correct conditions unsafe for the workers or the general public, for failure to carry out provisions of the Contract, including but not limited to failure to develop, submit, implement, and maintain the ITCP. 108.07.01 Interference THE SECOND PARAGRAPH IS CHANGED TO: Schedule and perform the Work so that successive construction operations and lane or roadway openings follow preceding operations as closely as possible. Limit work zones according to the Special Provisions. Confine construction operations adjacent to traffic to one side of the roadway at a time unless otherwise specified by the Contract. Where the Work is performed in stages adjacent to traffic, ensure that the road opened to traffic adequately accommodates traffic. Do not interfere with existing traffic access, except when required to perform the Work or as approved by the RE. THE FOLLOWING NEW SUBPART IS ADDED: 108.09 MAINTENANCE WITHIN THE PROJECT LIMITS THE FOLLOWING IS ADDED: Any damage to the Roadway due to the Contractor’s operations shall be repaired at no Additional Compensation, except as specified in 107.11. The Contractor shall complete within 24 hours specific repairs directed by the RE, except where the requirements are specified elsewhere. Nothing in this Subsection shall be construed to limit or change the risks assumed by the Contractor as specified in 107.11. 108.10 CONTRACT TIME THE ENTIRE SECTION IS DELETED AND REPLACED WITH THE FOLLOWING: Please refer to the CONTRACT AND AGREEMENT Section in the front end of these specification for the contract time requirements. 108.11.01 Extensions to Contract Time THIS SUBSECTION IS CHANGED TO: C. Submitting Time Impact Evaluation. If an excusable delay occurs, notify the RE, detailing how the event or cause is affecting the approved progress schedule that is current at the time the delay occurred. When the full extent of the impact on the approved progress schedule can be determined, submit a request for an extension of Contract Time to the RE with a Time Impact Evaluation Form and a CPM fragnet diagram including all additional work, and the fragnet’s relationship to the approved progress schedule that is current at the time the delay occurred. Clearly identify how each change or delay is represented by an activity or group of activities. Ensure that the fragnet shows logic revisions, duration changes, and new activities,

Page 251

the delay occurred. Clearly identify how each change or delay is represented by an activity or group of activities. Ensure that the fragnet shows logic revisions, duration changes, and new activities, including the predecessor and successor relationships. The Contractor is considered to have waived its rights to claim an extension of Contract Time, if the Contractor fails to provide written notice or fails to provide the time impact evaluation. The RE will evaluate the time impact evaluation. The Department will only extend Contract Time when delay causes the work to be extended beyond the scheduled Contract Time as specified in 108.10. If the Contractor is already behind schedule and an excusable delay delays the work beyond the Contract Time as specified in 108.10, the Department will only extend Contract Time for the amount of time that directly results from the excusable delay. If the Department determines that an extension of Contract Time is warranted, the Department will extend Contract Time by a Change Order. For excusable, compensable delays, submit a request for and documentation supporting the entitlement to compensable delay damages associated with the delay. 108.14 DEFAULT AND TERMINATION OF CONTRACTOR’S RIGHT TO PROCEED LIST ITEM (1) OF THE FIRST PARAGRAPH IS CHANGED TO: HELEN AVE., LAWRENCE AVE., FLORENCE PL., AND LOWELL AVE., IMPROVEMENTS PROJECT Page 21 of 76

File revisions (1)