Show all pagesMA 2025 NJDOT Aid Program Section IV. Project Schedule We are committed to adhering to the Township’s goal of advertising for bids by Spring 2026 and starting construction in Summer/Fall 2026. We anticipate work will proceed within eight (8) months after the contract is awarded. GPI has the resources to complete the project promptly, and we are confident that we can achieve the Township’s goal. March 2026 February 2025 January 2026 December 2025 November 2025 October 2025 September 2025 August 2025 December 16, 2024 (Assumed Award & NTP ) We have assumed a December 16, 2024 Notice to Proceed award and have prepared the following Project Schedule: 1 Surveying Services 2 Design of Preliminary Plans/Specs 3 Township Review and Comment 4 Final Plans and Specifications for NJDOT 5 NJDOT Review 6 Final Bid Documents Section IV | Page 7