Page 1

WATA Document G701' - 2017 Change Order PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: West Orange Public Library Contract For: General Construction Change Order Number: 002 10 Rooney Circle Date: Date: September 1, 2022 ‘West Orange, NJ 07052 OWNER: (Name and address) ARCHITECT: (Name and address) CONTRACTOR: (Name and address) Township of West Orange Arcari + lovino Architects, P.C. H&S Construction and Mechanical, Inc. 66 Main Street One Katherine Street 721 Bayway Avenue West Orange, NI 07052 Little Ferry, NJ. 07643 Elizabeth, NJ 07202 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives.) Demolition of Existing Ductwork (COR #3). Add $25,366.66 The original Contract Sum was ‘The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be increased by this Change Order in the amount of The new Contract Sum including this Change Order will be ‘The Contract Time will be unchanged by Zero (0) days. ‘The new date of Substantial Completion will be NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Own id Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. OWNER (Firm name) SIGNATURE Anthony Tovino, President Daniel Hemandez, President PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE 9/1/22. G-1- AR DATE DATE DATE AIA Document G701” ~ 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017 by The American it rchitects. All rights reserved. The American institute ef Archilests Al the AIA Logo. and “Ale Contract Bocoments are cegstired Wauaniat y Pot he Used wilhieal permission This document was produced by AIA software at 10:03:26 ET an 09/01/2022 under Order No.2114292317 which expires on 02/22/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents” Terms of Service. To reparl copyright violations, e-mall copyright@ala.org. User Notes: (3B9ADA3D)

Page 2

S & HConstruction & Mechanical, Inc. General Contractors · Sprinkler · Plumbing · Heating · Design CHANGE ORDER REQUEST Owner: Township of West Orange Construction Mngr: Architect: Arcari & Iovino Contractor: H&S Construction Project: West Orange Public Library Field: COR #: 3 To Contractor: Initiation date: H&S Construction & Mechanical Inc. Project No: 22-044 721 Bayway Ave Contract For: Completion Contract Elizabeth NJ 07202 Contract Date: The Contract is changed as follows: Removal of existing ductwork not shown on new work plans per RFI#7 Item Description Company Totals 1 Duct removal (see attached proposal) Airside sheetmetal $ 20,881.26 2 3 4 Sub-Contractor Subtotal $ 20,881.26 H&S - Overhead & Profit Of Sub Cost $ 1,044.06 Sub

Page 2

H&S - Overhead & Profit Of Sub Cost $ 1,044.06 Sub Contractors Total $ 21,925.32 Item Description Company Totals 5 Dumpsters H&S $ 1,600.00 6 PM time 5x $150per hour H&S $ 750.00 7 H&S 8 H&S 9 H&S 10 11 Contractor Subtotal $ 2,350.00 H & S - Overhead & Profit 15% of Contractor Cost $ 352.50 Contractors Total $ 2,702.50 Sub Total $ 24,627.82 H&S Bond Cost $ 738.83 Total $ 25,366.66 The contract time will be increased by: 5 days

Page 3

Change Order Request August 23, 2022 Ductwork / Sheet Metal Fabrication / Installation Dust & Fume Control Miad Ghaffari H&S Construction 721 Bayway Avenue Elizabeth, NJ 07202 RE: West Orange Public Library RE: Demolition of Existing Ductwork COR #1 We are pleased to provide our changed order after we were requested to demolish additional existing ductwork to make room for the new work. There is about 1100 additional linear feet of ductwork requested to demolished. The additional ductwork is shown highlighted in red sent to Airside on Monday, August 22 at 2:43pm. We are to carry demolished ductwork to dumpsters (provided by others) in parking lot within 100 ft of the building. Two men can demo between 180’-200’ of ductwork to dumpsters in a day. We are pleased to provide a cost of $20,881.26. Airside Inc. Hereby proposes provide all labor, equipment and material necessary to complete the work for the net total lump sum amount of $20,881.26, detailed as followed: Exclusions • New Work • Demo of Anything that is NOT Ductwork • Providing of Dumpsters • Any work not explicitly explained above or in the following Change Order Breakout Sheet Thank you. Michael Selvaggi Estimating 246 Brighton Road • Andover, NJ 07821 • Phone: (973) 786-6967 • Fax: (973) 786-6949

Page 4

Airside, Inc. Date: 8/23/2022 Tax on Material 0% Total of Material $ 1,500.00 Cost Breakdown Rev. Date Labor Rate Total of Labor Cost $ 16,357.62 Project: West Orange Public Library Foreman $ 167.82 Total of lump sum item's $ 300.00 Journeyman $ 162.53 Sub Total $ 18,157.62 Based on The Following : Mixed Rate $ 165.18 Overhead 10% $ 1,815.76 Demolition of Additional Existing Ductwork Shop Rate $ 162.53 Profit 5% $ 907.88 Change Order 1 PM/ Drafting Rate $ 167.82 Total $ 20,881.26 Items Of Extension ( with Tax on Material ) ITEM Description Qnt'y Material Hours Lump Sum Material Hrs.Total Labor Lump Sum TOTAL Demo of About 1100 Linear Feet of Exisiting Ductwork @ 200'/Day to Dumpsters provided by Others 1 $ - 0 $ - $ - 96 $ 15,856.80 $ - $ 15,856.80 Lift Rental 1 $ - 0 $ - $ 1,000.00 0 $ - $ - $ 1,000.00 Sawzal Blades, Misc Material 1 $ - 0 $ - $ 500.00 0 $ - $ - $ 500.00 PM Time 1 $ - 0 $ - $

Page 4

- $ 500.00 0 $ - $ - $ 500.00 PM Time 1 $ - 0 $ - $ - 2 $ 335.64 $ - $ 335.64 Delivery 1 $ - 1 $ 300.00 $ - 1 $ 165.18 $ 300.00 $ 465.18 $ - $ - Totals of Above = $ 1,500.00 99 $ 16,357.62 $ 300.00 $ 18,157.62