PB-24-18 County of Essex/ Turtle Back Zoo Block: 163 Lot: 1
Preserved file SHA-256
bb4f0f2cfefe32869ad8698295ae1ac0f175a9aba3f0ed7013377d3a6778329cIndexed text · page 3
Show all pages10. The current proposal involves redevelopment of existing facilities within an already developed area of the Zoo, and therefore would not result in expansion of the Zoo beyond its existing boundaries. 11. The Board finds that the proposed project and capital improvement is not contrary to the Master Plan of the Township of West Orange. NOW, THEREFORE, BE IT RESOLVED by the Planning Board of the Township of West Orange that it finds the proposed project and capital improvements are not inconsistent with the Township of West Orange Updated Master Plan. ADOPTED: A ilet Baquerizo Vite Planning Board Secretary
File revisions (1)
- Sep 29, 2026
bb4f0f2cfefe1,521,641 bytes