Engineering | Surveying | Planning | Construction Inspection October 25, 2024 Zayibeth Carballo, PE, PLS, PP, CME, CFM, CFS Director, Municipal Engineer Department of Engineering Township of West Orange 25 Lakeside Avenue West Orange. NJ 07052 Re: Proposal for Professional Services Oskar Schindler Performing Arts Center (OSPAC) and Crystal Lake Improvements Dear Ms. Carballo: Greenman-Pedersen, Incorporated (GPI) is pleased to submit our proposal for professional services related to improvements at the Oskar Schindler Performing Arts Center (OSPAC) and the adjoining Crystal Lake. The specific scope of work is set forth in the Request for Proposals, issued by the Township of West Orange and dated October 11, 2024, as may be clarified herein. In our review of the Request for Proposals, we note that the scope includes activities that will require permitting from the New Jersey Department of Environmental Protection (NJDEP) while other activities do not. This office is recommending that the Township consider bidding those items requiring NJDEP approvals separate from those that do not. By splitting the project into two bid schedules the ordering of potential long-lead items, including but not limited to the electronic entrance sign, site furniture and playground equipment, will not be delayed by the NJDEP review process. Our November 28, 2023 Qualifications Statement submitted to the Township demonstrates that our experienced staff can handle the project. Enclosed for your review is our Proposal to Provide Professional Engineering Services, dated October 25, 2024. We are pleased to have this opportunity to be of continued service to the Township of West Orange and hope you will find our proposal favorable. We would be happy to provide additional information or assistance as your needs dictate. Respectfully submitted, ___________________________________ Andrew Cangiano, PE, CME Director of Engineering ___________________________________ Thomas R. Lemanowicz, PE, PP, CME Principal Engineer AC/TRL/rem attachment m:\proposal\trl\west orange\2024 oskar schindler art center\corresp\outgoing\2024-10-25 crystal lake proposal.docx Greenman-Pedersen, Inc. 301 Gibraltar Drive, Suite 2A Morris Plains, NJ 07950 Over 60 offices throughout the United States www.gpinet.com An Equal Opportunity Employer p 973-377-8500

Page 72

Section 1 Scope of Services / Fee Schedule

Page 73

Zayibeth Carballo-Township Engineer Township of West Orange October 25, 2024 OSPAC/Crystal Lake SCOPE OF SERVICES DESIGN SERVICES The Base Scope of Work will include the installation of ADA accessible seating for the amphitheater, the installation/rehabilitation of a 6 foot wide stone path around the perimeter of the lake, the installation of decorative LED pathway lighting along the perimeter path, the installation of a monument sign with programmable message board, and the installation of miscellaneous site furnishings such as benches and trash receptacles. With respect to the work on the pathway, this proposal assumes that the surface will not be HMA as this surface will be counted as impervious and could qualify the project as a Major Development for Stormwater Design. Further, the RFP lists the pathway width as 6 to 8 feet. Since Freshwater Wetlands General Permit #17 will be utilized for this work, and since the permit conditions restrict the maximum pathway width to 6 feet, the pathway work will not widen any part of the pathway to more than 6 feet. The project is not intended to qualify as a Major Development for Stormwater Design. Therefore, while not specifically required, GPI will include the replacement of inlet heads and grates as required by the stormwater management rules. There are additional items listed in the Alternate Scope of Work. These items are specifically discussed in Section I of this proposal. The Township’s decision on which, if any, of the additional items will be included in the project must be early in the project schedule to assure compliance with the timeline in the RFP. A. SURVEYING SERVICES 1. Prepare a Conceptual Base Map utilizing public domain aerial orthographic images with tax map parcel and feature overlays, to be provided by the Township in CAD format. 2. Prepare a Boundary and Topographic Survey of the subject parcels, being known as Lot 1.02 (Crystal Lake) and Lot 5 (Oskar Schindler Performing Arts Center) and the area of the walking trail, with all three mentioned parcels encompassing approximately 9.3 acres of land, in accordance with N.J.A.C. 13:40-5.1 in support of permitting and construction plans. Corner markers will NOT be set under this agreement. We will obtain a ten-foot (10’) overlap onto adjoining properties where accessible. Prior to commencing with the survey, we require that the Township supply or

Page 73

rs will NOT be set under this agreement. We will obtain a ten-foot (10’) overlap onto adjoining properties where accessible. Prior to commencing with the survey, we require that the Township supply or make available, all pertinent information and documentation in the Township’s possession relative to the subject parcel. Such information includes, but is not limited to, title reports/searches, area surveys, construction plans related to prior improvements to the property, records, deeds, original tract maps, public records, State, County, or Municipal maps. We also require any information on adjoining properties in the Township’s possession. If the information supplied is not sufficient to render an accurate survey, GPI will make all reasonable efforts in accordance with the industry standard of care, to obtain additional required information. If, as a result of these efforts, not enough information is found to prepare a boundary survey, or if a title search is not supplied, or if ambiguous or clouded title areas are found, the Township will be notified in writing of the various options for proceeding with the project. These options may consist of additional fees necessary by either GPI, a title search consultant, attorneys, or other expert professionals to further research subject and adjoiner deeds, investigate the chain of title, trace ownership to original cloth, identify easements, or other services pertaining to the specific problem related to the project. Our firm does not provide title search services; therefore, boundary surveying services offered herein will be subject to such facts as a complete title search might disclose. 3. Map the location of wetland flags and depict the locations of the associated buffers, FEMA Special Flood Hazard Area Zone lines, and riparian zones on the Survey plan. 4. Depict the horizontal limits of the tree canopy encompassing Crystal Lake. 5. Collect sufficient topographic information in the improved area of the OSPAC for the design of curb ramps and ADA accessible areas. Page | 1

Page 74

Zayibeth Carballo-Township Engineer Township of West Orange October 25, 2024 OSPAC/Crystal Lake We will obtain horizontal and vertical information on the referenced site, including buildings, walks, driveways, concrete pads, walls, fences, curbs, curb ramps, swales, streams, top of bank, tree lines, horizontal limits of tree canopy, limits of parking areas, porches, steps, ramps, and visible storm, sanitary and other utility structures including utility poles. Individual, isolated trees will be located. We will obtain horizontal and vertical information, including the nearest upstream and downstream structure, type of structure, type of casting, size and types of pipes entering the structure, and inverts on accessible pipes from aboveground observation of the storm and sanitary sewer system. Elevations on hard surfaces will be shown to the nearest hundredth foot (0.01’) and ground elevations will be shown to the nearest tenth foot (0.1’). Contour lines will have a one-foot (1’) interval. 6. Tie the field work horizontally into the North American Datum of 1983 (NAD 83), and vertically into the North American Vertical Datum of 1988 (NAVD 88). 7. Record water surface elevation information at Crystal Lake. 8. Set a minimum of two (2) elevation benchmarks on-site for future use by the Township or its agents. 9. Generate final topographic mapping at a scale of one inch equals fifty feet (1” = 50’) or other appropriate scale that will be available in AutoCAD® Civil3D® 2024 “.dwg” format along with the boundary survey and survey control information. 10. Contract with an underground utility locating firm to provide a Level “B” markout on the OSPAC property and to provide sketches, ground surface marks, and a summary report of findings. We will locate markings on the ground which in conjunction with field sketches and reports by the utility locator subcontractor will be depicted on the Survey plan. B. CONCEPT PHASE 1. Perform site inspection to establish extent of wetlands within work area. Assume the required buffers for Concept Plan discussion purposes. 2. Coordinate a Kick-off/Concept Plan meeting with municipal officials and/or department heads to finalize the Scope of Work. GPI will prepare a meeting agenda to establish meeting goals. 3. Prepare a draft Concept Plan for the overall project based upon Township clarifications. The Concept Plan is anticipated to

Page 74

pe of Work. GPI will prepare a meeting agenda to establish meeting goals. 3. Prepare a draft Concept Plan for the overall project based upon Township clarifications. The Concept Plan is anticipated to be returned to the Township within one week of the Concept Plan meeting. 4. Prepare two color renderings based upon the Concept Plan and comments received within one week of the submission of the draft plan to the Township. 5. Create the Concept Plan while acknowledging that the version to be discussed with the NJDEP as part of permitting will only show the activities requiring NJDEP permits. C. NJDEP PRE-APPLICATION PROCESS 1. Prepare a Pre-Application package in preparation for a Pre-Application meeting with the NJDEP. The package will follow the requirements of the checklist provided in the RFP. 2. Coordinate Pre-Application meeting with the NJDEP. Attend and prepare minutes of meeting. 3. Coordinate a meeting with Township officials to discuss NJDEP comments and their impact on the Concept Plan. 4. Establish final scope of work and project layout. Page | 2

Page 75

Zayibeth Carballo-Township Engineer Township of West Orange October 25, 2024 OSPAC/Crystal Lake D. NJDEP PERMIT SUBMISSION PACKAGE 1. Pursuant to NJAC 7:13-2.3(b), a flood hazard area exists along every regulated water that has a drainage area of 50 acres or greater. If a regulated water has a drainage area of less than 50 acres, the water does not possess a flood hazard area that is regulated under this chapter. Based upon the documentation attached to the RFP, and our independent review, the Crystal Lake has a drainage area of approximately 23 acres. Therefore, Flood Hazard Area permitting relating to flood hazard areas is not anticipated, or included in this proposal. However, it is acknowledged that permitting will be required for disturbance in the Riparian Zone. 2. Crystal Lake is tributary to the Rahway River. Pursuant to NJAC 7:9B-1.15(f), the Rahway River is not a Category One Water. Therefore, design considerations, including mitigation, for Category One Waters are not anticipated or included in this proposal. 3. Prepare combined application for Freshwater Wetlands (FWW) Letter of Interpretation (LOI) and FWW General Permits (GP) for the improvements shown on the accepted Concept Plan. The need for an FWW Individual Permit (IP) is not anticipated. Potential permits are as follows: a. General Permit 2―Underground utility lines. b. General Permit 11―Outfalls and intake structures. c. General Permit 17--Trails and boardwalks. d. General Permit 19―Docks and piers. e. General Permit 20―Bank stabilization f. General Permit 21―Above ground utility lines. g. General Permit 25― Minor channel or stream cleaning for local government agencies. E. HUDSON-ESSEX-PASSAIC SOIL CONSERVATION DISCTRICT (SCD) 1. Complete SCD application forms. 2. Include Soil Erosion and Sediment Control Plan, with construction details, in the plan set. 3. Prepare Engineering Report. 4. Complete revisions as may be requested by SCD. 5. Request NJDEP Stormwater General Permit Authorization (RFA). F. FINAL DESIGN OF CONSTRUCTION PLANS GPI assumes the need for the preparation and submission of two separate sets of bid construction documents. One set will be prepared in advance for work not under NJDEP jurisdiction. A second set for work requiring NJDEP permits will also be prepared. The following sequence is for each bid package submission: 1. Finalize preliminary plans incorporating

Page 75

ot under NJDEP jurisdiction. A second set for work requiring NJDEP permits will also be prepared. The following sequence is for each bid package submission: 1. Finalize preliminary plans incorporating permit conditions and contract items in comprehensive plans set to be reviewed by the Township. Prepare preliminary cost estimate for the project. 2. Coordinate a Final Design meeting with Township officials to establish consensus of the final design. Page | 3

Page 76

Zayibeth Carballo-Township Engineer Township of West Orange October 25, 2024 OSPAC/Crystal Lake 3. Coordinate and attend a Public Presentation meeting for the project. 4. Following plan approval by Township, prepare construction plans, specifications and estimate to be supplemented by the West Orange front-end documents to be provided by the Township. Adherence to bid schedule is contingent upon timely responses from the Township with respect to choosing the make and model of site improvements such as light fixtures, entrance sign, floating dock, seating, pedestrian bridge, playground equipment and surface type, etc. as may be applicable to the ultimate content of the improvements. G. BID PHASE 1. Assemble 20 copies of two bid packages with separate work scopes. The first bid package will include those work items not under the jurisdiction of the NJDEP permitting process and is anticipated to be advertised in the Spring of 2025. The second bid package will include those work items requiring NJDEP permits and is anticipated to be advertised in July of 2025. Bid packages will be provided to the Township of West Orange for distribution to bidders. 2. Respond to Requests for Information (RFI) from prospective bidders. 3. Issue addenda and/or clarifications as required. 4. Attend bid opening and prepare Recommendation of Award. H. CONSTRUCTION ADMINISTRATION SERVICES 1. Coordinate Pre-Construction Meeting with successful bidder and Township officials. Township to provide list of Township officials to be invited to the Pre-Construction Meeting. 2. Chair Pre-Construction Meeting and provide draft minutes to all attendees within one week of meeting. Minutes to be amended based upon attendee comments and become final one week from distribution of draft minutes. 3. Provide full-time construction observation and prepare daily observation reports. 4. Review and respond to change order requests by contractor. 5. Review and respond to payment requests by the contractor. 6. Perform initial project completion walk-through and punch list preparation. 7. Perform final project walk-through for final approval. 8. This item is specifically limited to 150 hours of construction management and 800 hours of construction observation. This is based on an assumed five month construction period encompassing both construction contracts as proposed above. I. ALTERNATE CONSTRUCTION

Page 76

management and 800 hours of construction observation. This is based on an assumed five month construction period encompassing both construction contracts as proposed above. I. ALTERNATE CONSTRUCTION ITEMS The RFP sets forth a number of significant alternate construction items that are being considered. The listing below represents our understanding of the scope of work involved with each of the alternate items. It is expected that the Township will advise which, if any, of the alternate items will be included in the project at the Kick-off/Concept Plan meeting as noted in Scope Item B2, herein. Changing the inclusion or exclusion of an alternate item during the design process may result in extra design fees. Page | 4