Page 4

11. Dockery Drive, Carteret Street to Crystal Woods a. Curb, aprons, mill, pave b. 570 LF @ $170 per LF $ 96,900 12. Ronald Terrace, Pleasant Valley Way to dead end a. Curb, asphalt aprons, mill, pave b. 800 LF @ $150 per LF $120,000 13. Terrace Avenue, Eagle Rock Avenue to dead end a. Curb, asphalt aprons, mill, pave b. 710 LF @ $150 per LF $106,500 Total Length, 11,580 LF or 2.19 miles Engineering Design (Estimated) ± $ 30,000 General Drainage Improvements (Estimated) ± $ 150,000 Estimated Total ± $2,073,600