ient shall not proceed with any design work for which reimbursement shall be sought without the specific written authorization of the State. It is agreed that any and all Project Costs incurred by the Subrecipient prior to the execution of this Agreement by all parties shall be non-participating by the State and FHWA.
October 2024 New Jersey Department of Transportation Division of Local Aid and Economic Development Federal Aid Cost Reimbursement Agreement 7 5.2.5 Subrecipient shall submit to the State documentation of the consultant selection process or use of in-house forces and final negotiated consultant cost proposal. In order to use in-house staff for design work, Subrecipient must allow the State to review its project accounting systems and be cost-basis approved by the State. 5.2.6 If Subrecipient is not performing design work in-house, Subrecipient shall solicit proposals in accordance with Section 3.8 of this Agreement. Upon receipt of proposals from responsible design consultants, Subrecipient shall select professional services based upon qualifications and shall furnish the name of such consultant to the State for concurrence. Subrecipient agrees not to contract with any consultant to whom the State has made a reasonable and timely objection. 5.2.7 If the design consultant is to be retained for construction engineering purposes during the construction phase, contracts with design consultants shall include stipulations on retaining the designer for that purpose during which the negotiated cost of the construction engineering activity should be part of the construction contract. 5.2.8 Subrecipient or its consultant shall be required to submit a design schedule to the State which should include, at a minimum, the submission dates for Project plans and descriptions for NEPA determination, environmental screening, environmental permits/approvals, preliminary plans specifications, and estimate, and for the funding authorization request package. 5.2.9 Funds for design work shall be authorized by the State once the design authorization submission has been approved. 5.2.10 Subrecipient agrees that all pedestrian facilities shall be designed to provide safe and easy accessibility for all users. These facilities shall comply with the Americans with Disabilities Act (ADA) of 1990, Section 504 of the Rehabilitation Act of 1973, 49 C.F.R. Part 27 , and the current version of the NJDOT Roadway Design Manual in effect at the time this Agreement is executed. 5.2.11 Subrecipient agrees that the monies requisitioned from the Project Fund will be used only to reimburse actual, eligible costs and for no other purpose. Subrecipient agrees that it shall provide to the State, upon
agrees that the monies requisitioned from the Project Fund will be used only to reimburse actual, eligible costs and for no other purpose. Subrecipient agrees that it shall provide to the State, upon demand and at no cost to the State, such documentation as will enable the State to determine that the proceeds of the Project Fund have been applied solely to Project Costs. 5.2.12 When the Subrecipient considers the design work to be finally complete, Subrecipient shall request that the State's representative make a final review of the plans, specifications and estimate. If it is determined, after such review, that the design work has been completed in accordance with all applicable laws and requirements, Subrecipient shall submit a final invoice to the State and the State shall disburse an amount equal to the approved final payment. Upon payment of the amount approved for final payment, the State shall be released from any further responsibility in connection with the Project Fund and the Project design work.
October 2024 New Jersey Department of Transportation Division of Local Aid and Economic Development Federal Aid Cost Reimbursement Agreement 8 5.3 Construction Projects 5.3.1 Subrecipient shall complete or cause the completion of Project Work in accordance with the plans and specifications approved by the State. 5.3.2 Subrecipient covenants that Project Work will comply with all applicable laws and other requirements of federal, state and local governmental bodies. Subrecipient shall obtain all permits and licenses necessary to complete Project Work prior to federal authorization. 5.3.3 The Subrecipient shall not advertise the project until federal authorization for the Project is obtained and the State provides written authorization to proceed. 5.3.4 Subrecipient shall not proceed with any Project Work for which reimbursement shall be sought without the written authorization of the State. 5.3.5 Subrecipient shall solicit bids for Project Work in accordance with Section 3.8 of this Agreement. The Subrecipient shall advertise the project within sixty (60) days of the State’s authorization of funds and must award the project within six months of authorization of funds. The Subrecipient shall comply with, and cause all bidders to comply with, the applicable Civil Rights and bidding provisions of the Standard Specifications, including, but not limited to, Sections 102.13.01 and 105.02.05. Upon receipt of bids from responsible contractors, Subrecipient shall select the contractor submitting the lowest responsive bid. Within thirty (30) days of the award of the contract, the Subrecipient shall submit: 5.3.5.1 One copy of the summary of construction bids showing all bid quantities, unit prices, and amounts for the construction of pay items, and 5.3.5.2 A fully executed and sealed resolution awarding the contract to the lowest responsible bidder, which shall be subject to the approval of the State. 5.3.5.3 Once the State has received all of the information listed above, it shall notify Subrecipient in writing whether it has been approved. Subrecipient agrees not to contract with any contractor to whom the State has made a reasonable and timely objection. 5.3.6 Subrecipient shall submit to the State documentation of the consultant selection process or use of in-house forces and final negotiated consultant cost proposal. The use of in-house staff is permitted but is
pient shall submit to the State documentation of the consultant selection process or use of in-house forces and final negotiated consultant cost proposal. The use of in-house staff is permitted but is subject to the approval of the State. In order to use in-house staff for design work, Subrecipient must allow the State to review its project accounting systems and be cost-basis approved by the State. 5.3.7 If Subrecipient is not performing construction inspection work in-house, Subrecipient shall solicit proposals in accordance with Section 3.8 of this Agreement. Upon receipt of proposals from responsible consultants, Subrecipient shall select professional services based upon qualifications and shall furnish the
October 2024 New Jersey Department of Transportation Division of Local Aid and Economic Development Federal Aid Cost Reimbursement Agreement 9 name of such consultant to the State for concurrence. Subrecipient agrees not to contract with any consultant to whom the State has made a reasonable and timely objection. 5.3.8 Subrecipient agrees that the monies requisitioned from the Project Fund will be used only to reimburse actual, eligible Project Costs and for no other purpose. Subrecipient agrees that it shall provide to the State, upon demand and at no cost to the State, such documentation as will enable the State to determine that the proceeds of the Project Fund have been applied solely to Project Costs. 5.3.9 Upon written request of the State, the Subrecipient shall cause its contractor to provide payment and performance bonds in an amount equal to 100% of the cost of the Project Work. A surety company satisfactory to the State and qualified to do business in the State of New Jersey shall execute such bonds. Copies of all bonds shall be delivered to the State upon request. Only those sureties listed in the US Treasury Department Circular 570 and authorized to do business in the State shall furnish the surety bonds. Payment and performance bonds shall be part of the contract standard items. Performance and/or Payment bonds shall be billed to the State upon award of contract. 5.3.10 Foreign Materials And Equipment. Subrecipient agrees that it will comply and cause its contractor to comply with the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. No. 117-58, which includes the Build America, Buy America Act (“Buy America”), Pub. L. No. 117-58, §§ 70901-52 and implementing regulations, and § 106.03.2 of the current version the NJDOT Standard Specifications, which sets forth the federal requirements for the use of foreign materials and equipment on Federal-aid projects. 5.3.11 Subrecipient agrees that it shall cause its contractor to comply with Federal ADA requirements. All pedestrian facilities constructed or reconstructed shall provide safe and easy accessibility for all users. These facilities shall comply with the Americans with Disabilities Act (ADA) of 1990, Section 504 of the Rehabilitation Act of 1973 and 49 C.F.R. Part 27 and the current version of the NJDOT Roadway Design Manual in effect at the time this Agreement is executed. Failure to
DA) of 1990, Section 504 of the Rehabilitation Act of 1973 and 49 C.F.R. Part 27 and the current version of the NJDOT Roadway Design Manual in effect at the time this Agreement is executed. Failure to comply may result in the loss of projects funds. 5.3.12 The Subrecipient agrees that it will ensure its contractors are aware of and are in compliance with 31 U.S.C. § 1352 prior to execution of any agreement in order to remain eligible for federal-aid funds. 5.3.13 When Subrecipient considers the Project to be finally complete, Subrecipient shall request that the State's representative make a final inspection of the Project. If it is determined, after such inspection, that the Project has been completed in accordance with the plans and specifications, Subrecipient shall prepare and submit to the State a certification that the final inspection has been made and the cost of the Project has actually been incurred in accordance with the provisions of the
October 2024 New Jersey Department of Transportation Division of Local Aid and Economic Development Federal Aid Cost Reimbursement Agreement 10 Agreement. Upon receipt, the State shall disburse an amount equal to the approved final payment. Upon payment of the amount approved for final payment, the State shall be released from any further responsibility in connection with the Project Fund and the Project. The State will monitor maintenance of completed Project by the Subrecipient. Failure to maintain Project will result in the withholding of funds payable to the Subrecipient on other State funded programs. 5.3.14 The Subrecipient must designate a person in Responsible Charge who is a full time employee of the agency as per 23 C.F.R. § 635.105. The person in "Responsible Charge" of LPA administered projects need not be an engineer. This requirement applies even when consultants are providing construction engineering services. This person may share duties, but is expected to be able to perform the following duties and functions: 5.3.15 Administers inherently governmental project activities, including those dealing with cost, time, adherence to contract requirements, construction quality and scope of Federal-aid projects; 5.3.16 Maintains familiarity of day to day project operations, including project safety issues; 5.3.17 Makes or participates in decisions about changed conditions or scope changes that require change orders or supplemental agreements; 5.3.18 Visits and reviews the Project on a frequency that is commensurate with the magnitude and complexity of the project; 5.3.19 Reviews financial processes, transactions and documentation to ensure that safeguards are in place to minimize fraud, waste, and abuse; and; 5.3.20 Directs Project staff, agency or consultant, to carry out Project Administration and Contract Oversight, including proper documentation. 5.3.21 Is aware of the qualifications, assignments and on-the-job performance of the agency and consultant staff at all stages of the Project. 5.3.22 In addition to adhering to the requirements specifically set forth in this Agreement, Subrecipient agrees that it will cause its contractor to comply with the USDOT/FHWA’s official Disadvantaged Business Enterprises (DBE) Program Guidance, including that all contract bidders/offerors submit DBE subcontractor information and/or good faith efforts, either at
USDOT/FHWA’s official Disadvantaged Business Enterprises (DBE) Program Guidance, including that all contract bidders/offerors submit DBE subcontractor information and/or good faith efforts, either at the time of bid (responsiveness) or within 5 days of bid (responsibility). Guidance with regard to the DBE program can be found on the USDOT and FHWA Civil Rights’ websites. 6. Insurance 6.1 Subrecipient shall maintain or cause to be maintained:
October 2024 New Jersey Department of Transportation Division of Local Aid and Economic Development Federal Aid Cost Reimbursement Agreement 11 6.1.1 General Comprehensive Liability Insurance in the minimum amount of $1,000,000.00 combined single limit plus $1,000,000.00 in an umbrella policy. This insurance shall specifically provide for coverage of the State as an additional insured and shall provide for coverage at least as broad as the standard, basic un- amended commercial general liability policy and shall be endorsed to include broad form contractual liability coverage, independent contractor’s coverage and completed operations coverage. 6.1.2 Comprehensive Automobile Liability Insurance in the minimum amount of $1,000,000.00. 6.1.3 Workers Compensation Insurance in the amount required by law. 6.2 A copy of each insurance policy shall be made available to the State upon request. 6.3 Subrecipient shall cause to be maintained Errors and Omissions, Professional Liability Insurance and/or Professional Malpractice Insurance sufficient to protect against liabilities arising out of professional obligations performed pursuant to the requirements of this Agreement. This insurance shall be in the minimum amount of $1,000,000.00. 6.4 Subrecipient expressly understands and agrees that any insurance protection required by this Agreement shall in no way limit the obligations assumed by Subrecipient pursuant to this Agreement and shall not be construed to relieve Subrecipient of liability in excess of such coverage, nor shall it preclude the State from taking such other actions as are available to it under any other provision of this Agreement or otherwise in law. 7. Disbursement of Project Fund 7.1 It is agreed that any and all Project Costs incurred by the Subrecipient prior to the execution of this Agreement by all parties shall be non-participating by the State and FHWA. 7.2 The State shall disburse monies from the Project Fund to Subrecipient in order to reimburse actual, eligible costs associated with Project Work in accordance with the terms and conditions of this Agreement. Only those costs specifically enumerated in the Project Scope of Work and Cost Estimate are eligible for reimbursement. Nothing contained herein shall impose upon the State any obligation to ensure the proper application of the monies paid to Subrecipient from the Project Fund.