Show all pagesSection 108.11, Title 23 CFR 635.120, NJAC 5:30 and the procedure outlined below. Contract changes must be monitored and documented daily. The Contractor may not deviate from the requirements of the contract unless and until a field order is issued by Resident Engineer upon approval by the RC/PM and NJDOT-BLA. Contract line-item overruns are not permissible without formal requests by the Contractor and approvals by the RC/PM and NJDOT-BLA. All new or supplemental costs must be negotiated, itemized, and justified. In addition, contract time must be evaluated for each change to the contract. All documentation of the negotiations, including the basis of cost, must be on file and included in the change order request. 5.6 Change Orders The Resident Engineer will notify the RC/PM once it becomes apparent that a change to the Plans and/or Specifications is required. After reviewing the Plans and/or Specifications to determine if the change is valid and necessary the RC in conjunction with the RE and/or the consultant who designed the project the potential extra work is and recommended for approval. • The RC/PM notifies NJDOT- BLA once it has been established that a Change Order for changes in the contract quantities or extra work is necessary and prepares a field order (see Section 5.7). The form shall state the description of the change or extra work , reason for the change, value of the change (increases or decreases against the contract price). Time is also evaluated as part of the change order. This form will authorize the Contractor to proceed with the work upon written approval from NJDOT-BLA. • The Contractor shall provide to the RE a detailed cost proposal (materials, labor, equipment, overhead) for extra work. The cost will be reviewed by the RE and RC, documented, and negotiated based on the cost estimate prepared by the RE, under the supervision and approval of the RC, for the extra work presented by the Contractor. Documentation of the negotiated costs will be included in the change order. The change order will be signed by the Contractor, the RE and submitted to the RC for review. If the price for the extra work cannot be mutually agreed upon, Township of West Orange will initiate work by force account as per Section 104.03 of the Standard
ed to the RC for review. If the price for the extra work cannot be mutually agreed upon, Township of West Orange will initiate work by force account as per Section 104.03 of the Standard Specifications. • The RC prepares a Federal Change Order (DC-173A) and submits to NJDOT-BLA for review and approval once Township of West Orange formally approves the change order. The Change Order will serve as a contract document adjusting the contract price . Any amounts in excess of the authorized contract amount cannot be expended until the Change Order is approved. • Work included in the Change Order cannot be invoiced until the DC-173A has been approved by NJDOT-BLA. Time should always be evaluated as part of a change order as it could change the contract time and contract completion date. • The RC/PM will notify NJDOT-BLA if during construction, an inherent job condition should arise, and said condition, if not immediately corrected or changed, would unduly delay the Contractor. Upon the written authorization of the NJDOT-BLA, the Contractor will be instructed by field order and Township of West Orange will proceed with the approval of the time extension change order at the next available Township of West Orange Governing Body meeting. • Changes of 20% or more to the contract will require approval in accordance with NJAC 5:30-11.3 and 11.9. • Changes to the contract may require revision of DBE goals. NJDOT-Civil Rights will 29 | P a g e
File revisions (1)
- Sep 29, 2026
1227a7e49ff07,987,641 bytes