Supporting Documentation · Apr 26, 2022

125-22 Attachment - Admin Procedures Appendices Final Revised March 2022.pdf

Preserved file SHA-25667f522fbe67a6517f161ff763a90217ae744e7aa5eec0936734382a47d5bec39

Indexed text · page 29

Show all pages
Page 29

estimates for the RC/PM. The summary of pay items must be used for comparison and negotiations of Contractor payment request. The RC/PM must ensure proper payments are being made in accordance with the contract provisions. Upon acceptance of the negotiated Contractor payment, a voucher request will be forwarded to Township of West Orange Chief Financial Officer for Contractor payment. h. The Resident Engineer reviews prevailing wage rate requirements of 23 U.S.C and the Davis-Bacon Act, and documents in the Township of West Orange’s project files. i. NEPA and all environmental commitments and/or permit requirements must be met and documented in the daily inspection reports. j. All pedestrian facilities must be constructed or reconstructed in accordance with the American with Disabilities Act (ADA) of 1990; Section 504 of the Rehabilitation Act of 1973; 28 CFR Part 35.151 (e) and NJDOT Standard Construction Details. k. DBE requirements are monitored and enforced to ensure compliance with 49 CFR 26; the contract plans, specifications and related contract documents; the NJDOT Construction Handbook Section V, Subsection B and NJDOT DBE/ESBE Programs. 6.6 Buy America Steel or iron products including application of coating permanently incorporated into federal-aid projects must be manufactured in the United States as per Title 23 CFR 635.410 requirements. These requirements apply to the entire federal-aid project. There is no exemption for steel and iron purchased with other than federal funds. Minimal use of foreign steel or iron is permissible if the cost of such materials does not exceed one-tenth of one percent of the total cost or $2,500, whichever is greater. Pursuant Section 3 of this document, the RC/PM, as responsible charge, will request to the Resident Engineer and Inspector to ensure that the Buy America Certification be provided at the time of material delivery. No steel or iron will be incorporated into the project without a signed Buy America certification. The certification must be properly labeled as per project specific, and be current, dated, signed and notarized, and specific to the

Page 29

orated into the project without a signed Buy America certification. The certification must be properly labeled as per project specific, and be current, dated, signed and notarized, and specific to the materials at hand and should be delivered prior to steel/iron material is installed. The certification must be printed on the supplier letterhead. This will be documented in the daily inspection reports. The Resident Engineer will maintain a log of all the steel placed on the project; permanently incorporated, temporary, and temporary but must remain in place (stay in place forms, temporary sheeting left in place by the Contractor). 6.7 DBE/Trainee Compliance A specified DBE goal is received from NJDOT-Local Aid by the Township of West Orange and included on the Federal Attachments of the bid documents. The RC/PM and the Resident Engineer continuously monitor DBE and Trainee participation and perform Commercial Useful Function reviews as the project progresses and are responsible for ensuring the DBE contract goals will be Procedure for Administration and Inspection of Federal Aid Highway Projects Page 29

File revisions (1)