2544-18 (2017-2018-2019) STREET RESURFACING LISTVersion 1 Oct 12 2017 (002).pdf

Preserved file SHA-256a57810cf1afbac986c052b6f2b5d3644bc0acc1d0e90fd1aa01f0ac7b98b7d6e

Indexed text

Page 1

2017, 2018 AND 2019 STREET RESURFACING LIST, VERSION 1, OCTOBER 12, 2017 REVISED JANUARY 8, 2018 2016 STREET RESURFACING LIST TO BE COMPLETED OCTOBER AND NOVEMBER 2017 1. Spring Hill Drive, Fernwood Circle, Cherrywood Circle Curb, Aprons and Drainage complete; milling and resurfacing week of October 16 or October 23 2. Ralph Road, Manger Road to Manger Road Curb and Aprons to begin week of October 16, milling and paving November 2017 2017 PHASE III STREET RESURFACING LIST TO BE STARTED FALL 2017 AND COMPLETED BY SUMMER 2018 1. Manger Road, Ralph Rd to McGuire Drive – curb, aprons, mill & pave 2. Lorelei Road – curb, aprons, mill & pave 3. Carolina Avenue – curb, aprons, mill & pave. 4. Roosevelt Avenue, Elmwood Avenue to Lorelei Rd Curb, aprons, mill and pave, Speed Tables, four 5. Elmwood Avenue - mill and pave, drainage 6. Westwood Drive North – curb, aprons, mill & Pave 7. Westwood Drive South – curb, aprons, mill & pave 8. Garfield Avenue, Shelly Terrace to dead end – curb, aprons, mill & pave 9. Shelly Terrace – curb, aprons, mill & pave 10. Calvin Terrace - curb, aprons, mill & pave 11. Parkside Avenue – curb, aprons, mill & pave CONTRACT AMOUNT $ 1,755,182.37 2017 PHASE IV STREET RESURFACING LIST TO BE STARTED FALL 2017 AND COMPLETED BY SUMMER 2018 1. Mountain Way – curb, aprons, mill & pave - Started October 12, Completion November 2017 2. Mountain Way South- curb, aprons, mill & pave – Started October 12, Completion November 2017 3. Devon Drive - curb, aprons, mill & pave – Started October 12, Completion November 2017 4. Sylvan Place – curb, aprons, mill & pave – Started October 12, Completion November 2017

Page 2

5. Connel Drive - curb, aprons, mill & pave 6. Powell Drive - curb, aprons, mill & pave 7. Stone Drive - curb, aprons, mill & pave 8. Weber Road - curb, aprons, mill & pave 9. Tornillo Road - curb, aprons, mill & pave 10. Essex Terrace – curb, aprons, mill & pave 11. Undercliff Terrace, Walker Road north to dead end – curb, aprons, mill & pave 12. Birchwood Avenue cul de sac – curb, aprons, mill & pave CONTRACT AMOUNT $ 2,055,200.72 2017 PHASE II STREET IMPROVEMENTS, TO BE STARTED AND COMPLETED SPRING 2018 20. Chestnut Street, Franklin Avenue to Harrison Avenue - curb, aprons, mill & pave $216,000 1,200 L.F. @180/L.F. 21. Elm Street, Franklin Avenue to Harrison Avenue - curb, aprons, mill & pave $180,000 1,000 L.F. @ $180/L.F. 22. Roosevelt Avenue, Lincoln Avenue north to dead end – curb, aprons, mill & pave 860 L.F. @ $180/L.F. $154,800 23. Samuel Street – curb, aprons, sidewalks, mill & pave 500 L.F. @ $235/L.F. $117,500 24. Chestnut Street, Whittlesey Avenue to Watchung Avenue curb, aprons, sidewalks, mill & pave 660 L.F. @ $235/L.F. $155,100 25. Ridge Avenue, Whittlesey Avenue to Watchung Avenue Curb, aprons, sidewalks, mill & pave 660 L.F. @ $235/L.F. $155,100 TOTAL $978,500 2017 STREET IMPROVEMENTS, PHASE I, WINDING WAY, SHEFFIELD TERRACE TO DEAD END TO BE COMPLETED FALL 2017 New Drainage system, new granite block curb, new full depth asphalt pavement

Page 3

2018 PHASE I STREET IMPROVEMENTS, TO BE STARTED SPRING 2018 AND COMPLETED SUMMER 2018 1. Curtis Avenue and Garfield Avenue from Curtis Avenue to Hoover Avenue Storm sewer, curb, aprons, sidewalks, mill & pave $613,000 2018 PHASE II STREET IMPROVEMENTS, TO BE STARTED SUMMER 2018 AND COMPLETED SUMMER 2019 1. Whittingham Place (mill and pave) $120,000 1,000 L.F. @ $120/L.F. 2. Rollinson Street, Northfield Avenue to Mitchell Street, curb & aprons one side, $285,000 mill & pave 1,900 L.F. @ $150/L.F. 3. Longview Street - curb, aprons, mill & pave $225,000 1,250 L.F. @ 180/L.F. 4. Randolph Place - curb, aprons, mill & pave $207,000 1,150 L.F. @ $180/L.F. 5. Marion Drive - curb, aprons, mill & pave, sidewalk one side $214,500 1,300 L.F. @ $165/L.F. Sidewalk $ 40,000 6. Barone Road – curb, aprons, mill & pave $126,000 700 L.F. @ $180/L.F. 7. Phyllis Road - curb, aprons, mill & pave $297,500 1,700 L.F. @ $175/L.F. 8. Marshall Street - curb, aprons, mill & pave $113,400 630 L.F. @ $180/L.F. 9. Westminster Terrace – curb, aprons, mill & pave 870 L.F. @ $180/L.F. $156,600 10. Devonshire Terrace – curb, aprons, mill & pave 1,010 L.F. @ $180/L.F. $181,800 11. Cheshire Terrace – curb, aprons, mill & pave 930 L.F. @ $180/L.F. $167,400 12. Nottingham Road – curb, aprons, mill & pave 720 L.F. @ $180/L.F. $129,600 13. Barbara Avenue – curb, aprons, mill & pave 710 L.F. @ $180/L.F. $127,800

Page 4

14. Waddington Avenue – curb, aprons, mill & pave 1,850 L.F. @ $180/L.F. $333,000 15. Syme Avenue – curb, aprons, mill & pave 860 L.F. @ $180/L.F. $154,800 16. Kirk Street (Harrison Avenue to Franklin Avenue) curb, aprons, mill & pave 700 L.F. @ $180/L.F. $126,000 17. Maple Street (Harrison Avenue to Franklin Avenue) Curb, aprons, mill & pave 870 L.F. @ $180/L.F. $156,600 18. Lessing Road (Edgewood Avenue to Highland Blvd) Curb, aprons, mill & pave 750 L.F. @ $180/L.F. $135,000 19. Walker Road (Undercliff Terrace South to Lower Burnett Terr) Mill and pave 1,550 L.F. @ $120/L.F. $186,000 20. Crestwood Drive Curb, aprons, mill and pave 1,160 L.F. @ $180/L.F. $208,000 21. Greenwood Avenue Curb, aprons, mill and pave 1,750 L.F. @ $180/L.F. $315,000 3 speed tables @ $5,000 each $ 15,000 TOTAL $4,021,800 2018 PHASE III STREET IMPROVEMENTS START SUMMER 2018 COMPLETE FALL 2018 Lessing Road, St. Cloud Avenue to Highland Boulevard New Curb, aprons, mill & pave 2,650 L.F. 1 $190 / L.F. $503,500

Page 5

2018 PHASE IV STREET IMPROVEMENTS START FALL 2018 COMPLETE FALL 2018 Meade Street Some curb and sidewalk, mill and pave $120,000 Columbia Street Some curb and sidewalk, mill and pave $180,000 2018 PHASE V STREET IMPROVEMENTS WINDING WAY PHASE II, LOWELL AVENUE TO SHEFFIELD TERRACE START FALL 2018, COMPLETE FALL 2018 New Drainage System, new curb, new full depth asphalt pavement $350,000 2018 PHASE VI STREET IMPROVEMENTS UPPER MELLON AVENUE $275,000 2019 AND 2020 STREET IMPROVEMENTS Kenz Terrace Mellon Avenue (lower) Rand Drive Parson Drive Thorn Terrace Dunn Road Mann Avenue Nicholas Avenue (Redwood Avenue to Terrace Avenue) Kingwood Road Glenview Drive Hillcrest Avenue (Maple Avenue to Springhill Drive) Ash Avenue Mitchell Street (Valley Road to Orange line)

Page 6

Stockman Street Tompkins Street Renna Plaza OTHER STREET IMPROVEMENTS Curtis Avenue and Garfield Avenue from Curtis Avenue to Hoover Avenue (NJDOT Grant, partial) Samuel Street (CDBG) Chestnut Street, Whittlesey Avenue to Watchung Avenue (CDBG) Ridge Avenue, Whittlesey Avenue to Watchung Avenue (CDBG, partial) “Upper” Mellon Avenue and Cleveland Terrace from Mellon Avenue to Hoover Avenue OTHER STREET IMPROVEMENTS – 2018 Lessing Road, St. Cloud Avenue to Edgewood Avenue (NJDOT Grant, partial) Meade Street (CDBG) Columbia Street (CDBG) Kenz Terrace

Page 7

Barbara Avenue Mellon Avenue (lower) Rand Drive Parson Drive Thorn Terrace Dunn Road Mann Avenue Nicholas Avenue (Redwood Avenue to Terrace Avenue) Westminster Terrace Devonshire Terrace Cheshire Terrace Nottingham Road Waddington Avenue Syme Avenue Kingwood Road Glenview Drive Hillcrest Avenue (Maple Avenue to Spring Hill Drive) Ash Avenue Mitchell Street (Valley Road to Orange line) Stockman Street Tompkins Street Renna Plaza Kirk Street (Harrison Avenue to Franklin Avenue) Maple Street (Harrison Avenue to Franklin Avenue)