Show all pagesMavis Tire Supply, LLC May 5, 2026 Page 8 of 21 14. The existing and proposed drainage area maps and hydrograph summary reports must be revised to separate the drainage areas between which stormwater enters the underground pipe system and which stormwater sheet flows off site. Response: The enclosed Stormwater Report has been revised to separate drainage areas and hydrograph summary reports between underground piping and off-site sheet flow. 15. The maintenance plan should be revised to include as-built construction plans of the stormwater management measures and copies of pertinent construction documents such as laboratory test results, permits and completion certificates. Response: The enclosed Stormwater Management Operation and Maintenance Manual has been revised to include as-built construction plans of the stormwater management measures. 16. The maintenance plan should be revised to note that the party responsible for maintenance must submit to the Township every May 1st an annual maintenance report including all preventative and corrective maintenance for the structural stormwater management measures incorporated into the design of the development. Response: The enclosed Stormwater Management Operation and Maintenance Manual has been revised to note the Township submittal requirement of an annual maintenance report, by the party responsible for maintenance. 17. The maintenance plan must be revised to include the language from §25-29.13 (Stormwater License and Inspection Requirements). Response: The enclosed Stormwater Management Operation and Maintenance Manual has been revised to include the requested language from the Township Code section §25-29.13. 18. As stipulated in §25-29.12b7(d), the party responsible for maintenance of the site's stormwater system must post a two-year maintenance guarantee in accordance with N.J.S.A. 49:55D-53. Response: Acknowledged. 19. The stormwater management operation and maintenance manual and any future revisions must be recorded upon the deed of record for the property. Prior to recording, the form of the deed must be approved by the Board Attorney and our office. Response: Acknowledged. 20. There is a discrepancy between sheet 6 and the 'Underground Basin Outlet Control Structure' Detail on sheet 16 regarding the rim elevation. Revise plans accordingly. Response: The site plan drawings have been revised to
ncy between sheet 6 and the 'Underground Basin Outlet Control Structure' Detail on sheet 16 regarding the rim elevation. Revise plans accordingly. Response: The site plan drawings have been revised to eliminate discrepancy on rim elevation between plans and the “Underground Basin Outlet Control Structure Detail”.
File revisions (1)
- Sep 29, 2026
0741d19ba1a6475,440 bytes