and further agrees to obey all lawful rules and regulations and to meet all lawful requirements by all duly authorized state or federal officials, and said Professional agrees to indemnify and save harmless the Township from any such contributions or taxes or liability therefore. 24. EQUAL EMPLOYMENT OPPORTUNITY Professional acknowledges that he/she shall comply with the requirement of N.J.S.A. 10:5-31, et seq. and N.J.A.C. 17:27 as set forth in Exhibit C entitled “Affirmative Action”, and submit to the State of New Jersey and/or the Township such documentation as shall be required by law as more specifically set forth in Exhibit D entitled "Mandatory Equal Employment Opportunity Language." 25. STATE REQUIRED RECORD RETENTION N.J.S.A. 52:15C-14(d) and N.J.A.C. 17:44-2.2 The Professional shall maintain all documentation related to products, transactions or services under this contract for a period of five years from the date of final payment. Such records shall be made available to the New Jersey Office of the State Comptroller upon request. Refusal by the Professional to provide information upon request by the State Comptroller or otherwise impede or fail to cooperate with any audit or performance review, the State Comptroller may recommend to the Township that the person be subject to termination of their contract, or temporarily or permanently debarred from contracting with the Township. The Professional shall maintain all documentation related to products, transactions or services under this contract for a period of five years from the date of final payment. Such records shall be made available to the New Jersey Office of the State Comptroller upon request. Upon refusal by Professional to provide information upon request by the State Comptroller or otherwise impede or fail to cooperate with any audit or performance review, the State Comptroller may recommend to the Township that the person be subject to termination of their contract, or temporarily or permanently debarred from contracting with the Township. 26. DEFAULT In the event the Professional fails or neglects to perform any of the conditions or

Page 83

covenants set forth herein during the Term of this Agreement, the Township shall upon three (3) days written notice to the Contractor, deliver to the Contractor by Certified Mail a Notice of Default, with the opportunity to cure within three (3) days. In the event that the Contractor fails to cure such default within three (3) days of receipt of the Notice, the Township shall terminate this Agreement, and all rights, privileges, or interest herein shall cease. The Professional shall be liable to the Township for any damages or loss, including, but not limited to reasonable attorneys’ fees in the event any legal action is necessary, as a result of the Default. IN WITNESS WHEREOF, this Agreement has been executed on the day first noted above, for the purposes and the terms specified herein. TOWNSHIP OF WEST ORANGE: ___________________________ By: ___________________________ Attest: HERBST-MUSCIANO, LLC ___________________________ By: ___________________________ Attest:

Page 84

300-26 EXHIBIT A PROPOSAL FOR SERVICES

Page 85

300-26 EXHIBIT B HERBST-MUSCIANO MUNICIPAL RATE SHEET

Page 86

300-26 EXHIBIT C AFFIRMATIVE ACTION

Page 87

300-26 EXHIBIT D MANDATORY EQUAL EMPLOYMENT OPPORTUNITY LANGUAGE

Page 88

300-26 October 13, 2026 Zayibeth Carballo, PE Municipal Engineer Township of West Orange 25 Lakeside Avenue West Orange, NJ 07052 SUPPLEMENTAL A/E SERVICES PROPOSAL FOR: Interior Alterations for Restrooms Improvements Second Floor Tenant 10 Rooney Circle, West Orange, NJ A. PROJECT DESCRIPTION 1. Herbst-Musciano, LLC will include the following in the project documents: a. Check water pressure and function of existing pressure reducing valve. b. Replace existing WCs and Urinals completed with flush valves. c. Removal and replacement of ceramic floor tile. d. Clothing hanger rods for men's shower area. e. Countertop trash opening and trash bin f. Secure restroom supply storage. g. New GFIC outlet receptacles at men's and women's vanities. B. ARCHITECTURAL DESIGN SERVICES 1. CONSTRUCTION DOCUMENTS PHASE i. Include the above items in the contract drawings and specs C. COMPENSATION 1. A fixed fee payable monthly in proportion to services rendered, with overall lump sum fee attributed generally as follows: Task 2. Staff Architect Est. ManHrs 16 MEP Engineer Plumber Av. Hourly Rate Fee $ 175 2,800. 12 200 2,400. 4 250 1,000. Notes Man-Hrs are for reference only Man-Hrs are for reference only Check water pressure and regulator TOTAL SERVICES $ 6,200. Billing shall be made monthly in proportion to services rendered and payment is appreciated within 30 days of date of invoice. I hope that this is acceptable. Please contact me if you have any questions. Sincerely, Gary Musciano, AIA, PP HERBST-MUSCIANO, LLC Architecture & Planning New Jersey Certificate of Authorization AC 830 611 Main Street, Second Floor, Boonton, New Jersey 07005 Tel 973 538 3815 Fax 973 538 4095 www.herbstmusciano.com

Page 89

2026 RATE SCHEDULE 300-26 Time Based Billing Rates Principal Architect $ 190. /hr. Staff Architect / Project Manager $ 175. /hr. MEP Engineer $ 175. /hr. Sr. Designer / Field Technician $ 145. /hr. Designer / Drafter / Field Technician $ 110. /hr. Jr. Designer / Drafter / Field Technician $ 94. /hr. Administrative / Clerical Support $ 84. /hr. Reimbursable Expenses Sub-Consultants Invoice + 10 percent Airfare, train, automobile rental & fuel, automobile Mileage, parking, taxi, shipping & printing expenses Cost + 10 percent Conditions 1. 2. 3. Hourly rates include all direct and indirect overhead and general administrative costs, including equipment and materials required to perform services, unless otherwise noted. Rates exclude costs associated with scheduling that requires workdays in excess of eight hours and work on weekends and holidays or fast tracked and rushed scheduling. Billing time will commence and terminate from portal to portal at 611 Main Street, Boonton, New Jersey. HERBST-MUSCIANO, LLC Architecture & Planning New Jersey Certificate of Authorization AC 830 611 Main Street, Second Floor, Boonton, New Jersey 07005 Tel 973 538 3815 Fax 973 538 4095 www.herbstmusciano.com

Page 90

300-26 REQUIRED EVIDENCE AFFIRMATIVE ACTION REGULATIONS N.J. S.A. 10:5-31, et seq. (N.J.A. C. 17:27) If awarded a contract, the Bidder will be required to comply with the requirements of N.J.S.A. 10:531, et seq., and N.J.A.C,_ 17:27. Within five (5) days after receipt of the notification of intent to award the contract, the Bidder shall present one of the following: 1. Appropriate evidence that the Contractor is operating under an existing federally approved or sanctioned affirmative action program; or 2. A Certificate of Employee Information Report Approval issued in accordance with N.J.A.C. 17:27-4; or 3. An initial Employee Information Report consisting of forms provided by the Affirmative Action Office and completed by Contractor in accordance with N.J.A.C. 17:27-4. The Bidder must submit no later than three (3) days after the signing of the Contract an Initial Project Manning Table consisting of forms provided by the Affirmative Action Office and completed by Contractor in accordance with N.J.A.C. 17:27-7. Bidders are referred to the Bidder's Information Section of the Bid Packet for a further description of the above requirements. NO BIDDER MAY BE ISSUED A CONTRACT UNLESS THEY COMPLY WITH THE AFFIRMATIVE ACTION REGULATIONS OF N.J.S.A. 10:5-31, et seq. The following questions must be answered by all Bidders: 1. Do you have a federally-approved or sanctioned Affirmative Action Program? Yes ________ (If yes, submit a copy of such approval.) 2. No Do you have a State Certificate of Employee Information Report approval? Yes ________ {If yes, submit a copy of such approval.) No The undersigned Bidder certifies that he is aware of the commitment to comply with the requirements of N.J.S.A. 10:5-31, et seq., and agrees to furnish the required documentation pursuant to the law. COMPANY: _____________________________ NAME: ____________________________ SIGNATURE: ____________________________ TITLE: ____________________________

Page 91

NOTE:A bid must be rejected as non-responsive if a Bidder fails to comply with requirements of N.J.S.A. 10:5-31, et seq., within stipulated time.