RUCTION ENTRANCE AND OTHER EROSION CONTROL MEASURES INCLUDING SILT FENCING - 1 WEEK BY CHK 2. CLEAR & DEMO SITE, ROUGH GRADING - 1 WEEK ---- ---- ----
---- ---- ---- ---- ----
---- ---- ---- ---- ----
JC 2 EACH DUMP 3. REMOVE EXISTING GRAVEL - 1 WEEK STRAPS RP ----
---- ---- ---- ---- ----
---- ---- ---- ----
---- ---- 4. CONSTRUCT TURFSTONE - 2 WEEKS 5. REMOVE ALL EROSION CONTROL STRUCTURES -1 DAY 5/26/2026 DATE
---- ---- ---- ---- ----
---- ---- ---- ----
---- ---- ---- EXPANSION RESTRAINT *NOTE: INDIVIDUAL LOT ACCESS POINTS MAY REQUIRE STABILIZATION. (1/4" NYLON ROPE, THICKNESS SHOWN IS FOR STONE CONSTRUCTION ENTRANCE ONLY