ruptions. Up to three days of MPT/Police are included, as most survey work is anticipated behind the curb. Primary Control Horizontal and vertical control will be established within the project limits based on GPS observations and tied to NJ State Plane NAD 83 and NAVD 88 datums. Primary control points will include three swing ties, benchmarks will be established at approximately 500-foot intervals as required, and tie sheets will be prepared. Ground Survey Conventional survey methods will be used to obtain roadway cross sections at approximately 50-foot intervals and locate topographic features, including visible utility hardware, pole numbers, overhead wires, hydrants, manholes, catch basins, valves, and similar features. Buildings within the survey limits will be located where possible, including building lines/corners, doorway thresholds, finished floor elevations, landings, and stoops. Sidewalk joints are excluded. Significant grade breaks and curb depressions will be located. 4

Page 77

Drainage & Sanitary Sewer Survey M&S will survey up to 40 drainage/sanitary structures and obtain locations, grate/rim elevations, and invert elevations where accessible. ADA Curb Ramp Survey Detailed conventional survey will be performed for up to 10 corner locations on an approximate 5-foot grid extending up to 15 feet beyond the PT of each identified curb ramp. Activity 3025 – Prepare Base Maps Base Mapping and DTM Base mapping will incorporate surveyed planimetrics and topography and be prepared in AutoCAD Civil 3D consistent with 1" = 20' mapping specifications. Features will be assigned appropriate layers and attributes and edited in three dimensions. The DTM will incorporate pertinent field survey information, and 1-foot contours will be generated. Survey work will be subject to M&S QA/QC procedures. Existing Baseline The existing roadway baseline will be established from available documents and surveyed features such as ROW markers, curb lines, and other identifiable points. It is assumed the County/Township will provide available alignment plans, parcel plans, and/or as-builts showing existing baseline and geometry. Deed Mosaic and Research Current cover deeds for up to 36 lots abutting Pleasant Valley Way will be obtained, reviewed, and plotted. M&S will prepare a deed mosaic and property owner listing. A complete title search will not be performed. Existing ROW Although ROW impacts are not anticipated, M&S will develop existing ROW lines using deeds, available County/Township plans, and tax maps under a normal standard of analysis. It is assumed existing ROW plans will be provided by the County/Township. Activities 3110 - Prepare ROW Report, 3115 - Initiate ROW Impact Plan, and 3120 - Hold ROW Kickoff Meeting are excluded. ENGINEERING DESIGN Activity 3006 – Prepare & Submit PE Complete Streets Checklist M&S will prepare the NJDOT Preliminary Engineering Complete Streets Checklist documenting applicable accommodations for pedestrians, bicyclists, transit users, persons with disabilities, and other roadway users. The checklist will be coordinated with the Preliminary Engineering design and submitted to NJDOT Local Aid for review. M&S will address applicable review comments and revise the checklist as necessary to obtain acceptance. Activity 3012 – Develop Landscape Architectural Design M&S will develop the Preliminary Engineering landscape and

Page 77

applicable review comments and revise the checklist as necessary to obtain acceptance. Activity 3012 – Develop Landscape Architectural Design M&S will develop the Preliminary Engineering landscape and streetscape design, including proposed street trees, plantings, planters, benches, bicycle racks, trash receptacles, bus shelters, and other proposed streetscape amenities. The design will consider existing conditions, pedestrian circulation, visibility, utilities, drainage, maintenance requirements, adjacent development, and input from the Township and project stakeholders. M&S will coordinate with the Township Forester regarding the selection of species and the locations of proposed street trees, plantings, and landscape areas and will incorporate applicable comments into the Preliminary Engineering design. M&S will develop the landscape and streetscape design to a Preliminary Engineering level sufficient to establish the proposed locations, types, materials, and general character of the improvements for 5

Page 78

incorporation into the Preliminary Roadway Plans and Construction Cost Estimate. Detailed planting plans, construction details, final quantities, and final specifications will be developed during Final Design. Activity 3030 – Prepare Horizontal & Vertical Geometry M&S will develop the preliminary horizontal and vertical geometry for the proposed streetscape improvements based upon the approved survey base mapping, existing roadway characteristics, field investigations, and the project goals. The preliminary geometry will establish the framework for the proposed roadway, sidewalk, streetscape, and pedestrian improvements while minimizing impacts to existing infrastructure, utilities, adjacent properties, and traffic operations. The preliminary geometric design will include evaluation of roadway cross sections, sidewalk alignments, curb alignments, curb ramp locations, pedestrian refuge opportunities, driveway transitions, streetscape amenity locations, and ADA-compliant pedestrian facilities. Existing roadway widths will be evaluated to determine whether lane width adjustments can improve pedestrian safety, including opportunities to provide pedestrian refuge areas at the Greenwood Avenue crossing while maintaining acceptable traffic operations. The proposed geometry will incorporate the conceptual locations of decorative crosswalks, RRFB crossings, pedestrian-scale lighting, landscaping, street furnishings, bus shelters, bicycle racks, and other streetscape elements. Proposed grading will be coordinated with existing drainage patterns to minimize impacts to adjacent properties while maintaining ADA accessibility requirements throughout the project corridor. The preliminary geometric design will provide the basis for roadway layout, utility coordination, traffic engineering, environmental documentation, drainage design, construction staging, and preparation of the preliminary construction plans. Activity 3070 – Prepare Preliminary Roadway Plans M&S will prepare Preliminary Roadway Plans illustrating the proposed improvements necessary to support environmental documentation, utility coordination, stakeholder review, and advancement into Final Design. The plans will be developed utilizing the approved survey base mapping, preliminary roadway geometry, landscape and streetscape design, environmental constraints, traffic engineering recommendations, and utility

Page 78

ill be developed utilizing the approved survey base mapping, preliminary roadway geometry, landscape and streetscape design, environmental constraints, traffic engineering recommendations, and utility coordination completed under previous activities. The Preliminary Roadway Plans will depict the conceptual layout of the proposed streetscape improvements throughout the project corridor, including roadway improvements, sidewalk reconstruction, ADA-compliant curb ramps, decorative crosswalks, pedestrian refuge opportunities, streetscape amenities, landscaping, pedestrian-scale lighting, RRFB crossings, traffic signal improvements, bus shelters, bicycle racks, benches, trash receptacles, and other proposed features. Existing and proposed right-of-way, utility facilities, drainage improvements, and environmental constraints will be incorporated as appropriate to support project development. Roadway plans will be developed in sufficient detail to evaluate constructability, utility impacts, environmental commitments, maintenance of traffic, stakeholder comments, and preliminary construction quantities. Throughout plan development, M&S will coordinate with the Township, Essex County, NJDOT, and project stakeholders to refine the proposed improvements and incorporate comments received during Preliminary Engineering. The Preliminary Roadway Plans are anticipated to include the following: • Title Sheet and Key Map • Typical Sections • Construction Plans 6

Page 79

• • • • • Traffic Control and Staging Plans Traffic Striping and Signing Plans Electrical Plans Landscape Plans Construction Details The Preliminary Roadway Plans will provide the basis for preparation of the Construction Cost Estimate and development of the Final Design scope. Activity 3085 – Prepare Preliminary Drainage Design M&S will prepare a preliminary drainage design to accommodate the proposed improvements while generally maintaining existing drainage patterns. The design will evaluate impacts to existing drainage facilities and identify localized modifications, which may include adjustment or relocation of inlets, modification of inlet types, short storm sewer extensions or replacements, and adjustment of structure elevations. Proposed grading will be coordinated with drainage and ADA requirements. Based on the anticipated improvements, the project is assumed not to constitute a Major Development under the NJDEP Stormwater Management Rules. Applicable NJDEP MS4 requirements will be incorporated into the design, including approved storm drain inlet protection measures where required. Evaluation of the existing storm drainage system for hydraulic capacity, existing flooding conditions, or existing drainage deficiencies is not included. Activity 3090 – Determine Traffic Engineering Facility Locations M&S will evaluate the existing traffic control devices, pedestrian facilities, signing, pavement markings, traffic signals, roadway lighting, and pedestrian crossing treatments throughout the project corridor to determine the preliminary locations and conceptual design of proposed traffic engineering improvements. Traffic engineering services will include collection of existing traffic data, traffic operational analyses, and conceptual design of pedestrian safety improvements. Traffic counts will be collected to support evaluation of pedestrian crossing treatments, RRFB warrants, signal timing refinements, and overall corridor operations. Data collection will occur as follows: ATR counts will be recorded for a continuous 24-hour period for 7 days in both travel directions, on a non-holiday week during the school year. ATRs will collect volume, speed and vehicle classification data, provided in 15-minute increments. ATR counts will be collected at the following nine (9) locations: • • • Pleasant Valley Way at Greenwood Avenue (3 Legs) Pleasant Valley

Page 79

vehicle classification data, provided in 15-minute increments. ATR counts will be collected at the following nine (9) locations: • • • Pleasant Valley Way at Greenwood Avenue (3 Legs) Pleasant Valley Way at Marmon Terrace (4 Legs) Pleasant Valley Way at Eagle Rock Avenue (2 legs – Eagle Rock Avenue) Intersection turning movement counts (TMCs) will be collected during one weekday (Tuesday, Wednesday or Thursday) and Saturday while school is in session in the Spring or Fall when local traffic generators have the most foot traffic. Data will be collected using MioVision count units. Vehicle and pedestrian data will be processed for the Weekday AM, Midday, PM, and Saturday peak periods. TMC counts will occur at the following locations: • • • Pleasant Valley Way at Greenwood Avenue Pleasant Valley Way at Marmon Terrace Pleasant Valley Way at Eagle Rock Avenue 7

Page 80

Traffic analyses will be performed utilizing Synchro traffic engineering software to evaluate existing and future operating conditions associated with the proposed improvements. Future traffic analysis will consider the following peak hour periods: • • • • Weekday AM Peak Hour Weekday Midday Peak Hour Weekday PM Peak Hour Saturday Peak Hour Each time period will be analyzed under the following conditions: • • • Existing Conditions Future No-Build (With No Proposed RRFB crossings and Existing Lane Geometry and Signal Timings) Future Build (With Proposed RRFBs and Signal Timing Adjustments (if needed) at Eagle Rock Avenue) Synchro model simulations (SimTraffic) will be run for one (1) one-hour period. The Synchro and simulation results will be utilized to report existing and future condition Level of Service (LOS), delay, and queues. It is anticipated that two iterations of the Synchro model may need to be evaluated to determine if the proposed traffic signal timings to a level acceptable by the County. M&S will prepare tables to summarize the results of the traffic analysis. Based upon the results of the traffic analyses and field investigations, M&S will prepare preliminary layouts for the proposed RRFB installations, traffic signal modifications, signing and striping improvements, and pedestrian crossing enhancements. Push button locations will be reviewed for MUTCD compliance. The traffic signal timing directive will be developed for weekday peak, weekday non-peak, and weekend time periods (or as needed based on the existing timing plans). A review of pedestrian clearance intervals will be conducted, and new pedestrian heads may be recommended as needed. Existing roadway geometry will be evaluated to determine opportunities to improve pedestrian safety, including potential lane width modifications and pedestrian refuge areas near the Greenwood Avenue crossing, while maintaining acceptable traffic operations. A sign inventory within the project limits will be prepared using street view webpages and field observations. Each sign will be documented based on MUTCD and NJDOT sign designations, size, condition, compliance and photographed. Non-standard signs will also be inventoried. Condition of existing pavement markings will be assessed. Preliminary Plans showing the existing and proposed layout of roadway signs and pavement markings will be developed in

Page 80

ll also be inventoried. Condition of existing pavement markings will be assessed. Preliminary Plans showing the existing and proposed layout of roadway signs and pavement markings will be developed in accordance with NJDOT Standard Details and guidance from the FHWA MUTCD. The existing lane geometry and marking types are anticipated to remain, as appropriate. Lane geometry modifications will be assessed at the Greenwood Ave intersection with the goal of gaining enough space for a center raised median to act as a pedestrian refuge area. This would result in the travel lanes in each direction being shifted toward the outside curb in each direction. Preliminary lighting design will include evaluation of existing lighting at each of the above-mentioned intersections, conceptual pedestrian-scale decorative lighting, preliminary lighting layouts, lighting warrant evaluations, and coordination with PSE&G regarding proposed lighting infrastructure. Preliminary photometric analyses and lighting calculations will be performed using Visual Lighting Design 8

Page 81

Software, as appropriate, to establish conceptual fixture locations and spacing consistent with NJDOT requirements. Traffic engineering recommendations developed during this activity will be incorporated into the Preliminary Roadway Plans and Construction Cost Estimate. Assumptions: • • • • • • • • • • Trip generation or volume distribution for future developments will not be performed. No Traffic Control will be required to perform the set-up or takedown of the count equipment. A Traffic Impact Report is not required. No temporary signal design will be required. No geotechnical borings, investigations and reporting will be performed under PE at new traffic signal locations. It is assumed geotechnical activities for signal pole foundations will be performed in FD. Volume diagrams will not be prepared. Raw data sheets will be used for the analysis/warrants. Business driveway traffic data will not be collected. No signal operations or equipment modifications are proposed at Eagle Rock Ave except for potential timing refinements based on current traffic conditions, and installing microwave pedestrian detection devices. A County signal plan may be used as the go-by if directed by the Township. M&S will coordinate with NJDOT/County to determine preferred luminaire type, manufacturer, and model number. Activity 3130 – Update Preliminary Detour and Construction Staging Plans M&S will develop preliminary construction staging and maintenance of traffic concepts to facilitate construction while maintaining safe and efficient access for motorists, pedestrians, transit users, emergency responders, businesses, and adjacent property owners. Construction staging concepts will evaluate the sequence of proposed improvements, pedestrian detours, temporary sidewalk accommodations, maintenance of access to commercial properties and residences, coordination with utility construction, and opportunities to minimize traffic disruptions throughout construction. The preliminary staging concepts will identify anticipated construction phases, temporary traffic control requirements, business driveway access needs, and maintenance of pedestrian accessibility during construction. Potential impacts to bus stops, intersections, and pedestrian crossings will also be evaluated. Construction staging assumptions developed during this activity will be reflected in the Preliminary Roadway Plans