Show all pages6.0 Construction Project Management Title 23 CFR 635.105 specifies oversight requirements for locally administrated federal aid construction projects, which mandates a full-time employee to be responsible charge of Federal- Aid construction projects and to work in conjunction with the consulting company providing Construction Management and Construction Inspection Services outlined by the RFP as described in a separate section of this document. In accordance with 23 CFR 635.105, a full-time Township of West Orange employee will be designated to be the “Responsible Charge” for each federally funded project. This protocol will be required and applied even when consultants are providing design/contract administration/ or other engineering services on the project. 6.1 Responsible Charge/Project Manager (RC/PM) The Township of West Orange will provide a full-time employee as required by Title 23 CFR 635.105(a) to be in responsible charge of the construction project. The responsible person in charge is the RC/PM for the project. This applies even when a Consultant provides construction engineering services. The RC/PM is involved in the entire project from start to finish, including the close out process. The RC/PM is required to have completed the Rutgers CAIT Responsible Charge Training Course. A RC/PM can be, if needed, acting as responsible charge on more than one project and directing Township of West Orange personnel to specific projects. The RC/PM is aware of the qualifications, assignments and on the job performance of the consultant. The RC/PM schedules the pre-construction meeting after the contract has been signed, and insurances and bonds are posted to the satisfaction of the Corporation Counsel thru the Legal Department. A Notice to Proceed is issued after the pre-construction meeting specifying the start date, the duration of the project as per the specifications and the completion date. The RC/PM, who is accountable for the project, may share duties with the Resident Engineer (Consultant Inspection Services), however the RC/PM is responsible for the following: a. Administers Government project activities, in regard to cost, time, adherence to contract requirements, construction quality and scope of Federal-aid-projects. b. Maintains familiarity of day to day project operations, including project safety issues.
adherence to contract requirements, construction quality and scope of Federal-aid-projects. b. Maintains familiarity of day to day project operations, including project safety issues. At a minimum, requires to the Resident Engineer to check daily the maintenance and protection of traffic control to ensure it is set up as established on the bid documents and request the Contractor to resolve any non-conformance issues found. c. Makes and participates in decisions about changed conditions or scope changes that require change orders or supplemental agreements. d. Visits and reviews the project site on a frequency appropriated to the complexity of the project, maintains record of these visits on a hard copy diary document. Procedure for Administration and Inspection of Federal Aid Highway Projects Page 20
File revisions (1)
- Sep 29, 2026
67f522fbe67a1,554,006 bytes