V3 RESUBMISSION Stormwater Management Report Rev 2 Dated November 3 2022
51baad1e902190dbd8bc99e285d5ec57900256b219be5005cdb7869b76e2669bIndexed text · page 10
Show all pagesdrive aisles, and sidewalks. A time of concentration of 10.14 minutes was calculated for this drainage area. DRAINAGE AREA 3 (DA-3) Drainage Area 3 consists of both pervious and impervious surfaces which drain to Basin #2. The pervious area, 5.56 acres, consist primarily of the wooded areas in the rear of the site along with some landscaped area around the proposed parking lot. The impervious area, 1.38 acres, is mainly comprised of the proposed parking lot. A time of concentration of 14.46 minutes was calculated for this drainage area. DRAINAGE AREA 4 (DA-4) Drainage Area 4 consists of both pervious and impervious surfaces which drain to Basin #3. The pervious area, 4.84 acres, consists primarily of the wooded area located to the rear of the site, along with some lawn and landscape areas around the proposed building and parking lot. The impervious area, 1.08 acres, is comprised of the portion of building to be constructed in phase III, as well as some proposed parking lots, drive aisles, sidewalks, and patios. A time of concentration of 14.30 minutes was calculated for this drainage area. CURVE NUMBERS Table 4 — Curve Number (Existing Conditions) Description Hydrologic Curve Group Number Woods A 30 Woods Cc 70 Woods D 71 Open Space A 39 Open Space € 74 Open Space D 80 Impervious A/B/C/D 98 WATER QUANTITY BASIN #1A — 3.230 CF Detention Basin #1A is a subsurface detention basin with 3,230 cubic feet of storage. The system is comprised of 3 rows of 48" diameter HDPE pipe, each 75 feet in length. The bottom of the basin is at elevation 418.00, along with 1 — 4" x 6.5" orifice. At elevation 420.50, 1 — 8” x 12" orifice will also be placed, followed by a 4' weir at an elevation of 421.30. ° 6
File revisions (1)
- Sep 29, 2026
51baad1e902114,491,312 bytes