NOW THEREFORE BE IT RESOLVED, by the Township Council of the Township of West Orange that the Mayor and Clerk are authorized to execute the attached Federal Aid Agreement, Agreement No. 2026-DT-DLA-521; and BE IT FURTHER RESOLVED, that the Clerk is hereby directed to return three (3) original signed and sealed copies of the attached agreement along with three (3) signed/sealed Resolutions, including the signed/sealed certification statement, for execution by the Department of Transportation; and BE IT FURTHER RESOLVED that the NJDOT will receive an initial billing (payment voucher) from the Township for the design project no later than 3 months after the award of the design contract, and will receive subsequent billings on a monthly basis, but no later than 3 months thereafter, in accordance with the terms of the agreement. Attest and Affix Seal: _________________________ Karen J. Carnevale, R.M.C., Municipal Clerk Adopted: October 27, 2026 ___________________________ Susan Scarpa, Council President

Page 70

TABLE OF CONTENTS PRELIMINARY ENGINEERING SCOPE AND COST PROPOSAL for Pleasantdale Streetscape Project Pleasant Valley Way (from 250 Feet South of Greenwood Avenue to Kenz Terrace) NJDOT Transportation Alternatives Set-Aside Program 2025 Located in Township of West Orange Essex County, New Jersey Prepared by September 3, 2026

Page 71

TABLE OF CONTENTS I. PRELIMINARY ENGINEERING SCOPE OF WORK Activity ID Activity Name Utility Engineering 3035 Prepare Utility Base Plans 3045 Send Utility Verification Request Letter 3055 Identify and Analyze Utility Risks 3080 Conduct Subsurface Utility Engineering 3985 Update Utility Risk Assessment Plan Survey & Base Mapping 3015 Prepare Control Survey Report 3020 Conduct Topographic Survey 3025 Prepare Base Maps Engineering Design 3006 Prepare & Submit PE Complete Streets Checklist 3012 Develop Landscape Architectural Design 3030 Prepare Horizontal & Vertical Geometry 3070 Prepare Preliminary Roadway Plans 3085 Prepare Preliminary Drainage Design 3090 Determine Traffic Engineering Facility Locations 3130 Update Preliminary Detour and Construction Staging Plans 3135 Prepare Construction Cost Estimate Environmental Studies & Public Involvement 3300 Initiate Cultural Resources (Section 106) Process 3305 Conduct Cultural Resources Survey 3310 Prepare Cultural Resources Survey Report 3320 Address Comments on Cultural Resources Survey Report 3765 Conduct Ecology Study 3840 Conduct Hazardous Waste Study 3865 Hold Public Information Center 3874 Execute PE Public Involvement Action Plan (PIAP) 3890 Prepare Certified Categorical Exclusion (CCE) Document Preliminary Engineering Documentation 3160 Prepare Draft Preliminary Engineering Report 3165 Finalize Project Plan 3185 Develop Final Design Public Involvement Action Plan II. COST PROPOSAL III. SUB CONSULTANT PROPOSALS Page 2 2 3 3 3 4 4 5 5 5 6 6 7 7 9 9 10 10 10 10 11 11 11 11 12 12 12 12

Page 73

292-26 TOWNSHIP OF WEST ORANGE NJDOT Transportation Alternatives Set-Aside Program 2025 Pleasantdale Streetscape Project - Pleasant Valley Way (from 250 Feet South of Greenwood Avenue to Kenz Terrace) Township of West Orange, Essex County, New Jersey September 3, 2026 PRELIMINARY ENGINEERING PROJECT UNDERSTANDING & ASSUMPTIONS Malick & Scherer, PC (M&S) will provide Preliminary Engineering (PE) services for the Pleasantdale Streetscape Project in the Township of West Orange, Essex County, New Jersey. The project is being advanced under the NJDOT Transportation Alternatives (TA) Set-Aside Design Assistance Program and will follow the NJDOT Capital Project Delivery Process and June 2026 Preliminary Engineering Activity Descriptions. The proposed improvements extend along Pleasant Valley Way (County Route 636) from approximately 250 feet south of Greenwood Avenue to Kenz Terrace. The project will improve pedestrian safety, accessibility, connectivity, and the visual character of the Pleasantdale commercial corridor. Proposed improvements generally include ADA-compliant pedestrian facilities, decorative crosswalks, RRFBs, pedestrian-scale decorative lighting, landscaping, streetscape furnishings and amenities, bus shelters, and related roadway and pedestrian improvements. Preliminary Engineering will also evaluate potential roadway striping modifications, pedestrian refuge opportunities, and traffic signal improvements. M&S will coordinate the Preliminary Engineering design with the Township, Essex County, NJDOT Local Aid, NJDOT Bureau of Environmental Program Resources (BEPR), utility owners, regulatory agencies, and project stakeholders. Preliminary Engineering will include the technical studies, environmental documentation, preliminary construction plans, cost estimate, utility coordination, and public/stakeholder involvement necessary to establish an approved design for advancement into Final Design. Unless otherwise noted within individual activity descriptions, this proposal is based upon the following assumptions: • PE services will be performed in accordance with the June 2026 NJDOT Preliminary Engineering Activity Descriptions and current NJDOT Local Aid procedures. Final Design and Construction Engineering services are not included. • Available survey mapping, record plans, GIS information, utility records, and right-of-way information will be

Page 73

al Aid procedures. Final Design and Construction Engineering services are not included. • Available survey mapping, record plans, GIS information, utility records, and right-of-way information will be obtained from the Township, Essex County, utility owners, and other available sources to supplement field investigations. • NJDOT BEPR will administer the Certified Categorical Exclusion process. M&S will prepare the technical studies and documentation identified herein to support the environmental document. Cultural resource investigations will be performed by Richard Grubb & Associates (RGA) under subcontract to M&S. • Public involvement will include one (1) Public Information Center, one (1) meeting with the Downtown West Orange Alliance, two (2) meetings with the Township Historic Preservation Commission, and coordination with the Pedestrian Safety Advisory Board, Township, and Essex County, as necessary. 1

Page 74

• • • • • The Township will review and approve property-owner notification/right-of-entry letters prior to field survey activities requiring access adjacent to private property. Utility impacts will be evaluated based on verified existing facilities and the preliminary design. Up to three (3) minor utility relocations are assumed, including preliminary coordination with affected utility owners. Adjustments to existing utility structures and appurtenances necessary to accommodate proposed improvements are also anticipated. Detailed utility relocation design, final relocation plans and agreements, and construction-phase utility coordination are not included in PE. Targeted subsurface utility engineering (SUE) consisting of up to five (5) test holes is included as described under Activity 3080. Right-of-way acquisition is not anticipated. Species-specific threatened and endangered species surveys, archaeological investigations, mitigation design, geotechnical investigations, and other services not specifically identified herein are not included unless subsequently authorized. Township Progress Reviews M&S will provide progress plans, exhibits, and other applicable design materials to the Township for review at key milestones during Preliminary Engineering, including the following: • following completion of the Survey and Base Mapping, supplemented with applicable SUE information as it becomes available • following completion of Activity 3130 – Update preliminary Detour and Construction Staging Plans and prior to preparation of the construction cost estimate under Activity 3135 • prior to the Public Information Center under Activity 3865. Materials for the Public Information Center will be provided to the Township a minimum of three (3) weeks prior to the meeting to allow for review and comment. SCOPE OF WORK UTILITY ENGINEERING Activity 3035 – Prepare Utility Base Plans M&S will review base mapping and observed surface utility features within and adjacent to the project limits to establish the base plans for the utility verification request. The plans will be developed from the project survey, field-observed features, and any applicable mark-outs observed in the field. This task also includes a field visit to create a photo log to verify changes to the existing utilities. Activity 3045 – Send Utility Verification Request Letter M&S will prepare and

Page 74

ved in the field. This task also includes a field visit to create a photo log to verify changes to the existing utilities. Activity 3045 – Send Utility Verification Request Letter M&S will prepare and distribute Utility Verification Request Letters and Utility Base Plans to seven (7) utility owners licensed to operate within the project limits. Utility owners will be requested to verify existing facilities; provide available record or as-built information; identify abandoned facilities, planned improvements, easements, and known operational constraints; and provide corrections or supplemental information, as applicable. M&S will review utility-owner responses and coordinate with the utility owners to clarify discrepancies between available records, field-observed facilities, project survey information, and utility-owner information to the extent practical during Preliminary Engineering. Verified information will be incorporated into the Utility Base Plans, as appropriate. 2

Page 75

The Utility Base Plans will be used to identify potential conflicts between existing utilities and the proposed roadway, sidewalk, ADA, drainage, traffic, lighting, landscape, and streetscape improvements. Potential conflicts will be advanced for utility verification and coordination under subsequent activities. Where the precise horizontal and vertical locations of underground utilities cannot be established from available information and additional information is necessary to evaluate a specific potential conflict, targeted SUE investigations may be performed under Activity 3080. Detailed utility relocation design is not included in this activity. Activity 3055 – Identify and Analyze Utility Risks M&S will review the preliminary design and verified utility information to identify potential utility conflicts and evaluate risks to project cost, schedule, constructability, and design. M&S will coordinate with affected utility owners to determine whether conflicts can be avoided or minimized through design refinements and, where necessary, establish preliminary utility accommodation requirements for advancement during Final Design. For purposes of this proposal, up to three (3) utility relocations and up to three (3) utilities with surface features requiring adjustment to accommodate proposed grades and improvements are assumed. M&S will perform preliminary coordination with the affected utility owners to establish the anticipated relocation requirements, including applicable clearances, access and operational constraints, sequencing considerations, and anticipated lead times. M&S will also identify existing manholes, valve boxes, handholes, utility castings, and similar facilities requiring adjustment to accommodate proposed improvements and grades. M&S Utility Team will assist the Lighting Design Team in coordinating with PSE&G regarding the conceptual pedestrian-scale decorative lighting layout and preliminary service requirements. PSE&G is anticipated to develop the detailed lighting layout based on conceptual fixture locations established during Preliminary Engineering. It is assumed that five (5) utility coordination meetings will be required for the three (3) utilities with potential conflicts, consisting of three (3) meetings with PSE&G and two (2) meetings with the other affected utilities. Unresolved utility conflicts and anticipated relocation

Page 75

hree (3) utilities with potential conflicts, consisting of three (3) meetings with PSE&G and two (2) meetings with the other affected utilities. Unresolved utility conflicts and anticipated relocation requirements will be documented for advancement during Final Design. Final utility relocation design, utility-specific construction plans and specifications, utility agreements, and incorporation of final utility relocation designs into the Contract Documents are not included in Preliminary Engineering. Activity 3080 – Conduct Subsurface Utility Engineering M&S will perform Subsurface Utility Engineering (SUE) at selected locations to verify the horizontal and vertical location of existing subsurface utilities where necessary to evaluate potential conflicts with the proposed improvements. M&S will identify and prepare a plan depicting the proposed test hole locations and coordinate the SUE investigation with a qualified SUE contractor. For purposes of this proposal, up to five (5) test holes are assumed. The SUE contractor will perform the test holes and prepare a SUE Test Hole Report documenting the results. M&S will review the results, update the existing utility mapping as appropriate, and incorporate the verified utility information. Activity 3985 - Update Utility Risk Assessment Plan M&S will prepare and update the Utility Risk Assessment Plan based on information received from the utility companies, the results of the SUE investigations performed under Activity 3080, and the advancing Preliminary Engineering design. The updated plan will be used to document and address 3

Page 76

identified utility risks and support preparation of the preliminary roadway and construction staging plans. M&S will inform the PM of any new project-specific utility risks or changes to previously identified utility risks. SURVEY & BASE MAPPING Malick & Scherer, P.C. (M&S) will perform conventional ground survey and base mapping along Pleasant Valley Way. A temporary shadow vehicle and/or local police/flagger may be required to protect the survey crew and maintain traffic. For this proposal, temporary lane interruptions, if required, are assumed to be permitted by the County and Township between 9:00 AM and 3:00 PM, Monday through Friday. Survey limits will extend along Pleasant Valley Way from 300 feet south of Greenwood Avenue to 100 feet north of Kenz Terrace, up to 10 feet beyond the existing right-of-way, and approximately 100 feet along intersecting side streets from the Pleasant Valley Way centerline. Survey will include topographic, drainage, and sanitary sewer features, including pipe sizes, materials, and invert elevations where accessible. Activity 3015 – Prepare Control Survey Report M&S will prepare a Primary Survey Report in accordance with applicable sections of the Procedures Manual and Article 44 of the Consultant Contract, for submission to the County/Township if required. The report will document monuments and benchmarks used and established; NJ State Plane Coordinate System, NAD 1983 and NAVD 1988 references; survey equipment and calibration; survey procedures; software used to process and adjust observations; and data computations and results. Activity 3020 – Conduct Topographic Survey M&S will perform conventional field topographic survey and develop English-unit digital base mapping compatible with AutoCAD Civil 3D. Survey data will be processed into a Digital Terrain Model (DTM), and an ASCII point file will be prepared. Mobilization and Document Research M&S will mobilize a field crew and request relevant existing plans and documents from the County/Township. Permit and MPT Coordination M&S will coordinate roadway permit requirements and Maintenance and Protection of Traffic (MPT) services and/or local police for temporary lane interruptions. Up to three days of MPT/Police are included, as most survey work is anticipated behind the curb. Primary Control Horizontal and vertical control will be established within the project limits