Page 41

EXISTING UTILITIES AT TIE-IN CONNECTION LOCATIONS AND REINSTALL AS REQUIRED TO ELIMINATE THE CONFLICT AT NO ADDITIONAL COST TO THE OWNER. 0 0' 10 6. CONTRACTOR SHALL ADEQUATELY PROTECT ALL EXISTING PIPELINES AND STRUCTURES DURING INSTALLATION OF DRY WELL SYSTEM.

Page 41

R= R RED =1

Page 41

7. ALL LOCATIONS, DIMENSIONS, AND ANGLES OF NEW FACILITIES ARE TO BE VERIFIED IN THE FIELD. CONTRACTOR IS ADVISED THAT MINOR ADJUSTMENTS MAY BE REQUIRED TO AVOID POTENTIAL CONFLICTS. 00 R-T 0'

Page 41

0' 8. ALL EARTHWORK ACTIVITIES SHALL COMPLY WITH THE COUNTY SOIL CONSERVATION DISTRICT'S RULES AND REGULATIONS GOVERNING EROSION CONTROL. I-B COLU B-1

Page 41

JOHN ST 9. THE SITE PLAN INDICATES THE APPROXIMATE LOCATION OF EXISTING PIPING. THE CONTRACTOR SHALL LOCATE ALL EXISTING PIPE BY TEST PIT AND/OR TEST TRENCH TO AVOID POSSIBLE CONFLICTS WITH NEW PIPING. THE CONTRACTOR SHALL NOTIFY ALL UTILITY MBIA

Page 41

WHITTLESEY AVE WEST ORANGE

Page 41

COMPANIES AND NJ ONE CALL PRIOR TO CONSTRUCTION; ALL PIPELINES AND CONDUITS SHALL BE MARKED OUT. THIS WORK SHALL BE AT NO ADDITIONAL COST TO THE OWNER. T S LIBE RTY I B-1

Page 41

B-1 WATSON AVE 10. DURING ALL CONSTRUCTION ACTIVITIES, THE CONTRACTOR SHALL COMPLY WITH ALL THE REQUIREMENTS OF THE STATE OF NEW JERSEY CONSTRUCTION SAFETY CODES, HIGH VOLTAGE PROXIMITY ACTS AND OSHA. THE CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR

Page 41

COMPLIANCE WITH ALL LOCAL BUILDING CODES AND ORDINANCES. ST W AT CHU NG A

Page 41

R-T HIGH ST 11. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING REQUIRED APPROVALS FROM AUTHORITIES WITH JURISDICTION OVER PROPOSED WORK.