Packet · Apr 28, 2026
Township Council Meeting — Packet
06df1f76951def1c065c048330083bddbf54ecfa8c126d71d405205e5febb42fIndexed text · page 94
Show all pagesFINAL DESIGN GENERAL TASKS 1 Project Management 4795 2 Execute FD Public Involvement Action Plan Coordination Meetings 2a Stakeholder Meetings 2b 2d Hold Public Information Center In-Person PIC Plan Displays Update Project Website Quality Assurance & Quality Control 3 4010 4 Initiate Final Design TOTAL PRELIMINARY ENGINEERING- SUBTOTAL TOTAL PRJ. MNGR. (P-VII). SEN. ENGR. (P-V) PROJ. ENGR. (P-IV) ENGINEE R (P-III) ASSOC. ENGR. (P-I) SEN. PLAN. (P-IV) PLANNE R (P-II) SEN. DRAFT. (ET-V) ACTIVITY I.D. TASK DESCRIPTION HRS. HRS. HRS. Hours Cost 24 52 308 1,518 $ 96,591.96 44 18 32 8 234 40 8 8 16 16 4 8 8 16 4 4 4 40 4 4 8 4 4 20 20 12 48 6 $ $ $ $ $ $ $ $ $ $ $ 18,417.82 3,543.76 2,779.02 3,549.70 1,553.48 1,290.88 914.08 4,258.16 528.74 HRS. HRS. HRS. HRS. SUBTOTAL 32 258 400 444 SUBTOTAL 28 8 104 32 2 2 4 2 8 2 HRS. 38 50 8 2 4 1 a b GEOMETRICS AND ROADWAY Complete Horizontal and Vertical Geometry Prepare Final Roadway Plans SUBTOTAL 12 4 8 40 16 24 64 32 32 64 32 32 180 84 96 $ $ $ 10,257.12 4,669.36 5,587.76 2 SUBTOTAL a TRAFFIC Complete Flashing Pedestrian Beacon, Signing and Striping Plans 4 4 8 8 16 16 16 16 44 44 $ $ 2,513.28 2,513.28 DRAINAGE/ H&H/ SWM Complete Drainage / H&H/ SWM Design SUBTOTAL 4270 3 a 4 4 8 8 16 16 28 28 $ $ 1,768.32 1,768.32 4 a STRUCTURES Prepare Final Structures Documents SUBTOTAL 4160 4 4 8 8 24 24 60 60 $ $ 3,310.72 3,310.72 GEOTECHNICAL ENGINEERING SUBTOTAL 4300 4305 5 a b 240 20 67 82 $ $ $ $ 13,081.86 1,344.78 3,239.64 4,836.98 4210 4220 4240 4320 c Develop Subsurface Exploration Program Gather Subsurface Information Conduct Geotechnical Foundation, Roadway, and Rock Slope Design 6 2 2 2 46 6 5 24 80 12 20 24 24 24 108 40 32
File revisions (1)
- Sep 29, 2026
06df1f76951d9,023,608 bytes