e. Equipment. If as the result of the delay, the equipment cannot be used for any active work, and is directed by the RE to remain on the work site during the delay, the Department will make payment as specified in 104.03.08.7.a.5. If as the result of the delay, the RE determines that the equipment cannot be used for any active work, the RE may request the Contractor to remove the equipment. The Contractor may remove the equipment from the work site or allow it to remain. If the equipment is removed from the work site, the Department will make payment for labor and equipment costs to remove the equipment and to return it to the work site at the end of the delay period. If the equipment remains, the Department will not make payment for the equipment as specified in 104.03.08.7. If the equipment is required for additional maintenance within the Project Limits, maintenance of traffic control devices, maintenance of SESC measures, and similar activities resulting from the delay and approved by the RE, the Department will make payment as specified in 104.03.08.7. THE FOLLOWING IS ADDED: 4. Equipment Escalation. If, as the result of the delay, equipment use, which had a planned late-finish date occurring before an equipment rate increase date, is required to start after the equipment rate increase date, the Department will make payment for the following: a. Contractor owned equipment. Equipment costs as specified in 104.03.08 at the higher rate as evidenced by a comparison of the Blue Book rate between the planned late finish date for the work and the Blue Book rate when the work was required because of the delay. b. Rented equipment. Equipment costs as specified in 104.03.08 at the higher rate as evidenced by a comparison of rental agreements, including paid invoices, between the planned late finish date for the work and the date the work was required because of the delay. If rental agreements and paid invoices are not available, provide quotes from the rental company for both dates. SECTION 105 – CONTROL OF

Page 241

delay. If rental agreements and paid invoices are not available, provide quotes from the rental company for both dates. SECTION 105 – CONTROL OF WORK 105.01 AUTHORITY OF THE DEPARTMENT 105.01.01 RE REVISE THE SECOND PARAGRAPH TO: Unless otherwise specified, send correspondence with the Department to the RE. Where correspondence is specified to be directed to persons other than the RE, send a copy to the RE. Ensure that correspondence complies with the following: 1. Assign every correspondence sent to the Department a unique correspondence serial number in the subject line, numbered sequentially beginning with Contractor Correspondence No. 1. 2. If the correspondence includes a request for information or asks for an interpretation of the Contract, also assign a unique RFI serial number in the subject line numbered sequentially beginning with RFI-1. 3. If the correspondence constitutes a notice of change, assign a unique change notice serial number in the subject line numbered sequentially beginning with Change Notice No. 1. For subsequent correspondence referring to a change notice or to the events that are the subject of a previous change notice, refer in the subject line to the original change notice number. 105.02 RESPONSIBILITIES OF THE CONTRACTOR 105.02.05 Civil Rights Requirements REVISE SECTION 105.02.05.1 TO THE FOLLOWING: HELEN AVE., LAWRENCE AVE., FLORENCE PL., AND LOWELL AVE., IMPROVEMENTS PROJECT Page 11 of 76

File revisions (1)