Show all pages• Concerns raised regarding the illumination levels and the application not currently meeting some of the requirements of the ordinance 7. Stormwater: • Engineer noted need for stormwater management compliance • Applicants indicated they needed to figure out the site layout issues first • O & M plan and record on deed is needed for the rain gardens • A high-level review is needed for the Board • Soil testing is required before Board approval 8. Other Points: • Applicant should provide a statement of operations • A letter from the Downtown Alliance regarding this application is expected 9. Conclusion: • Applicant to review and submits revised plans based on SPARB Comments • Another Technical meeting may be conducted, if necessary