Page 192

The FOLLOWING IS ADDED: Before any milling operations, the Contractor shall provide the construction baseline layout and survey notes to the RE after performing the field layout. Also, before milling operations the Contractor's licensed surveyor shall obtain and verify existing grades and provide the RE with grading/cut sheets for review before any milling operations and/or construction of any asphalt. The Contractor's licensed surveyor shall provide, ata minimum, grades along the baseline/centerline, points of noticeable grade changes in the cross slopes, gutter line, and/or edge of road and top of curb at fifty (50) foot intervals along with all inlets and manholes. The grading/cut sheets shall provide a finished paving grade that provides positive drainage flow in a surface mat laid in a uniform layer. Prior to completing this task, the Contractor shall meet with the RE to confirm that this information is desired on all roadways. The RE reserves the right to eliminate this work on one or more roadways during construction. Layout of work shall be adjusted in the field to meet site conditions as approved in writing by the professional engineer responsible for the design. The contractor is responsible to layout all new work prior to construction for Field Engineer's approval. Any locations not approved by the Field Engineer and installed by the contractor shall be removed and replaced as per the Field Engineer's instructions at no additional cost to the owner. All layout work shall be done by a New Jersey Licensed Land Surveyor. The Horizontal Datum is based upon NAD’83. 157.04 MEASUREMENT AND PAYMENT THE FOLLOWING IS ADDED: Item Pay Unit CONSTRUCTION LAYOUT STANDISH AVENUE LUMP SUM SECTION 158 — SOIL EROSION AND SEDIMENT CONTROL AND WATER QUALITY CONTROL 158.04 MEASUREMENT AND PAYMENT THE SECTION AND ALL PAY ITEMS ARE DELETED AND REPLACED WITH THE FOLLOWING: The contractor is responsible to have all soil erosions and sediment control measures in place and maintained throughout construction in accordance with the plans, the latest edition The Standards for Soil Erosion and Sediment Control in New Jersey, all applicable specifications of this section, industry standards or as directed by the local Soils Conservation district or as directed by the Engineer. The cost for all necessary Soil Erosion and Sediment Control Measures shall be included under

Page 192

industry standards or as directed by the local Soils Conservation district or as directed by the Engineer. The cost for all necessary Soil Erosion and Sediment Control Measures shall be included under the pay item SOIL EROSION & SEDIMENT CONTROL MEASURES. THE FOLLOWING ITEM IS ADDED: Pay Item Pay Unit SOIL EROSION & SEDIMENT CONTROL MEASURES LUMP SUM 12

File revisions (1)