Town CrierWest Orange, New Jersey
← Back to search

Supporting Documentation · Feb 12, 2025

EX Flow 2240719_JC_JF_Memo

Preserved file SHA-256ec3577dcdf103623d157924fc1fd8184e59b1c02a38ce7edf79684f28aa820a8

Indexed text · page 2

Show all pages
Page 2

Project No. 24006174A July 19, 2024 Page 2 | 9 42 Eagle Ridge Way. When the contractor was responding to the HEP SCD directive, he encountered two (2) 12” collapsed clay pipes at the outfall. The intention was to repair and improve this item as part of the cleaning and repair process, not to increase velocity existing at the outfall. The contractor believed that a flatter and wider pipe with a larger surface area should diminish the flow compared to dual 12-inch pipes. Figure 1: 36” Elliptical Outfall per Omland and Osterkorn Interim As-Built Plan

File revisions (1)