STANDARDS FOR A COUNTY ROAD

Page 13

Standards for a County Road In order for a road to be considered, assumed and/or maintained within the County's Highway network, it should meet the following criteria (in part or in full); It should, 1. Facilitate a relatively high volume of traffic. 2. Connect more than one town. 3. Intersect and/or connect other county roads. 4. Constitute a major more direct route than municipal roads. With these criteria in mind, the following standards shall prevail for county highway right of way widths. These standard right- of-way widths (R.O.W.'s) are set forth in order to further promote the general health, safety, and welfare of the public. The County Planning Board's policy shall be to adhere to the standards set forth herein and to make exceptions where the health safety and welfare of the public are not at stake and where strict adherence is not feasible due to past development patterns or some other hardship basis which | must be established by the applicant or his representative. The minimum highway standard ROW shall be 66', described as follows:- a) 2 12 ft. lanes = 24 2 10 ft. shoulders = 20 2 11 ft. sidewalk areas = 22 66

Page 14

For those county roads that require more than a 66' ROW due to future growth and development patterns or projections an 86" or 108' standard shall be required. An 86' ROW shall be described as follows:- b) 2 12 ft. lanes = 24 2 11 ft. lanes = 22 2 10 ft. shoulders = 20 2 10 ft. sidewalk areas = 20 86 The maximum County Highway ROW shall be 108' and may be described as follows:- c) 2 12 ft. lanes = 24 4 11 ft. lanes = 44 2 10 ft. shoulders = 20 2 10 ft. sidewalk areas = 20 108 -2s

Page 15

lil COUNTY POLICY DEDICATION; RESERVATION, EASEMENT

Page 16

County Policy/Dedication, Reservation, Easement Based upon the criteria and standards established by the Essex County Planning Board for R.O.W. widths, the Planning Board will request dedications, reservations and/or easements. Each road or road segment will be delineated in terms of a dedication or reservation or easement requirement. Exceptions to the established request should be minimal but will be judged on a case by case basis and through the established appeal process. It is the Board's policy that in areas where existing buildings are closer to the roadway than the proposed future right- of-way line, the determination of requirements for dedication or reservation shall be decided on a case by case basis. The intent is that where the majority of the property along a significant length of said roadway has buildings closer to the roadway than the proposed right-of-way, the requirement of dedication or reservation would be waived; otherwise it would be required. The purpose of reservation i. and dedication is for the orderly improvement of the County roadway system. In areas where roadway widening is not anticipated in the near future, only a reservation of right-of-way will be required. Where roadway widening is desirable in the near future, a dedication of right-of-way will be required.

Page 17

There are distinct differences and implications in making the request for either a dedication, reservation, or easement. A clear definition of each term is therefore included:- 1. RESERVATION - An agreement for reservation of land is the setting aside of property by the owner for future use by the County when widening and otherwise improving the County roadways pursuant to the County Highway Master Plan. The owner continues to hold title to the property and can use it in any way permitted by local ordinance; municipal zoning set back and offset requirements are not affected by the Reservation. : sae ; If and when the County requires the use of the land, it must pay to the owner the current fair market value of the land only. The owner is not to be compensated by the County for improvements “ placed in or upon the land after the Reservation is granted, and the owner is liable for any expense in demolishing and removing from the property any such improvements. An Agreement for Reservation puts the property owner on notice that the County wishes to use the land at some future date.

Page 18

2. DEDICATION - The appropriation of land, by the owner for the use of the public, and accepted for such use by or on behalf of the public. A deliberate appropriation of land by its owner for any general and public uses, reserving to himself no other rights than such as are compatible with the full exercise and enjoyment of the public uses to which the property has been devoted. 3. EASEMENT - The right of use over the property of an individual granted to the public for use of the public and accepted for such use by or on behalf of the public normally granted for the benefit of adjoining lands. A right in the owner of one parcel of land, by reason of such ownership, to use the land of another fora special purpose not inconsistent with a general property in the owner. An interest which one person has in the land of another. It is also the intent of the County Planning Board to streamline the appeal process, and minimize the processing time, while maintaining its integrity for all applicants. All applicants will be subject to the same practices, procedures, policies, and process.

Page 19

A. County Highway Network Assessment Focusing Upon Inclusion of Additional Roads into the County System. There may be some roads that meet one or more of the listed criteria but may not necessarily enhance the County's Highway Network. If these roads are not included in the County Highway Network, their inclusion will not be given consideration until such time that enhance- ment can be established. There are some roads whose inclusion would definitely enhance the County Highway Network and, therefore, merit immediate inclusion into the County's system. These roads are:- , - 1. Grove Street - Which is owned by the County except the portion between Bloomfield Avenue and Franklin Street, within and owned by the Township of Bloomfield. Both Bloomfield Avenue and Franklin Street are County roads which would be connected by the inclusion of Grove Street between the two County roads. Grove Street would then be a County road throughout its entire length. 2. J.F. Kennedy Drive - Which is owned by the County except the portion between Belleville Avenue and Franklin Street within the Township of Bloomfield but owned by the Garden State Parkway. The inclusion of J.F. Kennedy Drive, in this case, would provide a continuous county road throughout its entire length as well as to connect two other major County roads. 3. Washington Avenue - Which is owned by the State of New Jersey entirely but is the northern extension of Broadway from

Page 20

3. Washington Avenue - continued Mill Street in Belleville to the Essex County line. The inclusion of Washington Avenue will not only provide a continuous county road but will connect two Towns, two counties as a major route and will also intersect Kingsland Road (in another County). 4. Kingsland Road/Rt. 7_- Which is State owned within the Township of Nutley from the County line to a point west where the county assumes ownership. Ownership by the County throughout the entire length will provide a continuous County road that will connect W. Passaic Avenue and Washington Avenue. IT IS RECOMMENDED THAT NEGOTIATIONS COMMENCE WITH THE APPROPRIATE OWNERS TO BRING THESE ROADWAY SEGMENTS INTO THE COUNTY HIGHWAY NETWORK.

Page 21

B. Highway Network Assessment Focusing Upon the Return’of Existing County Roads to State and Municipal Systems. There are existing County roads or portions thereof that do not enhance the County Highway Network and therefore the return thereof to the proper jurisdictions should be given consideration. It is the prerogative of the County to abandon roads or turn them over to municipalities as it sees fit. However, it will be the policy of this Board not to do so without negotiations with the appropriate jurisdictions. This Board will make every attempt to maintain good working relationships, maximum communications, and high levels of understanding as far as reasonably possible and as long as the general health, safety, and welfare of the public is not compromised. Where economically feasible, the County will not attempt to return roads until it can put them into a better state of repair. The County will not do so until it has local assurances that jurisdiction will receive and maintain the repaired road. A 5-year schedule for improving these roads will be developed and provided for the encouragement of the County Engineer's priority consideration. All considerations must be reasonable and economically feasible particularly where expenditures of large sums of county dollars will be involved. Until the proper conditions come together, the County Planning Board will not initiate steps to return any of the following roads:- 1. Fairfield - Brook Street Hollywood Avenue Pier Lane 2. Livingston Hobart Gap Road