Show all pagesCost Estimate Cost Overview Cost Type General cost for quarterly maintenance (sediment, trash, and debris removal) General cost for annual maintenance General cost for unscheduled maintenance Cost Details $1,045 Table A $2,255 Table B $500 Table C Total cost $3,800 Table A: General cost for quarterly maintenance Cost Type Personnel Crew-Site Cleanup Required Quantity Unit Price Cost 1 $500 $500 Equipment Truck 1 $200 $200 Services Disposal 1 $250 $250 Subtotal $950 Overhead $95 Total Cost $1,045 March 2024 Stormwater Management Measures Maintenance Plan & Field Manuals Page 9