Show all pagesS & HConstruction & Mechanical, Inc. General Contractors · Sprinkler · Plumbing · Heating · Design CHANGE ORDER REQUEST Owner: Township of West Orange Construction Mngr: Architect: Arcari & Iovino Contractor: H&S Construction Project: West Orange Public Library Field: COR #: 3 To Contractor: Initiation date: H&S Construction & Mechanical Inc. Project No: 22-044 721 Bayway Ave Contract For: Completion Contract Elizabeth NJ 07202 Contract Date: The Contract is changed as follows: Removal of existing ductwork not shown on new work plans per RFI#7 Item Description Company Totals 1 Duct removal (see attached proposal) Airside sheetmetal $ 20,881.26 2 3 4 Sub-Contractor Subtotal $ 20,881.26 H&S - Overhead & Profit Of Sub Cost $ 1,044.06 Sub
H&S - Overhead & Profit Of Sub Cost $ 1,044.06 Sub Contractors Total $ 21,925.32 Item Description Company Totals 5 Dumpsters H&S $ 1,600.00 6 PM time 5x $150per hour H&S $ 750.00 7 H&S 8 H&S 9 H&S 10 11 Contractor Subtotal $ 2,350.00 H & S - Overhead & Profit 15% of Contractor Cost $ 352.50 Contractors Total $ 2,702.50 Sub Total $ 24,627.82 H&S Bond Cost $ 738.83 Total $ 25,366.66 The contract time will be increased by: 5 days
File revisions (1)
- Sep 29, 2026
612e3d69654b321,706 bytes