Page 6

-permitted disturbance of freshwater wetlands, State open waters, or transition areas besides that shown on the approved plans shall be considered a violation of the Freshwater Wetlands Protection Act Rules unless the activity is exempt or a permit is obtained from the Department prior to the start of the disturbance. 26. This authorization is valid for a term not to exceed five years from the date of this permit. If the permittee wishes to continue an activity covered by the permit after the expiration date of the permit, the permittee must apply for and obtain a permit extension or a new permit, prior to the permit’s expiration. If the term of the authorization exceeds the expiration date of the permit issued by rule, and the permit upon which the authorization is based is modified by rule to include more stringent standards or conditions, or is not reissued, the applicant must comply with the requirements of the new regulations by applying for a new applicable permit authorization. FRESHWATER WETLAND MITIGATION CONDITIONS: 1. The permittee shall mitigate for the permanent disturbance of 0.006 acres of State open waters and 0.115 acres of forested wetlands through an on-site or off-site creation, restoration or enhancement project or with the purchase of credits from a mitigation bank serving the appropriate watershed management area in accordance with the mitigation hierarchy (N.J.A.C. 7:7A-11 et seq).

Page 7

DLRP File No. 0722-04-0001.1 LUP230001 Page 7 of 14 West Essex Highlands Inc. 2. At least 90 days prior to the initiation of regulated activities authorized by this permit, the permittee shall submit a mitigation proposal to the Division of Watershed Protection and Restoration for review and approval. Activities authorized by this permit shall not begin until the permittee has obtained written approval of a mitigation plan from the Department (N.J.A.C. 7:7A-11.6(a)). 3. All mitigation shall be conducted prior to or concurrent with the construction of the approved project (N.J.A.C. 7:7A-11.3(a)). Concurrent means that at any given time, the mitigation must track at the same or greater percentage of completion as the project as a whole. 4. If the permittee fails to perform mitigation within the applicable time-period the acreage of mitigation required shall be increased by 20 percent each year after the date mitigation was to begin (N.J.A.C. 7:7A-11.3(c)). 5. If the permittee is considering obtaining land to satisfy a mitigation requirement, the Department strongly recommends that the permittee obtain the Division’s conceptual review and approval of any land being considered as a potential mitigation area. 6. If the permittee is purchasing credits from a mitigation bank to satisfy a mitigation requirement, prior to the initiation of regulated activities authorized by this permit, the permittee shall submit proof of purchase for 0.121 mitigation credits from an approved wetland mitigation bank to the attention of the Mitigation Unit Supervisor, NJDEP, Division of Watershed Protection and Restoration at Mail Code 501-02A, P.O. Box 420, Trenton, NJ 08625-0420. At this time, the following bank(s) are approved to serve the project area; additional banks may be approved at any time, so please contact the Mitigation Unit for the most up to date service area information if you would like additional options. Pio Costa: Contact: Carmen Pio Costa, Anthony Pio Costa and he can be reached at (973) 575-1706 or carmon@piocosta.com Troy Meadows: Contact: Len Fariello, Wildlife Preserves, (973)887-0096 or LFariello@WildlifePreserves.org 7. If the permittee is considering conducting a creation, restoration or enhancement project, the following conditions shall apply: a. Prior to the initiation of regulated activities authorized by this permit the permittee shall submit a final

Page 7

ng a creation, restoration or enhancement project, the following conditions shall apply: a. Prior to the initiation of regulated activities authorized by this permit the permittee shall submit a final design of the mitigation project for approval and include all of the items listed on the checklist entitled Checklist for Completeness: Creation, Restoration or Enhancement for a Freshwater Wetland Mitigation Proposal located at https://dep.nj.gov/wlm/forms/#mit. b. The permittee shall obtain a secured bond or other financial surety acceptable to the Division from a firm licensed to provide such services in New Jersey. (N.J.A.C. 7:7A-11.17) c. Prior to the completion of the mitigation project, the permittee shall complete, sign and file with the County Clerk (the Registrar of Deeds and Mortgages in some counties), a conservation restriction that meets the requirements of N.J.A.C. 7:7A-12.1. The conservation restriction shall include the wetland and required transition area and conform to the format and content of the Wetlands Mitigation Area model conservation restriction that is available at: https://dep.nj.gov/wlm/forms/#mdr. The applicant is required to include a metes and bounds description shown on a map. Within 180 days of the issuance of the mitigation approval, the

Page 8

DLRP File No. 0722-04-0001.1 LUP230001 Page 8 of 14 West Essex Highlands Inc. recorded conservation restriction shall be provided to the Mitigation Unit, Division of Watershed Protection and Restoration for verification. (N.J.A.C. 7:7A-12.1 et. seq.) d. The permittee shall notify the Mitigation Unit at the Division of Watershed Protection and Restoration in writing at least 30 days prior to the start of construction of the wetland mitigation project to arrange an on-site pre-construction meeting among the permittee, the contractor, the consultant and the Division. e. To ensure the intent of the mitigation design and its predicted wetland hydrology is realized in the landscape, the mitigation designer shall be present on-site during all critical stages of mitigation construction and during the restoration of any temporarily impacted areas. Critical stages of construction include but are not limited to herbicide applications, earthmoving activities, planting, and inspections. f. The permittee shall be responsible for ensuring that best management practices are used throughout construction to control the spread and colonization of highly invasive plants. Specifically, all equipment, especially tracks and tires, must be thoroughly cleaned every time equipment or vehicles move from an area containing invasive plants or from off-site to the mitigation area. In addition, soil containing root fragments and above-ground vegetative material from invasive plants shall be carefully managed during earthmoving activities and disposed of at a suitable off-site location rather than mulched and reused or stockpiled elsewhere on the site. For information on the specific species that are considered to be invasive, please refer to the Mitigation Technical Manual at https://dep.nj.gov/wp- content/uploads/wlm/downloads/mit/mit_054.pdf. g. If changes to the mitigation design are necessary to ensure success of the project as a result of on-site conditions, the mitigation designer shall immediately notify the Division in writing and submit an alternative plan which achieves the proposed wetland conditions. The Division shall review the plan in accordance with N.J.A.C. 7:7A-11.7. Any modifications to the plan that are reviewed and approved by the Division must be shown on a signed and sealed revised plan. The As-Built plans required as a part of the Construction Completion Report may

Page 8

ifications to the plan that are reviewed and approved by the Division must be shown on a signed and sealed revised plan. The As-Built plans required as a part of the Construction Completion Report may serve as the signed and sealed revised plan required to be submitted as part of the construction modification process described above if time constraints warrant such action and have been approved by the Division in writing. h. Within 30 days of final grading of the mitigation site and prior to planting, the permittee shall notify the Mitigation Unit at the Division of Watershed Protection and Restoration in writing to arrange a post-grading construction meeting among the permittee, contractor, consultant and the Division. i. Within 30 days following the final planting of the mitigation project, the permittee shall submit a Construction Completion Report to the Division detailing as-built conditions (see below) and any changes to the approved mitigation plan that were made during construction (N.J.A.C. 7:7A-11.12). The Construction Completion Report shall contain, at a minimum, the following information: i. A completed Wetland Mitigation Project Completion of Construction Form. This form is located at https://dep.nj.gov/wlm/forms/#mit and certifies that the mitigation project has been constructed as designed and that the proposed area of wetland creation, restoration or enhancement has been accomplished;

Page 9

DLRP File No. 0722-04-0001.1 LUP230001 Page 9 of 14 West Essex Highlands Inc. ii. As-Built plans which depict final grade elevations at one-foot contours and include a table of the species and quantities of vegetation that were planted including any grasses that may have been used for soil stabilization purposes; and iii. Photos of the constructed wetland mitigation project with a photo location map as well as the GPS waypoints in NJ state plane coordinates NAD 1983. j. Within 30 days following final planting of the mitigation project, the permittee shall post the mitigation area with permanent signs which identify the site as a wetland mitigation project and that all-terrain vehicle use, motorbike use, mowing, dumping, draining, cutting and/or removal of plant materials is prohibited and that violators shall be prosecuted and fined to the fullest extent under the law. The signs must also state the name of the permittee, a contact name and phone number, and the Department’s permit number. k. The permittee shall monitor all freshwater wetland and transition area projects for a minimum of 5 years, unless otherwise stipulated within the approved mitigation proposal, beginning the first full growing season after the mitigation project has been completed. The permittee shall submit monitoring reports to the Division of Watershed Protection and Restoration no later than December 31st of each full monitoring year (N.J.A.C. 7:7A-11.12(g)). All monitoring reports must include the standard items identified in the checklist entitled, “Mitigation Monitoring Checklist”, which can be found at https://dep.nj.gov/wlm/forms/#mit. l. Once the required monitoring period has expired and the permittee has submitted the final monitoring report, the Division will make the finding that the mitigation project is either a success or a failure. This mitigation project will be considered successful if the permittee demonstrates all of the following: i. That the goals of the wetland mitigation project, including acreage and the required transition area, as stated in the approved wetland mitigation proposal and the permit have been satisfied. The permittee shall submit a field wetland delineation of the wetland mitigation project based on the Federal Manual for Identifying and Delineating Jurisdictional Wetlands (1989) which shows the exact acreage of State open waters, emergent,

Page 9

d delineation of the wetland mitigation project based on the Federal Manual for Identifying and Delineating Jurisdictional Wetlands (1989) which shows the exact acreage of State open waters, emergent, scrub/shrub and/or forested wetlands in the mitigation area; ii. The site has an 85 percent survival and 85 percent area coverage of the mitigation plantings or target hydrophytes, which are species native to the area and similar to ones identified on the mitigation planting plan. All plant species in the mitigation area must be healthy and thriving and all trees must be at least five feet in height; iii. The site has less than 10 percent coverage by invasive or noxious species. iv. The site contains hydric soils or there is evidence of reduction occurring in the soil; and, v. The proposed hydrologic regime as specified in the mitigation proposal has been satisfied. m. The permittee is responsible for assuming all liability for any corrective work necessary to meet the success criteria established above (N.J.A.C. 7:7A-11.12(i)). The Division will notify the permittee in writing if the mitigation project is considered a failure. Within 30 days of notification, the permittee shall submit a revised mitigation plan to meet the success criteria

Page 10

DLRP File No. 0722-04-0001.1 LUP230001 Page 10 of 14 West Essex Highlands Inc. identified above for Division review and approval. The financial surety, if required, will not be released by the Division until such time that the permittee satisfies the success criteria as stipulated above. STANDARD CONDITIONS: 1. The issuance of a permit shall in no way expose the State of New Jersey or the Department to liability for the sufficiency or correctness of the design of any construction or structure(s). Neither the State nor the Department shall, in any way, be liable for any loss of life or property that may occur by virtue of the activity or project conducted as authorized under a permit. 2. The issuance of a permit does not convey any property rights or any exclusive privilege. 3. The permittee shall obtain all applicable Federal, State, and local approvals prior to commencement of regulated activities authorized under a permit. 4. A permittee conducting an activity involving soil disturbance, the creation of drainage structures, or changes in natural contours shall obtain any required approvals from the Soil Conservation District or designee having jurisdiction over the site. 5. The permittee shall take all reasonable steps to prevent, minimize, or correct any adverse impact on the environment resulting from activities conducted pursuant to the permit, or from noncompliance with the permit. 6. The permittee shall immediately inform the Department of any unanticipated adverse effects on the environment not described in the application or in the conditions of the permit. The Department may, upon discovery of such unanticipated adverse effects, and upon the failure of the permittee to submit a report thereon, notify the permittee of its intent to suspend the permit. 7. The permittee shall immediately inform the Department by telephone at (877) 927-6337 (WARN DEP hotline) of any noncompliance that may endanger public health, safety, and welfare, or the environment. The permittee shall inform the Watershed & Land Management by telephone at (609) 777-0454 of any other noncompliance within two working days of the time the permittee becomes aware of the noncompliance, and in writing within five working days of the time the permittee becomes aware of the noncompliance. Such notice shall not, however, serve as a defense to enforcement action if the project is found to be

Page 10

in writing within five working days of the time the permittee becomes aware of the noncompliance. Such notice shall not, however, serve as a defense to enforcement action if the project is found to be in violation of this chapter. The written notice shall include: i. A description of the noncompliance and its cause; ii. The period of noncompliance, including exact dates and times; iii. If the noncompliance has not been corrected, the anticipated length of time it is expected to continue; and iv. The steps taken or planned to reduce, eliminate, and prevent recurrence of the noncompliance. 8. Any noncompliance with a permit constitutes a violation of this chapter and is grounds for enforcement action, as well as, in the appropriate case, suspension and/or termination of the permit.

Page 11

DLRP File No. 0722-04-0001.1 LUP230001 Page 11 of 14 West Essex Highlands Inc. 9. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the authorized activity in order to maintain compliance with the conditions of the permit. 10. The permittee shall employ appropriate measures to minimize noise where necessary during construction, as specified in N.J.S.A. 13:1G-1 et seq. and N.J.A.C. 7:29. 11. The issuance of a permit does not relinquish the State’s tidelands ownership or claim to any portion of the subject property or adjacent properties. 12. The issuance of a permit does not relinquish public rights to access and use tidal waterways and their shores. 13. The permittee shall allow an authorized representative of the Department, upon the presentation of credentials, to: i. Enter upon the permittee's premises where a regulated activity, project, or development is located or conducted, or where records must be kept under the conditions of the permit; ii. Have access to and copy, at reasonable times, any records that must be kept under the conditions of the permit; iii. Inspect, at reasonable times, any facilities, equipment, practices, or operations regulated or required under the permit. Failure to allow reasonable access under this paragraph shall be considered a violation of this chapter and subject the permittee to enforcement action; and iv. Sample or monitor at reasonable times, for the purposes of assuring compliance or as otherwise authorized by the Federal Act, by the Freshwater Wetlands Protection Act, or by any rule or order issued pursuant thereto, any substances or parameters at any location. 14. The permittee shall not cause or allow any unreasonable interference with the free flow of a regulated water by placing or dumping any materials, equipment, debris or structures within or adjacent to the channel while the regulated activity, project, or development is being undertaken. Upon completion of the regulated activity, project, or development, the permittee shall remove and dispose of in a lawful manner all excess materials, debris, equipment, and silt fences and other temporary soil erosion and sediment control devices from all regulated areas. 15. The permittee and its contractors and subcontractors shall comply with all conditions, site plans, and supporting documents approved