Show all pagesEXHIBIT D PROJECT SCHEDULE Estimated Construction Schedule Estimated project schedules if constructed in one phase Submission of site plan application Receipt of all approvals for project Commencement of construction Completion of construction 6/1/2021 7/1/2022 7/1/2022 7/1/2025 Estimated Project Schedule if the project is Phased Submission of site plan application Receipt of all approvals for project Phase 1 Commencement of Construction (Approximately 300 units) Phase 1 Completion of Construction Phase 2 Commencement of Construction (Approximately 125 units) Phase 2 Completion of Construction 4839-2360-2911, v. 3 6/1/2021 7/1/2022 7/1/2022 9/1/2024 1/1/2026 1/1/2028