12 ○ Mr. Schkolnick clarified that addressing those comments would be a matter of resolution compliance. - Mr. Misarti also referenced Ms. Apte's June 2026 planning review letter, which contained comments regarding landscaping, trees, fences, additional information, approvals from other agencies, and required variances. He asked whether those comments would also be incorporated into the revised site plans. Mr. Cote confirmed that the applicant had agreed to address Ms. Apte's comments as part of resolution compliance. - Ms. Micaela Bennett of Old Indian Road asked Mr. Cote to explain what existing condition or engineering deficiency made the proposed new traffic signal necessary. Mr. Cote explained that the traffic-related safety elements had already been addressed through testimony from the applicant's traffic engineer. He stated that, from a civil engineering standpoint, the project would improve existing drainage conditions along Eagle Rock Avenue. - Ms. Bennett asked how much additional impervious surface would be created by the proposed driveway, parking, and roadway improvements. Mr. Cote stated that the project would create approximately 12,000 square feet of additional impervious surface on-site, slightly more than one-quarter acre, and approximately 9,900 square feet of additional impervious surface off-site along Eagle Rock Avenue. He stated that the total additional impervious surface would be approximately one-half acre. - Ms. Bennett requested the existing and proposed stormwater runoff rates for the 2-year, 10-year, 25-year, and 100-year storm events. Mr. Cote explained that the stormwater analysis was divided into two areas, with one discharge point near the intersection of Eagle Rock Avenue and Laurel Avenue and the other at the eastern end of the site. He stated that the calculations considered both current storm events and future storm events based on projected conditions for the year 2100. Mr. Cote provided the following existing and proposed peak flow rates for Point of Analysis 1, located near Eagle Rock Avenue and Laurel Avenue, under current storm conditions: ○ 2-year storm: 13.48 cubic feet per second (CFS) existing and 11.32 CFS proposed. ○ 10-year storm: 23.47 CFS existing and 19.76 CFS proposed. ○ 100-year storm: 44.56 CFS existing and 38.87 CFS proposed. - Mr. Cote provided the following rates for Point of Analysis 1 under future

Page 12

d. ○ 10-year storm: 23.47 CFS existing and 19.76 CFS proposed. ○ 100-year storm: 44.56 CFS existing and 38.87 CFS proposed. - Mr. Cote provided the following rates for Point of Analysis 1 under future storm conditions: ○ 2-year storm: 16.83 CFS existing and 14.07 CFS proposed. ○ 10-year storm: 29.21 CFS existing and 24.77 CFS proposed. ○ 100-year storm: 58.39 CFS existing and 53.61 CFS proposed. - Mr. Cote provided the following existing and proposed peak flow rates for Point of Analysis 2, located at the other end of the site, under current storm conditions: ○ 2-year storm: 9.63 CFS existing and 5.67 CFS proposed. ○ 10-year storm: 17.05 CFS existing and 10.31 CFS proposed. ○ 100-year storm: 37.74 CFS existing and 23.96 CFS proposed. - Mr. Cote provided the following rates for Point of Analysis 2 under future storm conditions: ○ 2-year storm: 11.97 CFS existing and 7.27 CFS proposed. ○ 10-year storm: approximately 21.2 CFS existing and 14.02 CFS proposed. ○ 100-year storm: 42.47 CFS existing and 31.63 CFS proposed. - Ms. Bennett asked where stormwater from the modified site would discharge. Mr. Cote explained that the proposed stormwater connections would be located within Eagle Rock Avenue, with pipes running east and west of Oval Road and connecting to the existing County stormwater drainage system near the limits of the project.

File revisions (1)