Supporting Documentation · Aug 7, 2018

188-18 Attachment.pdf

Preserved file SHA-256737dfa5855e03e5a53ad6d8dec78a44a9c2ffef216c22dddbe3795a3b7cfee49

Indexed text

Page 1

CHANGE ORDER NO. I PROJECT: 2017 STREET IMPROVEMENTS, PHASE III CONTRACTOR: REGGIO CONSTRUCTION, INC. 1575 WEST STEEET FORT LEE, NEW JERSEY 07024 ADDITIONAL WORK AUTHORIZED TO COMPLETE PROJECT REASON FOR INCREASE – ADDITIONAL AS-BUILT QUANTITIES ADDITIONAL AMOUNT $ 60,616.22 ORIGINAL CONTRACT AMOUNT $1,755,200.20 ADJUSTED CONTRACT AMOUNT $1,815,816.42 PERCENTAGE INCREASE 3.45% RECOMMENDED BY MUNICIPAL ENGINEER ______________________________ LEONARD R. LEPORE AGREED TO BY CONTRACTOR ______________________________ REGGIO CONSTRUCTION, INC. APPROVED BY OWNER ______________________________ TOWNSHIP OF WEST ORANGE AUTHORIZED BY RESOLUTION NO. DATED:

File revisions (1)