Show all pagesSection 3 Financial Proposal Neglia Group will provide cost proposals for definite feasibility, review, design, and construction management assignments as requested by the governing body. The following rates would serve as the man hour multiplier that would serve as a component of proposal scope, schedule, and fee. Design and Construction Management proposals are typically fixed fee not to exceed or lump sum-which are inclusive of the man-hours and meeting times-needed to complete a project. We look to our work ethic to hold our budgets and deadlines. HOURLY BILLING RATES 2024 PRINCIPAL $205.00 SENIOR ENGINEER / SENIOR MANAGER/SR. PROF. PLANNER $200.00 PROFESSIONAL ENGINEER / PROJECT MANAGER $195.00 SENIOR DESIGN ENGINEER $185.00 DESIGN ENGINEER/ENVIRONMENTAL SCIENTIST $175.00 ENGINEERING ASSISTANT $110.00 PROFESSIONAL PLANNER $200.00 PROFESSIONAL LANDSCAPE ARCHITECT $185.00 LANDSCAPE DESIGN $145.00 COMPUTER AIDED DESIGNER $145.00 CONSTRUCTION MANAGER $170.00 RESIDENT ENGINEER $195.00 TECHNICAL OBSERVER $145.00 PROFESSIONAL SURVEYOR / PROJECT MANAGER $195.00 SURVEY PROJECT MANAGER $175.00 3 MAN SURVEY CREW $275.00 2 MAN SURVEY CREW $235.00 1 MAN SURVEY CREW (GPS AND
$275.00 2 MAN SURVEY CREW $235.00 1 MAN SURVEY CREW (GPS AND EQUIPMENT) $205.00 CERTIFIED WETLAND DELINEATOR $200.00 LICENSED COLLECTION SYSTEM OPERATOR $195.00 DRONE PILOT AND VISUAL OBSERVER $245.00 DRONE EDITOR $175.00 GIS MANAGER $190.00 GIS SPECIALIST $165.00 GIS TECHNICIAN $115.00 REIMBURSABLE EXPENSES PAPER PRINTS (All Sizes) $ 4.25/sheet MYLARS $32.50/sheet COLOR PRINTS $70.00/sheet PHOTOCOPIES (Black & White) $ .30/page PHOTOCOPIES (Color) $ .45/page MILEAGE (Federal Standard Milage Rate) $ .65.5/mile SUB-CONSULTANTS 10% administrative fee Notes: 1. Expert testimony for deposition or trial is billed at 1½ standard billing rate. 2. Labor billings include miscellaneous direct costs such as telephone calls, faxes, copying and postage. No charges are levied for use of computers, plotters, or CAD systems. 3. After hour and Holiday Call Outs a. 7:00pm to 5:00am – 1.5 times the hourly rate and a 4-hour minimum b. Holidays – 2 times the hourly rate and a 4-hour minimum 4. Reimbursable expenses are subject to change annually based on industry fluctuation.
-hour minimum b. Holidays – 2 times the hourly rate and a 4-hour minimum 4. Reimbursable expenses are subject to change annually based on industry fluctuation. RFP- WALKER ROAD, S VALLEY ROAD AND ROONEY CIRCLE WEST ORANGE Page | 16
File revisions (1)
- Sep 29, 2026
b28d73feb1186,532,068 bytes