Show all pagesProject Schedule | Page 6 SECTION 3 Project Schedule We are committed to adhering to the Township’s goal to advertise for bids by Winter 2024/2025, with a construction start in Summer/Fall 2025. We anticipate work will proceed within one (1) week after the award of contract. GPI has the resources to complete the project in a timely fashion, and we are confident that we can achieve the Township’s goal. We have assumed a March 1, 2024 Notice to Proceed award and have prepared the following Project Schedule: March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 1 Surveying Services 2 Design of Preliminary Plans/Specs 3 Township Review and Comment 4 Final Plans and Specifications for NJDOT 5 NJDOT Review 6 Final Bid Documents March 1, 2024 (Assumed Award & NTP ) Project Schedule