Leonard R. Lepore, P.E. October 20, 2022 Page 3 e Prepare a New Jersey Department of Environmental Protection (NJDEP) Treatment Works Approval (TWA) for submittal to the Joint Meeting of Essex and Union Counties (JMEUC) and the NJDEP. e Prepare a Hudson-Essex-Passaic Soil Conservation District (HEPSCD) Soil Erosion and Sediment Control Plan Certification. The Contract Plans will be included in the submission. e Northfield Avenue is an Essex County Road identified as Route 508. Crew will submit the design drawings to the Essex County Department of Public Works, Engineering Division, for their review and approval. The respective utility contractor will secure the necessary Road Opening Permit from the County prior to construction for the work associated with connecting to the existing terminal manhole in Northfield Avenue. The Bid Documents will note this requirement. e Prepare easement metes and bounds descriptions and plats for the Township’s use in obtaining a sanitary sewer easement for the proposed gravity sewer main outside the rights-of-way or Township-controlled property. This Proposal is based on the anticipated need for a single permanent sanitary sewer easement. e Attend four meeting with the Township Officials: kickoff, coordination, preliminary design, final design. Construction-Related Services e Submit notification to HEPSCD in compliance with Plan Certification. e Actas the Township's professional representative during construction, provide assistance to the Township relative to construction activities, provide interpretation of construction requirements as may be needed during construction, and assist the Township in resolution of construction issues. This will include assisting the Township in a final walkthrough inspection and developing a punch list. e Coordinate and attend Preconstruction Meeting and weekly Construction Meetings (2 anticipated). If needed, Crew will host virtual meetings. Issue Notice to Proceed and meeting minutes. e Review Shop Drawings for construction materials and other submittals, including construction schedules and test results, furnished by the Contractor to determine compliance with Contract requirements. e Provide full-time construction observation to measure and record material quantities for payment, monitor Contractor's progress, and verify that work is performed in accordance with the

Page 18

quirements. e Provide full-time construction observation to measure and record material quantities for payment, monitor Contractor's progress, and verify that work is performed in accordance with the Contract requirements e Maintain daily construction reports recording Contractor's activities and work performance, including field sketches for installed work. An electronic copy of these reports and sketches will be provided to the Township at the end of the project upon request.

File revisions (1)