable Phase of the Project in accordance with the requirements of this Redevelopment Agreement. Within 30 days after receipt of the Notice of Completion from the Redeveloper, the Township shall provide the Redeveloper with the Certificate of Completion or a written statement setting forth in detail the reasons why it believes that Redeveloper has failed to complete the Project in accordance with the provisions of this 21 4839-2360-2911, v. 3

Page 333

Redevelopment Agreement or is otherwise in default under this Agreement, and what reasonable measures or acts will be necessary in the opinion of the Township in order for the Redeveloper to be entitled to the Certificate of Completion. If there is a dispute as to the Completion of the applicable phase of the Project between the Redeveloper and Township, the Township agrees to issue a Certificate of Completion with conditions that if satisfied by the Redeveloper shall convert the conditional Certificate of Completion to a final one for the applicable phase of the Project so as not to delay or interfere with the Redeveloper’s ability to secure permanent financing for the Project. When issued the Certificate of Completion shall constitute a recordable, conclusive determination of the satisfaction and termination of the agreements and covenants (as limited herein) in this Redevelopment Agreement and the Redevelopment Plan with respect to the obligations of the Redeveloper to construct the Project or relevant Phase, as well as a determination by the Township that the conditions that were found and determined to exist at the time the Redevelopment Area was determined to be in need of redevelopment shall be deemed to no longer exist and the conditions and requirements of N.J.S.A. 40A:12A-9 shall be deemed to have been satisfied with respect to the Redevelopment Project or applicable Phase thereof. Unless otherwise required by a related Financial Agreement, Governmental Approval or Applicable Law, upon the issuance of Certificate of Completion the provisions of this Agreement shall no longer encumber the applicable Phase of the Project; provided, however, that any other documents theretofore delivered pursuant to this Agreement that by their terms are intended to survive Completion of Construction (including, without limitation and by of example only, any deed restrictions, the Declaration of Restrictions, tax exemption agreements, etc.) shall not be affected by delivery of the Certificate of Completion except as otherwise expressly provided therein. 4.12 Estoppel Certificates (Prior to Certificate of Completion). At any time and from time to time prior to the issuance of a Certificate of Completion, the Township shall, within thirty (30) days following a written request by Redeveloper, execute and deliver to (a) Redeveloper, or (b) a third party (e.g., a

Page 333

e issuance of a Certificate of Completion, the Township shall, within thirty (30) days following a written request by Redeveloper, execute and deliver to (a) Redeveloper, or (b) a third party (e.g., a prospective lender, purchaser, investor, tenant, etc.) designated by Redeveloper, an instrument in which the Township (i) certifies that this Agreement is unmodified and in full force and effect as to the Project (excepting only modifications which shall be set forth), and (ii) states whether to the actual knowledge of the Township Redeveloper is in default under this Agreement, and, if so, specifying each such default of which the Township shall have knowledge. 4.13 Escrow Account to Cover Township Costs. (a) The Redeveloper covenants and represents that it will make timely payment or reimbursement to the Township for all Township Costs. The Redeveloper has established with the Township an escrow account (the “Escrow Account”) to cover Township Costs. From time to time during the implementation of the Project and until issuance of a final Certificate of Completion the Redeveloper agrees to replenish the Escrow Account upon the written request of the Township, to provide for a sufficient balance, as determined by the Township in its reasonable judgment, to cover anticipated Township Costs. (b) The Escrow Deposit is separate from and in addition to all other application fees and escrow deposits that may be required by the Township in connection with applications for land use approvals to implement the Redevelopment Plan. Additions to the Escrow Deposit may subsequently become necessary to cover all reimbursable expenses incurred by the Township 22 4839-2360-2911, v. 3

Page 334

pursuant to the terms of this Agreement. (c) The Escrow Deposit and all additions thereto shall be held by the Escrowee in a banking institution or savings and loan association in the State of New Jersey insured by an agency of the federal government, or in any other fund or depository approved for such deposits by the State of New Jersey, in a segregated, non-interest-bearing account referenced to the Redevelopment Agreement. (d) The Escrowee shall use the Escrow Deposit and all additions thereto to pay Township Costs in accordance with the provisions of the Redevelopment Agreement. Township Costs paid out of the Escrow Account shall include all Township Costs as defined in the Redevelopment Agreement. Each payment for professional services charged to the Escrow Account shall be pursuant to a voucher from the professional or consultant, identifying the personnel performing the reimbursable service, each date the services were performed, the hours spent in not greater than one-quarter (1/4) hour increments, the hourly rate, and specifying in reasonable detail the properly reimbursable expenses. All professionals shall submit the required vouchers or statements to the Escrowee on a monthly basis in accordance with the schedule and procedures established by the Escrowee. The professional shall simultaneously send an informational copy of each voucher or statement submitted to the Escrowee to the Redeveloper (redacted as necessary to remove confidential and privileged information). (e) At least annually during the term of the Redevelopment Agreement, or as reasonably requested by the Redeveloper (but not more often than quarterly), Escrowee shall prepare and send to the Redeveloper a statement which shall include an accounting of funds listing all deposits, interest earnings, disbursements and the cumulative balance of the Escrow Account. If at any time the balance in the Escrow Account is less than Twenty-Five Thousand Dollars ($25,000.00), or if the Escrow Account in the Township’s reasonable estimation for good cause shown otherwise contains insufficient funds to enable the Township to continue performance of its obligations under the Redevelopment Agreement, the Escrowee shall provide Redeveloper with a notice of the insufficient Escrow Account balance and the amount of additional funds required. Upon receipt of such notice Redeveloper shall deposit to the

Page 334

he Escrowee shall provide Redeveloper with a notice of the insufficient Escrow Account balance and the amount of additional funds required. Upon receipt of such notice Redeveloper shall deposit to the escrow account additional funds such that the total amount on deposit shall be not less than Fifty Thousand Dollars ($50,000.00), such deposit to be made within fifteen (15) business days of the Township’s notice, failing which the Township may unilaterally cease work without liability to Redeveloper. (f) Upon the issuance of a Certificate of Completion the Redeveloper shall send written notice by certified mail to the Escrowee requesting that the remaining balance of the Escrow Deposit be refunded, or otherwise applied in accordance with the provisions of the Redevelopment Agreement. After receipt of such notice, and within 30 days of Escrowee’s receipt of all outstanding invoices for Township Costs, if any, the Escrowee shall pay all outstanding Township Costs and render a written final accounting to the Redeveloper. (g) Redeveloper may dispute the propriety or reasonableness of Township Costs paid out of the Escrow Deposit by written notice to the Escrowee. A copy of such notice shall be sent simultaneously to any the entity(ies) whose charges or estimated costs are the subject of the 23 4839-2360-2911, v. 3

Page 335

dispute. Such written notice of a disputed charge shall be given within 45 days from Redeveloper’s receipt of the informational copy of a voucher or invoice, statement, bill or invoice, except that if Redeveloper has not received an informational copy then the Redeveloper shall send notice within 60 days from receipt of the first statement of activity against the Escrow Account containing the disputed charge. Failure to dispute a charge in writing within the prescribed time shall constitute Redeveloper’s acceptance of the charge and a waiver by Redeveloper of all objections to the charge and to payment thereof out of the Escrow Account. During the pendency of a dispute the Escrowee may continue to pay undisputed charges out of the Escrow Account. If a dispute over a charge is resolved in Redeveloper’s favor after having been paid, the Escrowee shall reimburse the Escrow Account in the amount determined to be properly disputed. 4.14 Shuttle Service. A shuttle from within the Project to the Essex Green Bus Stop shall be provided by the Redeveloper to coordinate with the Jitney and to provide access to the shopping center and bus at other times of the day. 4.15 Public Improvements Contribution. Redeveloper shall remit to the Township Five Hundred Thousand Dollars ($500,000.00) to be used by the Township for public improvements. The payment shall be made by Redeveloper to the Township at Closing Date One. The specific public improvements to be funded by the payment shall be at the sole discretion of the Township. ARTICLE V REDEVELOPER PROTECTIONS 5.1 Redevelopment Plan Amendments. The Township agrees that prior to Commencement of Construction of the last Phase of the Project the Township will not amend the Redevelopment Plan with respect to the Property or otherwise impair this Agreement without Redeveloper’s prior consent. 5.2 Impossibility of Performance; Changed Market Conditions. Notwithstanding the Redeveloper’s right to terminate this Agreement prior to Closing on the acquisition of the Property or any other rights to terminate the Agreement set forth herein, Redeveloper’s failure or refusal to develop a particular Phase of the Project shall not constitute a Default by Redeveloper in the performance of its obligations hereunder if such failure or refusal is for the following reasons and on the following terms and conditions: (a) Subject to the provisions

Page 335

Default by Redeveloper in the performance of its obligations hereunder if such failure or refusal is for the following reasons and on the following terms and conditions: (a) Subject to the provisions of Section 5.2(c) below, Redeveloper’s failure or refusal to develop a particular Phase of the Project shall not constitute a default hereunder if due to physical impossibility of performance or economic infeasibility due to the condition of the property or to regulatory restrictions relating to the condition of the property. By way of example, “physical impossibility of performance” would be an irremediable environmental condition. An example of “economic infeasibility” would be a cost of Remediation of an environmental condition that would significantly and adversely affect the 24 4839-2360-2911, v. 3