Page 32

a detailed cost proposal (materials, labor, equipment, overhead) for extra (new work). The negotiated cost will be sent to NJDOT Local Aid and included in the Change Order (Form DC- 173A). Upon approval by NJDOT Local Aid, the Contractor will be instructed by Field Order to proceed with the work. The process for a Field Order shall be as follows: a. The contractor shall immediately notify the Resident Engineering that there is a need for a Field Order. b. The Resident Engineer shall set up a meeting in the field to include the Contractor and the RC/PM to discuss the needed change, potential cost impacts and potential changes to the Progress Schedule. c. Once the change has been agreed upon by all parties, the Resident Engineer shall issue, after the meeting, a written description of the change, including the immediate need for the change and the anticipated cost. d. The RC/PM will evaluate the Field Order request and, if acceptable, immediately notify the NJDOT Local Aid by e-mail. Upon written approval from NJDOT Local Aid, the Resident Engineer shall then issue a verbal approval to the contractor. The contractor can then proceed with the Field Order. The Resident Engineer will immediately prepare a written approval of the Field Order after verbal approval is given. The Resident Engineer shall record and verify all work and quantities related to the Field Order and immediately notify the RC/PM if the estimated work for the change should differ significantly f rom what was discussed. If there are significant differences, RC/PM shall decide whether a revised field change order is required. e. The RC/PM will proceed with the approval of the Field Order at the next available Municipal Council meeting and submit to NJDOT Local Aid for formal approval by use of a Federal Aid Change Order (Form DC-173A) as outlined above. 7.0 Contract Completion Date Contract Completion – Time of Completion and Liquidated Damages shall be in accordance with NJDOT Standard Specification, Section 108.10. The RC/PM issues a formal “Notice-To- Proceed” (NTP), once all Civil Rights documents have been submitted and approved by the NJDOT and all Pre-Construction Meeting Checklist items are completed. The NTP

Page 32

RC/PM issues a formal “Notice-To- Proceed” (NTP), once all Civil Rights documents have been submitted and approved by the NJDOT and all Pre-Construction Meeting Checklist items are completed. The NTP must include the Contract Completion Date. The Resident Engineer with the supervision of RC/PM, schedules progress review meeting periodically to evaluate the progress on the project and request progress schedule updates from the Contractor. If the Contractor falls behind the schedule, the Contractor will be notified in writing and asked to make every effort to improve the progress. The Contractor will be advised by the Resident Engineer, who will ensure that, contract time extensions will only be granted for excusable delays specified in Section 108.11 of the NJDOT Procedure for Administration and Inspection of Federal Aid Highway Projects Page 32

File revisions (1)