Supporting Documentation · Mar 20, 2025
ZB 22 13 2023 04 06 Twp Resubmission Letter
39f16dbaa7006bb91b6ec646266d4f680744e80bfe6613209751e7f735f4f2d0Indexed text · page 2
Show all pagesTownship of West Orange April 6, 2023 Page 2 of 2 • Six (6) signed and sealed copies of the Tree Removal Report, prepared by our office, dated October 2022, last revised April 2023; and • Six (6) signed and sealed copies of the Preliminary and Final Site Plan Drawings, prepared by our office, dated 11/9/2022, last revised 3/31/2023. Please review the enclosed documents towards issuance of Site Plan Approval for the above referenced project. Should you have any questions or require additional information, please do not hesitate to contact the undersigned. Sincerely, DYNAMIC ENGINEERING CONSULTANTS, PC Matthew Bersch, PE Danny Goncalves Enclosures cc: Benjamin T.F. Wine, Esq. (via email) Ed Baksh (via email) Lawrence BenBassett (via email)