Change Order AIA Document G701 - 2017 PROJECT: (Name and address) West Orange Public Library 10 Rooney Circle West Orange, NJ 07052 OWNER: (Name and address) Township of West Orange 66 Main Street West Orange, NJ 07052 CONTRACT INFORMATION: Contract For: General Construction Date: ARCHITECT: (Name and address) Arcari + Iovino Architects, P.C. One Katherine Street Little Ferry, NJ 07643 CHANGE ORDER INFORMATION: Change Order Number: 008 Date: January 4, 2023 CONTRACTOR: (Name and address) H&S Construction and Mechanical, Inc. 721 Bayway Avenue Elizabeth, NJ 07202 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives.) Additional electrical devices per SK.6A & SK.6B (COR#/3). Add $6,811.93 ‘The original Contract Sum was $ 5,075,000.00 The net change by previously authorized Change Orders $ 79,041.13 The Contract Sum prior to this Change Order was $ 5.154,041.13 The Contract Sum will be increased by this Change Order in the amount of $ 6,811.93 The new Contract Sum including this Change Order will be $ 5,160,853.06 The Contract Time will be unchanged by Zero (0) days. ‘The new date of Substantial Completion will be NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, shat have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owgér ahd Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. Township of West Orange H&S Construction and Mechanical, Inc. OWNER (Firm name) CONTRACTOR (Firm name) SIGNATURE SIGNATURE SIGNATURE Anthony Iovino, President Daniel Hernandez, President PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE tf 2023 DATE . DATE DATE ‘AIA Document G701™ ~ 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The “Amercan Institute of Architects,” 'AIA.” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 11:42:22 ET on 01/04/2023 under Order No.2114292317 which expires on 02/22/2023, is not for resale,

Page 1

red trademarks and may not be used without permission. This document was produced by AIA software at 11:42:22 ET on 01/04/2023 under Order No.2114292317 which expires on 02/22/2023, is not for resale, is licensed for one-time. use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (3B9ADA39) 1

Page 2

S & HConstruction & M echanical, Inc. G e n e ra l C o n tra c to r s · S p rin k le r · P lu m b in g · H e a tin g · D e s ig n CHANGE ORDER REQUEST Owner: Township of West Orange Construction Mngr: Date: 11/28/22 Architect: Arcari & Iovino Contractor: H&S Construction Project: West Orange Public Library Field: COR #: 13 To Contractor: Initiation date: H&S Construction & Mechanical Inc. Project No: 22-044 721 Bayway Ave Contract For: Completion Contract Elizabeth NJ 07202 Contract Date: The Contract is changed as follows: Costs associated with added devices & changes to locations per SK.6A & SK.6B Item Description Company Totals 1 Trenching and patching. See proposal HQ Construction $ 4,135.74 2 Device changes. See proposal Lowder electric $ 1,670.00 3 4

Page 2

Lowder electric $ 1,670.00 3 4 Sub-Contractor Subtotal $ 5,805.74 H&S - Overhead & Profit Of Sub Cost $ 290.29 Sub Contractors Total $ 6,096.03 Item Description Company Totals 5 PM Time 3hrs H&S $ 450.00 6 H&S 7 H&S 8 H&S 9 H&S 10 11 Contractor Subtotal $ 450.00 H & S - Overhead & Profit 15% of Contractor Cost $ 67.50 Contractors Total $ 517.50 Sub Total$ 6,613.53 H&S Bond Cost $ 198.41 Total $ 6,811.93

Page 2

198.41 Total $ 6,811.93 The contract time will be increased by: 4 days

Page 3

HQ CONSTRUCTION & DESIGN LLC. PO BOX 7016, East Brunswick NJ 08816 732-907-9717 PROPOSED CHANGE ORDER Proposed Change order # 10 Date: 11/22/2022 COMPANY: H&S Construction ATTN: Pat Blandino PROJECT: West Orange Library REQUESTED BY: Architect Description: Ticket # Cut concrete for the electrician in 6 locations only we did not include any other items in this change order Based on drawing by SK.6B Lower level Device Location plan 2 Laborers 2 Days to saw cut remove concrete and then Dowl and repour concrete Materials: Disposal 0 0 $50.00 Rebar $34.00 Saw rental 2 189.78 $379.56 Jack hammer rental 2 248.98 $497.96 $0.00 LABOR: Total materials cost: $961.52 Classification Hours Rate Sub Total Laborer 16 $84.57 1353.12 Laborer For 16 $90.32 1445.12 Carp 0 106.81 0 Carp For 0 $122.72 0 Operator 0 $115.76 0 Rodman 0 $119.12 0 Mason for 0 $108.90 0 Mason 0 $101.35 0 Drywawll Fin 0 $95.00 0 Painter 0 $89.60 0 Total labor cost:

Page 3

0 $95.00 0 Painter 0 $89.60 0 Total labor cost: $2,798.24 Subtotal $3,759.76 Profit & Overehad 10% $375.98 Total change to contract: $4,135.74 Approved by: Signature:

Page 4

Lowder Electric and Construction Corp Estimate 250 Hallock Ave. Unit B Middlesex, NJ 08846 US (732) 764-6000 info@lowder.biz ADDRESS SHIP TO H & S Construction West Orange Library 721 Bayway Ave. 10 Rooney Circle Elizabeth, NJ 07202 West Orange, NJ ESTIMATE # DATE 2653 11/01/2022 DATE DESCRIPTION QTY RATE AMOUNT Rm 206 relocate 2 floor boxes close 2 0.00 0.00 Remove 1 floor box. Cap the new circuit. 1 -230.00 -230.00 Relocate 1 floor box, cap new circuit. 1 35.00 35.00 Rm 206 relocate 4 floor boxes close 4 0.00 0.00 Rm 207 Desk relocate and cap new cable. 1 35.00 35.00 Rm 215 relocate 2 floor boxes. shorten 2 new circuits 2 50.00 100.00 Relocate 3 floor boxes cap the new circuit 3 35.00 105.00 Relocate 6 floor boxes close 6 0.00 0.00 Rm 216 relocated floor boxes. Add 4 new circuits only 4 250.00 1,000.00 Rm 220 Relocate 4 floor boxes close 4 0.00 0.00 Remove 3 outlets. Cap new circuits ran. 1 0.00 0.00 Rm 112 change 2 junction boxes to outlets 2 0.00 0.00 Cap two circuits and change one to an outlet. One circuit

Page 4

Rm 112 change 2 junction boxes to outlets 2 0.00 0.00 Cap two circuits and change one to an outlet. One circuit not yet 1 -250.00 -250.00 installed. Rm 105 relocate 2 wall outlets. extend wiring 2 75.00 150.00 Relocate 3 floor boxes extend wiring 3 75.00 225.00 Rm 103 Remove 2 wall outlets 2 -250.00 -500.00 Add 2 floor boxes with circuits 2 500.00 1,000.00 SUBTOTAL 1,670.00 TAX 0.00 TOTAL $1,670.00 Accepted By Accepted Date Lowder Electric & Construction Corp. Lic# 17955