Town CrierWest Orange, New Jersey
← Back to search

Supporting Documentation · Jan 10, 2023

21-23 Attachment.pdf

Preserved file SHA-25614c92698ec56453b61ed38dbbcf7198f72fc9103d86d6599a841247290b06cf8

Indexed text

Page 26

FEE SCHEDULE Our fee for the tasks outlined above is: Valley Road Ashwood Terrace & William Street (Freeman Street to Kingsley Street) (Franklin Avenue to Main Street) Survey $11,400.00 $10,800.00 Design $20,500.00 $13,000.00 Total Fee $31,900.00 $23,800.00 TOTAL COMBINED FEES: $55,700.00 FEE SCHEDULE – Construction Inspection & Certification of Completion The time required to perform construction inspection services is a function of established contract duration(s), contractor’s schedule, and the Township’s need for part-time or full-time inspection. We will provide construction inspection services to fit with the Township’s needs. The services will be provided on an hourly basis. Our fee for the above referenced services is as follows: Construction Inspection Services $ 95.00/hr. Construction Inspection Overtime Rate $142.50/hr. Construction Administration $150.00/hr. HOURLY BILLING RATES As submitted in our Qualification package to the Township of West Orange on December 21, 2021, following are our municipal billing rates: PROFESSIONAL ENGINEER $ 165.00 SENIOR PROJECT MANAGER, ENGINEERING $ 150.00 SENIOR PROJECT MANAGER, LANDSCAPE ARCHITECTURE $ 145.00 SENIOR DESIGNER $ 120.00 DESIGNER $ 95.00 INSPECTOR $ 95.00 ENGINEERING TECHNICIAN $ 85.00 PROFESSIONAL LAND SURVEYOR $ 160.00 SENIOR PROJECT MANAGER, SURVEYING

Page 26

$ 85.00 PROFESSIONAL LAND SURVEYOR $ 160.00 SENIOR PROJECT MANAGER, SURVEYING $ 145.00 PROJECT SURVEYOR $ 120.00 SURVEYING TECHNICIAN $ 80.00 PARTY CHIEF $ 95.00 INSTRUMENT PERSON $ 80.00 TECHNICAL TYPIST $ 60.00 Scope of Services | Page 4

Page 27

SECTION 2 Personnel Assignments For this project, GPI will perform the work in its entirety. No sub-consultants will be needed. All work will be done entirely within GPI’s Engineering and Surveying Departments. Muhammed S. Assal, PE, CME, Project Manager, will be responsible for the overall design, contract adherence, and overall project supervision. Mr. Assal is quite familiar with the Township of West Orange, having worked on several other Township projects in recent years. He will be assisted by Engineering Department staff members. Paul Szmaida, LLA., ASLA, Streetscape Specialist and Michael E. Pirog, PE, Designer. Quality Assurance-Quality Control (QAQC) will be performed by Andrew Cangiano, PE, PP, CME, Director of Engineering – Morris Plains Office. Personnel Assignments | Page 5

Page 28

SECTION 3 Project Schedule GPI is committed to adhering to the Township’s goal to advertise for bids by Spring 2023. We anticipate work will proceed within one (1) week after the award of contract. We have the resources to complete the project in a timely fashion, and we are confident that we can achieve the Township’s goal. We have assumed a December 2022 contract award, and have prepared the following Project Schedule. Project Schedule (Assumed Contract Award) February 2023 January 2023 March 2023 April 2023 December 2022 1 Surveying Services 2 Design of Preliminary Plans/Specs 3 Township Review and Comment 4 Final Plans and Specifications Project Schedule | Page 6

Page 29

SECTION 4 Sample Insurance Certificate Sample Insurance Certificate | Page 7

File revisions (1)