S & HConstruction & Mechanical, Inc. General Contractors · Sprinkler · Plumbing · Heating · Design CHANGE ORDER REQUEST Owner: Township of West Orange Construction Mngr: Date: 12/22/2022 Architect: Arcari & Iovino Contractor: H&S Construction Project: West Orange Public Library Field: COR #: 17R1 To Contractor: Initiation date: H&S Construction & Mechanical Inc. Project No: 22-044 721 Bayway Ave Contract For: Completion Contract Elizabeth NJ 07202 Contract Date: The Contract is changed as follows: Costs associated with additional steel needed to support roof top equipment as determined by structural engineer. No existing structural drawing information was given at bid time and no way to quantify what would be needed. [revised to include original rail cost credit] Item Description Company Totals 1 Supply and install rooftop steel -See attached ISE $ 20,300.00 2 Credit for 22 rails not used H&S $ (4,400.00) 3

Page 2

20,300.00 2 Credit for 22 rails not used H&S $ (4,400.00) 3 $ - 4 $ - Sub-Contractor Subtotal $ 15,900.00 H&S - Overhead & Profit Of Sub Cost $ 1,015.00 Sub Contractors Total $ 16,915.00 Item Description Company Totals 5 6 7 8 9 10 11 Contractor Subtotal $ - H & S - Overhead & Profit 15% of Contractor Cost $ - Contractors Total $ - Sub Total $ 16,915.00 H&S Bond Cost $ 507.45 Total $ 17,422.45 The contract time will be increased by: 4 days

File revisions (1)