HIERIBIST MUSCIANO 1. An EPA Accredited Asbestos Project Designer will generate two separate written scope documents for each Firehouse. These documents will be submitted to the local construction official wnen securing a permit to conduct the work. 2 EHI will generate separate plans for the abatement at each location. EHI will issue approval letters for submission to the local construction official when securing a permit to conduct the work. 3. EHI will provide assistance to the abatement contractor in securing construction permits. EHI will review all required notifications prior to the initiation work. EHI in its capacity as the ASCM will notify the NJ DCA as required prior to the initiation of work. 4, EHI will assist in logistics meetings including bid walks & bidder de-scope interviews. TASK 1; Flat Fee of $ 3,000.00 per Fire Station TASK 2: Asbestos Abatement Project Monitoring, Air Testing & Final Report Generation 1 EH! shall provide project monitoring and air testing services for each individual abatement activity conducted as required by State and Federal Regulations. Monitoring will conform to the requirements for non occupied buildings. 2 EHI shall document that the abatement contractor follows all state and federal regulations pertaining to this type of work. EHI shall review that all applicable documents, ¢.g., abatement contractor licensing, state and federal Notification and local building department permits. 3. EHI will be responsible for maintaining a daily log of abatement activities. At a minimum, this log will track workers’ names and permit numbers, a description of the work completed for each shift, and all testing/inspection results. This log will be compiled and included as part of the final project report due to the owner at the completion of the project. 4, EHI shall conduct pre-abatement and daily air sampling as required by Federal and State Asbestos Regulations. All air sample analysis will be done by our subcontract laboratory in accordance with NIOSH Method 7400. D: EHI shall perform inspections of the work site, including entering the containment area, to ensure all work procedures are being follows. 6. EHI shall participate in any governmental regulatory on site inspections (EPA, NJ DOL, NJ DCA, etc.) 7. EHI shall perform a final inspection of the work area to ensure that all asbestos materials have

Page 10

HI shall participate in any governmental regulatory on site inspections (EPA, NJ DOL, NJ DCA, etc.) 7. EHI shall perform a final inspection of the work area to ensure that all asbestos materials have been properly abated and conduct clearance air monitoring as required by the State of New Jersey. Final air testing is by Transmission Electron Microscopy via AHERA Methodology for work areas larger than 160 square feet or 260 linear feet. 8. EHI's project manager shall attend job meetings and respond immediately to any asbestos or environmental related issues or concerns. 9, A final report will be issued. Architecture & Planning NJ Certificate of Authorization AC 830 611 Main Streel, Second Floor, Boanton, NJ 07005 Telephone 973 538 3815 Facsimile 973 538 4095 www.herbstmusciano.com 22

File revisions (1)