SECTION 1 Scope of Services / Fee Schedule Greenman-Pedersen, Inc. (GPI) understands that the Township of West Orange requires engineering, surveying, and construction management services necessary for the Valley Road, Ashwood Terrace and William Street Improvements. Throughout the firm’s 56-year history, we have provided capital improvement project design to dozens of New Jersey municipalities. We have also served as the municipal engineer for various municipalities throughout the firm’s existence. We are very experienced in providing road reconstruction design, plans, specifications and contract documents of a professional nature in a cost effective and timely manner. We recommend commencing our work with a start-up meeting. This will allow us to understand your concerns and can advance the project in an expeditious manner. Professional services will include a complete design and two (2) separate bid packages as requested in the RFP; one (1) bid package for Valley Road and a separate package for Ashwood Terrace and William Street. Each bid package will include a cost estimate, plans and specifications (twenty copies each) for bidding purposes. We have reviewed the proposed tasks contained in the RFP and we believe we have a clear understanding of the goals of each project as follows: Valley Road, From Freeman Street to Kingsley Street A. Curb and sidewalk replacement. B. From Central Avenue to Kingsley Street Decorative Street lighting through Public Service Enterprise Group (PSE&G) for which Consultant will be responsible for coordinating with PSE&G and incorporating red line diagram in the design for Contractor’s responsibility to install footing, conduit, junction boxes and supplying all else in conjunction as necessary for PSE&G to install poles and the primary electric service as necessary. C. Pavement milling and pavement resurfacing. D. Pavement striping. E. New traffic signs as necessary. F. Shade trees as necessary. G. Drainage structures repairs with new frames, grates, curb pieces as necessary. Repair existing drainage structures as necessary. H. New manhole castings, frames and covers as necessary. Repair existing manholes as necessary. I. Curb ramps as necessary. The total length of this project is approximately 1,850 linear feet. Ashwood Terrace (Entire Length) and

Page 24

d covers as necessary. Repair existing manholes as necessary. I. Curb ramps as necessary. The total length of this project is approximately 1,850 linear feet. Ashwood Terrace (Entire Length) and William Street, From Franklin Avenue to Main Street A. Curb and sidewalk repairs. B. Pavement milling and pavement resurfacing. C. Pavement striping. D. New traffic signs as necessary. E. Shade trees as necessary. F. Drainage structures repairs with new frames, grates, curb pieces as necessary. Repair existing drainage structures as necessary. G. New manhole castings, frames and covers as necessary. Repair existing manholes as necessary. H. Curb ramps as necessary. The total length of this project is approximately 1,980 linear feet. Scope of Services | Page 2

File revisions (1)