Show all pages300 Tice Boulevard Suite 101 Woodcliff Lake, NJ 07677 Main: 877 627 3772 PROPOSED SEQUENCING SCHEDULE (DATES TO BE COMPLETED PER TOWNSHIP AUTHORIZATION) 1. Permit for outfall structure: a. Permit: Timing/start is pending Township authorization b. Work: 2-4 Weeks from permit approval, dependent on production of pre-cast double chamber Outlet Control Structure 2. Permit for wall: a. Permit: Timing/start is pending Township authorization b. Work: Up to 5 working days 3. Major Site Plan Development: a. Application & Plan Deliverable: Timing – On or before August 19, 2024 b. Township Review: 2 Weeks (Anticipated) c. Target Site Plan Review Meeting: 9/10/24 d. Site Plan Board: Dependent on Site Plan Committee Review