Supporting Documentation · Feb 12, 2025

EX Flow 2240719_JC_JF_Memo

Preserved file SHA-256ec3577dcdf103623d157924fc1fd8184e59b1c02a38ce7edf79684f28aa820a8

Indexed text · page 5

Show all pages
Page 5

Project No. 24006174A July 19, 2024 Page 5 | 9 Figure 4: Proposed OCS Location Figure 5: OCS Design Detail The OCS will be located at the midpoint of the 36” RCP pipe and will contain two (2) 10” orifices that will restrict the flow through the existing 36” elliptical RCP pipe outflow. The below table summarizes the existing and proposed peak flows and peak velocities through the pipes.