Gregory Avenue and Lowell Avenue Safe Routes to School Preliminary Engineering, Final Design, and Construction Engineering Services Page 12 Preliminary Engineering – Scope of Work through the following tasks: • Adherence to our Corporate Quality Assurance Plan (CQAP) and Project Specific QA/QC Plan • Assignment of appropriate staff for completion of the various tasks and quality reviews • Bi-weekly internal project status meetings The QA/QC team has the ability to work independently of the STV production/design team, so that quality control documents and other deliverables are of high quality. The QA/QC team will initially consult with the production/design team to establish major milestone reviews and will only participate during the QA/QC reviews to ensure they are examining the project objectively and following through on comments made by any reviewers. Subconsultants will be required to comply with STV’s Plan and submit their own QA/QC plan for inclusion in STV’s Plan. STV will maintain close coordination with subconsultants and will conduct periodic visits to monitor progress of their work to ensure compatibility with our work and compliance with assignment needs, scope, schedule, and budget. Internal project-specific reviews will be conducted and documented using STV’s own standard checklists for all submissions, in full compliance with NJDOT and federal standards and/or regulations. 4. INITIATE FINAL DESIGN (4010) STV will attend the kickoff meeting with the RC and team to review the PE documents, discuss the scope of work of the project, and schedule. STV will prepare the Meeting Minutes documenting the kickoff meeting. D. FINAL DESIGN 1. GEOMETRICS AND ROADWAY a. Complete Horizontal & Vertical Geometry (4210) STV will complete and refine the proposed geometric alignment. STV will review the current proposed alignment and finalize all roadway horizontal and vertical geometry and calculations. The horizontal geometry will be added to the Construction Plans. b. Prepare Final Roadway Plans (4220) STV will update the preliminary roadway plans that were
The horizontal geometry will be added to the Construction Plans. b. Prepare Final Roadway Plans (4220) STV will update the preliminary roadway plans that were prepared during the PE phase to produce the final roadway plans. STV will prepare the final roadway plans in accordance with the NJDOT Roadway Design Manual. This task will include the preparation of the roadway quantity calculations. STV will deliver the final design plans to the RC and team (electronic and hardcopies as needed). The final roadway plans may include the following: Roadway: • Key Sheet (1 Sheet) • Construction Plan Legend (1 Sheet) • Estimate-Distribution of Quantities (1 Sheet) • Construction Plans (4 Sheets) • Curb ramp layout details (5 Sheets) • Typical Sections (2 Sheets) • Preliminary Signing and Striping Plans (4 Sheets) • Soil Erosion and Sediment Control Plans (4 Sheets)
Gregory Avenue and Lowell Avenue Safe Routes to School Preliminary Engineering, Final Design, and Construction Engineering Services Page 13 Preliminary Engineering – Scope of Work • Pedestrian Flashing Beacon Plan (4 Sheets) • Preliminary Staging/Maintenance and Protection of Traffic/Detour Plans (8 Sheets) • Tie Sheets (2 Sheets) • Construction Details (10 Sheets) • Electrical Details (2 Sheets) Other: • Utility Relocation Plans (4 Sheets) 2. TRAFFIC a. Complete Flashing Pedestrian Beacon, Signing and Striping Plans (4240) STV will complete the signing and striping plan improvements. These items will better delineate travel lanes, and significantly increase visibility of crosswalks. STV will complete the plans for the proposed flashing beacons. Additionally, these items will also significantly improve safety along the corridor for pedestrians, bicyclists, and motorists. STV will prepare the flashing pedestrian beacon, electrical, signing and striping plans as per the MUTCD and NJDOT Roadway Design Manual. 3. DRAINAGE / HYDROLOGY & HYDRAULICS / STORMWATER MANAGEMENT a. Complete Drainage (4270) The drainage features determined during preliminary engineering will be finalized. The drainage improvements will be displayed on the Construction plans including bicycle safe grates and curb pieces. b. Complete Hydrology & Hydraulics Analysis (4310) H&H analysis is not anticipated for this project. There are no hours associated with this activity. 4. STRUCTURES There are no existing structures impacted with the project limits. Retaining walls are proposed to minimize impacts to the properties adjacent to the proposed sidewalk. a. Prepare Final Structures Documents (4160) STV will prepare final structures documents for the Lowell Avenue Retaining Wall, Lawrence Avenue to Helen Avenue; Lowell Avenue Retaining Wall, North of Helen Avenue; and Gregory Avenue Retaining Wall including: • Retaining Walls • Detail Sheets
Helen Avenue; Lowell Avenue Retaining Wall, North of Helen Avenue; and Gregory Avenue Retaining Wall including: • Retaining Walls • Detail Sheets • Structural Quantity Estimate 5. GEOTECHNICAL ENGINEERING Based on the preliminary design, STV will proceed with final design for the proposed improvements including: • Lowell Avenue Retaining Wall, Lawrence Avenue to Helen Avenue • Lowell Avenue Retaining Wall, North of Helen Avenue • Gregory Avenue Retaining Wall • Stormwater Management BMP
Gregory Avenue and Lowell Avenue Safe Routes to School Preliminary Engineering, Final Design, and Construction Engineering Services Page 14 Preliminary Engineering – Scope of Work STV will solicit bids for the geotechnical subsurface investigation and will advance the investigation. While the final geotechnical investigation program will be dependent on the final limits and heights of the retaining walls and BMPs, for pricing purposes, STV assumes that a total of 4 borings will be performed along the two Lowell Avenue retaining walls. Despite its conceptual length, we assume that only 2 borings will be performed for the Gregory Avenue retaining wall due to the cut section and expected height of less than 3 feet. All borings will be performed to a depth of 15 feet below ground surface with continuous SPT sampling. If predominantly fine-grained cohesive soils are encountered, relatively undisturbed Shelby tube samples will be attempted. We assume that rock will not be encountered within 15 feet below ground surface. Based on the anticipated size of the stormwater BMP, we anticipate that two test pits to a depth of 10 feet will be required with infiltration testing consisting of single-ring infiltration testing performed in accordance with the NJDEP’s Stormwater Management BMP Manual. STV assumes that maintenance and protection of traffic (MPT) will be required for the borings but that no MPT will be required for the test pits or infiltration testing. STV will provide a geotechnical engineer or geologist on-site full-time to monitor the investigation, to visually classify encountered soil using the Burmister Soil Identification Method, and to collect representative samples for possible laboratory testing. For the test pits, STV will identify indications of the seasonal high groundwater table, e.g. mottling. STV will select samples for laboratory testing, expected to consist of soil index testing, consolidation testing, and soil shear strength testing. The results of the stormwater investigation will be presented as part of a Stormwater Investigation Memorandum, including seasonal high water table elevation and infiltration testing results. Based on the results of the investigation program, STV will determine soil design parameters. Based on
Memorandum, including seasonal high water table elevation and infiltration testing results. Based on the results of the investigation program, STV will determine soil design parameters. Based on the conceptual height of the walls, we will consider segmental block walls, modular block walls, and concrete cinder block walls, similar to those installed by NJDOT at Tichenor Park in Newark for both cut and fill sections. STV will perform wall stability (bearing, sliding, & eccentricity), global slope stability, and settlement analyses and develop geotechnical recommendations for the retaining walls. We will also assess the use of lightweight fill to mitigate potential settlement or imposed lateral loading impacts. STV will summarize the results of the geotechnical investigation, analyses, and recommendations as well as construction considerations as part of the Geotechnical Engineering Report. STV will prepare special provisions to the NJDOT Standard Specifications for the walls, if required based on the final design recommendations and construction considerations. a. Develop Subsurface Exploration Program (4300) STV will solicit bids for subsurface exploration program. STV will be responsible for the bid opening, bid review, and recommendation for award. STV will prepare a subcontract agreement (driller) and PO agreement for the lab work. b. Gather Subsurface Information (4305) STV will coordinate with the drillers, monitor the borings, monitor the test pits and infiltration testing. We will record and prepare logs for all testing. STV will develop generalized subsurface profiles and a lab testing program. The lab testing results will be reviewed and STV will determine soil design parameters. c. Conduct Geotechnical Foundation, Roadway, and Rock Slope Design (4320) Lowell Avenue Retaining Wall, Lawrence Avenue to Helen Avenue STV will evaluate wall alternatives, perform wall stability analysis including bearing, sliding, and eccentricity analysis. We will perform global slope stability analysis and settlement analysis. Light weight fill alternative analysis will also be conducted.
Gregory Avenue and Lowell Avenue Safe Routes to School Preliminary Engineering, Final Design, and Construction Engineering Services Page 15 Preliminary Engineering – Scope of Work Lowell Avenue Retaining Wall, North of Helen Avenue STV will evaluate wall alternatives, perform wall stability analysis including bearing, sliding, and eccentricity analysis. We will perform global slope stability analysis and settlement analysis. Light weight fill alternative analysis will also be conducted. Gregory Avenue Retaining Wall STV will evaluate wall alternatives, perform wall stability analysis including bearing, sliding, and eccentricity analysis. We will also perform global slope stability analysis. STV will also develop construction considerations, a stormwater investigation memorandum, geotechnical engineering report, drawings, and special provisions. 6. RIGHT OF WAY AND EASEMENTS All efforts will be made to eliminate right-of-way impacts. However, in the event the proposed improvements will require the acquisition of right-of-way and/or easements, the following tasks will be conducted: a. Update Title Search (4624) If easements are needed, STV will conduct deed/title searches as necessary. A Title Summary document will be prepared. b. Prepare Final ROW/Easement Submission (4625) If easements are needed, STV will resolve all comments and incorporate the changes within the plans and documents and submit to West Orange. c. Acquire ROW/Obtain Easement (4670) If easements are needed, the team will prepare an appraisal, conduct negotiations, and reach agreements. STV will engage the services of a subconsultant to prepare the deeds. STV will review and send them to West Orange, RC and team and property owners for review and approval. Once the signed documents are returned, the deed will be recorded and payments for the acquired property will be processed by West Orange. 7. ACCESS If there are any changes to the plan, STV, RC and Township will discuss any proposed/desired access
will be processed by West Orange. 7. ACCESS If there are any changes to the plan, STV, RC and Township will discuss any proposed/desired access alterations with the impacted property owners. STV will document the minutes of the meetings. 8. UTILITIES a. Develop Alternatives of Accommodation (4050) While STV will attempt to avoid utility conflicts, if conflicts are unavoidable, STV will coordinate with the impacted utility companies and develop an Alternatives of Accommodation Plan to resolve utility conflicts. We will confirm the proposed utility accommodation scheme with each utility provider. For the purpose of this proposal, it is assumed there will be two (2) utility company facilities impacted. b. Prepare Utility Owner Design Authorization Checklist (4055) STV will prepare the Utility Owner Design Authorization Checklist according to the NJDOT Utility Accommodation Policy to accommodate the proposed improvements for each utility and send to the utility company. Upon review and approval by the utility company, STV will forward the approved Checklist to
Gregory Avenue and Lowell Avenue Safe Routes to School Preliminary Engineering, Final Design, and Construction Engineering Services Page 16 Preliminary Engineering – Scope of Work the RC and team for their concurrence and for future records. For the purpose of this proposal, it is assumed there will be two (2) utility company facilities impacted. c. Prepare Utility Relocation Plans, Specifications and Estimates (4060) Upon receipt of the approved checklists, STV will prepare the final Utility Relocation Plans of utility facilities to be relocated or altered. The Utility Relocation Plan provides an overview of the existing and proposed utility location and will be attached to the agreement. STV will complete the detailed plans, specifications and estimates for the utility facilities to be relocated or altered. For the purpose of this proposal, it is assumed there will be two (2) utility company facilities impacted. d. Prepare Utility Agreement Modifications (4070) STV will assist the RC and team in the preparation of Utility Agreement Modifications if necessary, to modify existing utility agreements. The modification will include a detailed cost estimate and any relevant documents for execution. For the purpose of this proposal, it is assumed there will be two (2) utility company facilities impacted. 9. PRE-CONSTRUCTION a. Update Preliminary Detour and Staging Plans STV will update the preliminary detour and construction staging plans if necessary. STV will coordinate efforts with the RC and team and obtain concurrence. b. Update Construction Cost Estimate (4275) Under this task, STV will update the cost estimate initially developed during Preliminary Engineering based on the additional design detail from the further development of the project. This includes computing quantities of work items and researching unit prices appropriate for this particular project. As part of the cost estimate, we will identify and evaluate any special conditions specific to this project that could impact the unit price or total cost for a particular
s part of the cost estimate, we will identify and evaluate any special conditions specific to this project that could impact the unit price or total cost for a particular element of the construction. Such conditions include work area, utility impacts, material supply, and/or time restrictions. STV will submit the Construction Cost Estimate to the RC and team for review and comment. c. Develop Specifications (4280) STV will develop the Special Provisions using the latest version of the NJDOT Standard Input and guidance provided by the latest Baseline Document Changes and Standard Specifications. STV will submit the final Special Provisions to the RC and team for review and comment. d. Develop Construction Schedule (4285) STV will create a construction schedule using Primavera and the NJDOT Construction Scheduling Manual. The construction schedule will be established for a completion date that provides the shortest practical duration of construction to minimize the disruption of traffic and allows the contractor a reasonable amount of time to complete the project at a reasonable cost. STV will submit the Construction Schedule to the RC and team for review and comment. 10. ENVIRONMENTAL a. Prepare Permit Application (4385) STV will apply for a Soil Erosion Control Certificate from the County Conservation District. If needed, STV will document the need for a freshwater wetland permit and/or wetland transition waiver. However,