AGREEMENT SUMMARY 2023 TRANSPORTATION ALTERNATIVES SET-ASIDE DESIGN ASSISTANCE WASHINGTON STREET CORRIDOR IMPROVEMENT PROJECT PHASE II CONSULTANT: ADDRESS: OWNER: PROJECT TITLE: TOTAL BUDGET: Greenman - Pedersen, Inc. 301 Gibraltar Drive, Suite 2A Morris Plains, NJ 07950 West Orange Township 25 Lakeside Avenue West Orange, NJ 07052-55623 TAP — 2023 Washington Street Corridor Improvement Project Phase 2 Township of West Orange, Essex County $382,214.78 Federal (FHWA Transportation Alternatives Program) Preliminary Engineering: $155,437.29 Final Design Engineering: $201,347.57 Estimated Construction Engineering Services: $25,429.92 Estimated Page 1 of 66 September 2024 TAP Standard Agreement