V4 12 Stormwater Maintenance Manual

Preserved file SHA-256f41cd2aa1331dc0cf62992b06a83f27408d9d80c43c8055a09773865117149ca

Indexed text · page 14

Show all pages
Page 14

Riser Each _retention/detention system typically has _ risers strategically placed for maintenance and inspection of the system. These risers are typically 24” in diameter or larger and are placed on the manifold fittings. Cleanouts Cleanout ports are usually 4-, 6-, or 8-in diameter pipe and are placed on the manifold fittings. They are used for entrance of RISER cLEANOUT a pipe from a vacuum truck or a water-jetting device. ‘CROSS-SECTION VIEW ‘CROSS-SECTION VIEW For a complete listing of available fittings and components please refer to the ADS Fittings Manual. Maintenance Overview of a Retention/Detention System Maintaining a clean and obstruction-free retention/detention system helps to ensure the system performs the intended function of the primary design. Build up of debris may obstruct flow through the laterals in a retention system or block the entranceway of the outlet pipe in a detention system. This may result in ineffective operation or complete failure of the system . Additionally, surrounding areas may potentially run the risk of damage due to flooding or other similar issues. Inspection/Maintenance Frequency All retention/detention systems must be cleaned and maintained. Underground systems may be maintained more cost effectively if these simple guidelines are followed. Inspection should be performed at a minimum of once per year. Cleaning should be done at the discretion of individuals responsible to maintain proper storage and flow. While maintenance can generally be performed year round, it should be scheduled during a relatively dry season. Pre-Inspection A post-installation inspection should be performed to allow the owner to measure the invert prior to accumulation of sediment. This survey will allow the monitoring of sediment build-up without requiring access to the retention/detention system. The following is the recommended procedure for pre-inspections: 1) Locate the riser section or cleanouts of the retention/detention system. The riser will typically be 24” in diameter or larger and the cleanouts are usually 4”, 6” or 8” in diameter. 2) Remove the lid of the riser or clean outs. 3) Insert a measuring device into the opening and make note to a point of reference on the stick or string. (This is done so that sediment build up can be determined in the future without having to enter the system.) 4640 TRUEMAN BLVD.

Page 14

e opening and make note to a point of reference on the stick or string. (This is done so that sediment build up can be determined in the future without having to enter the system.) 4640 TRUEMAN BLVD. HILLIARD, OH 43026. (800) 821-6710 - www.ads-pipe.com I 2 |

File revisions (1)