Show all pagesDAILY FIELD REPORT DFR No. 001 Date: 02/18/2025 Page 2 of 5 PROJECT NO.: 24006174A PROJECT/LOCATION: 40 Eagle Ridge Way, West Orange, NJ Items reviewed during today’s site visit were limited to those specifically discussed above. REPORT PREPARED BY: Francisco Sanchez-Dominici REVIEWED BY: Varunpreet Singh TP-11 (12:50 – 12:10) • Mobilized excavator to test pit location. • Test pit terminated at 9 ft below existing grades due to refusal on bedrock. • Test pit backfilled to surface with excavated soil. TP-12 (14:05 – 14:20) • Mobilized excavator to test pit location. • Test pit terminated at 12.5 ft below existing grades due to refusal on bedrock. • Test pit backfilled to surface with excavated soil.