Show all pageswork directed by the Change Order. The Township of West Orange will pursue a satisfactory resolution of disputed work issues or claims within a reasonable period of time as required by Standardized Changed Condition clauses per 23 CFR 635.109, NJDOT Standard Specifications and the project Supplementary Specification. The cost to settle work disputes, contract claims, or court awards must be reviewed by NJDOT prior to reimbursement as per 23 CFR 635.124. Any disputed work must be documented in the project records. Disputed work issues or claims must be resolved prior to close out of the project. Procedure for Administration and Inspection of Federal Aid Highway Projects Page 34