Supporting Documentation · Apr 28, 2026

129-26 (Exhibit A) STV-consultant-ageement_2026-01-05.pdf

Preserved file SHA-256ce3dc33c6f7d7241bcc0d9482fc70d2af2d8fb3d09f3e8b98b1345a9e5414c8d

Indexed text

Page 39

R R TASK DESCRIPTION HRS. HRS. HRS. HRS. HRS. HRS. HRS. HRS. Hours Cost PRELIMINARY ENGINEERING- SUBTOTAL SUBTOTAL 32 258 400 444 24 52 308 1,518 $ 96,591.96 FINAL DESIGN GENERAL TASKS SUBTOTAL 28 104 44 18 32 8 234 $ 18,417.82 1 Project Management 8 32 40 $ 3,543.76 4795 2 Execute FD Public Involvement Action Plan $ - 2a Coordination Meetings 2 8 16 4 8 38 $ 2,779.02 2b Stakeholder Meetings 2 8 16 8 16 50 $ 3,549.70 2d Hold Public Information Center $ - In-Person PIC 4 4 4 4 4 20 $ 1,553.48 Plan Displays 4 8 8 20 $ 1,290.88 Update Project Website 2 4 2 4 12 $ 914.08 3 Quality Assurance & Quality Control 8 40 48 $ 4,258.16 4010 4 Initiate Final Design 2 4 6 $ 528.74 1 GEOMETRICS AND ROADWAY SUBTOTAL 12 40 64 64 180 $ 10,257.12 4210 a Complete Horizontal and Vertical Geometry 4 16 32 32

Page 39

12 40 64 64 180 $ 10,257.12 4210 a Complete Horizontal and Vertical Geometry 4 16 32 32 84 $ 4,669.36 4220 b Prepare Final Roadway Plans 8 24 32 32 96 $ 5,587.76 2 TRAFFIC SUBTOTAL 4 8 16 16 44 $ 2,513.28 Complete Flashing Pedestrian Beacon, Signing 4 8 16 16 44 $ 2,513.28 a and Striping Plans 4240 3 DRAINAGE/ H&H/ SWM SUBTOTAL 4 8 16 28 $ 1,768.32 4270 a Complete Drainage / H&H/ SWM Design 4 8 16 28 $ 1,768.32 4 STRUCTURES SUBTOTAL 4 8 24 24 60 $ 3,310.72 4160 a Prepare Final Structures Documents 4 8 24 24 60 $ 3,310.72 5 GEOTECHNICAL ENGINEERING SUBTOTAL 6 46 80 108 240 $ 13,081.86 4300 a Develop Subsurface Exploration Program 2 6 12 20 $ 1,344.78 4305 b Gather Subsurface Information 2 5 20 40 67 $ 3,239.64 Conduct Geotechnical Foundation, Roadway, and 2 24 24 32 82 $ 4,836.98 c 4320 Rock Slope Design

Page 40

ACTIVITY ENGINEE PLANNE ASSOC. DRAFT. TOTAL TOTAL MNGR. (P-VII). ENGR. ENGR. ENGR. PROJ. PLAN. (ET-V) (P-IV) (P-IV) (P-III) (P-V) SEN. SEN. SEN. (P-II) PRJ. (P-I) I.D. R R

Page 40

(P-I) I.D. R R TASK DESCRIPTION HRS. HRS. HRS. HRS. HRS. HRS. HRS. HRS. Hours Cost Lowell Ave. RW, Lawrence Ave. to Helen Ave. 4 9 12 25 $ 1,303.04 Lowell Ave. RW, North of Helen Ave. 4 9 12 25 $ 1,303.04 Gregory Ave. RW 3 6 12 21 $ 1,054.38 6 RIGHT OF WAY & EASEMENT SUBTOTAL 4 20 16 32 72 $ 4,951.32 4624 a Update Title Search 4 8 12 $ 782.16 4625 c Prepare Final ROW/Easement Submission 8 16 24 48 $ 3,111.68 4670 d Acquire ROW/Obtain Easements 4 8 12 $ 1,057.48 7 ACCESS SUBTOTAL 2 8 16 26 $ 2,008.34 a Access Updates 2 8 16 26 $ 2,008.34 8 UTILITIES SUBTOTAL 6 24 40 64 16 150 $ 8,703.50 4050 a Develop Alternatives of Accommodation 4 8 24 36 $ 1,853.92 4055 b Prepare Utility Owner Design Authorization 2 4 8 14 $ 1,089.94 4060 c Checklist Prepare Utility Relocation Plans, Specifications 2 8 24 40 16 90 $

Page 40

14 $ 1,089.94 4060 c Checklist Prepare Utility Relocation Plans, Specifications 2 8 24 40 16 90 $ 4,873.70 4070 d and Estimates Prepare Utility Agreement Modifications 2 8 10 $ 885.94 9 PRE-CONSTRUCTION SUBTOTAL 4 16 32 72 16 140 $ 8,586.28 a Update Preliminary Detour and Staging Plans 4 8 16 16 44 $ 2,513.28 4275 b Update Construction Cost Estimate 4 8 16 28 $ 1,768.32 4280 c Develop Specifications 2 4 8 24 38 $ 2,364.82 4285 d Develop Construction Schedule 2 4 8 16 30 $ 1,939.86 10 ENVIRONMENTAL SUBTOTAL 2 24 44 12 82 $ 5,210.74 4385 a Prepare Permit Application 2 16 32 50 $ 3,300.18 4585 b Complete Environmental Plans 8 12 12 32 $ 1,910.56 11 LANDSCAPE SUBTOTAL 8 12 16 36 $ 2,301.16 4265 a Complete Landscape Architectural Design 8 12 16 36 $ 2,301.16 12 REPORTS AND SUBMISSIONS SUBTOTAL 12 28 56 64 160 $ 10,857.72 4410 a Prepare Soil Erosion and Sediment Control Report 8 16 24 48 $ 3,111.68 4290 b and Plans Prepare Final Design Submission Package 4 8

Page 40

8 16 24 48 $ 3,111.68 4290 b and Plans Prepare Final Design Submission Package 4 8 16 24 52 $ 3,454.76 4830 c Resolve Final Design Submission Comments 4 8 16 28 $ 2,179.88 4840 d Submit PS&E Package 4 4 8 16 32 $ 2,111.40

Page 41

ACTIVITY ENGINEE PLANNE ASSOC. DRAFT. TOTAL TOTAL MNGR. (P-VII). ENGR. ENGR. ENGR. PROJ. PLAN. (ET-V) (P-IV) (P-IV) (P-III) (P-V) SEN. SEN. SEN. (P-II) PRJ. (P-I) I.D. R R TASK DESCRIPTION HRS. HRS. HRS. HRS. HRS. HRS. HRS. HRS. Hours Cost FINAL DESIGN - SUBTOTAL SUBTOTAL 58 248

Page 41

TASK DESCRIPTION HRS. HRS. HRS. HRS. HRS. HRS. HRS. HRS. Hours Cost FINAL DESIGN - SUBTOTAL SUBTOTAL 58 248 264 292 64 18 32 132 1,108 $ 91,968.18 CONSTRUCTION SERVICES 1 ADVERTISEMENT AND BIDS SUBTOTAL 4 16 20 $ 1,771.88 5010 a Prepare Advertising Package 2 8 10 $ 885.94 5030 b Prepare Bids 2 8 10 $ 885.94 2 CONTRACT AWARD SUBTOTAL 6 14 20 $ 1,764.82 5050 a Award Contract 2 4 6 $ 528.74 5070 b Execute Contract 2 4 6 $ 528.74 5080 c Hold Pre-Construction Meeting 2 6 8 $ 707.34 3 CONSTRUCTION SUBTOTAL 20 59 54 62 16 211 $ 14,810.60 5100 a Perform Construction $ - I Field Visits / Meetings 4 12 12 28 $ 2,256.48 II RFI 4 7 14 25 $ 1,950.28 Review of Shop Drawing and Contractor 4 8 28 42 82 $ 5,252.72 III Submittals IV Change of Plans 2 4 12 16 34 $ 1,911.14 V Construction Schedule Monitoring 2 12

Page 41

4 12 16 34 $ 1,911.14 V Construction Schedule Monitoring 2 12 14 $ 1,243.14 VI Utility Coordination 2 8 8 18 $ 1,310.90 5140 VII Process Construction Change Requests 2 8 10 $ 885.94 4 CLOSE OUT SUBTOTAL 4 8 12 $ 1,057.48 5170 a Final Acceptance 2 4 6 $ 528.74 b As-built plans 2 4 6 $ 528.74 CONSTRUCTION SERVICES - SUBTOTAL SUBTOTAL 34 97 54 62 16 263 $ 19,404.78 TOTAL 124 603 718 798 64 42 84 456 2,889 $ 207,964.92

Page 42

STV, Inc. Certified Payroll Roster Employee Name Grade Title Average Salary T. Zachary Suralik PV Project Manager $ 85.77 Dan McGinnis PV Assistant Project Manager Michael Grantner PV Senior Engineer Darren Stanker PV Senior Engineer Matthew Luneman PV Senior Engineer Owen Trickey PV Senior Engineer $ 89.67 Esteban Garcia PV Senior Engineer Matthew Benscoter PV Senior Engineer Todd Davies PV Senior Engineer Drew Kinghorn PIV Project Engineer Andres Barrezueta PIV Project Engineer $ 71.30 Isaac Forero PIV Project Engineer Elaine Hughes PIII Engineer Chris Savo PIII Engineer Mason Krushinsky PIII Engineer Suma Kesavareddy PIII Engineer $ 51.66 Kush Patel PIII Engineer Zachary Hresko PIII Engineer Hilary Porter PIII Engineer Bill Walmsley PIII Engineer Darby Williamson PI Associate Engineer Marshall Callison PI Associate Engineer Norah Diehl PI Associate Engineer Bhupendra Oli PI Associate Engineer $ 38.98 Marcelo Alvarez Gallego PI Associate Engineer Phuong Nguyen PI Associate Engineer Tommy Burns PI Associate Engineer Matthew Tallia PI Associate Engineer Alexis Wiliams PIV Senior Planner $ 87.50 Dan Hutton PIV Planner $ 49.52 Joanna Hecht PIV Planner Michael Schemm ETV Senior Drafter $ 46.56 Richard Cattell ETV Senior Drafter CERTIFIED TRUE AND